19 Sept 2005Flavio Dal Corso INFN-Pd1 MiniCrates Status Components Status (BTIM, TRB, CCB, SB) MC production: quantity and rate, past and future Production Schedule for the near future
2
19 Sept 2005Flavio Dal Corso INFN-Pd2 BTIM Production completed (12500 modules). Production of spare modules (≈600) still in progress. CCB & SB Production completed (250 boards + 40 spares)
3
19 Sept 2005Flavio Dal Corso INFN-Pd3 TRB Produced up to now: –669 TRB Φ –333 TRB θ –65 TRB Φ32 Buffers: (≈17 MC) –82 TRB Φ –157 TRB θ –30 TRB Φ32 Problems: –Production stopped during August –Many boards (≈15%) with faults (mostly detected during pre-test). –Buffers limited by shortage of TRB Φ.
4
19 Sept 2005Flavio Dal Corso INFN-Pd4 MC produced up to now
5
19 Sept 2005Flavio Dal Corso INFN-Pd5 MC produced: details 110 MC delivered –71 installed –9 for the September installation (100% of the chambers to be installed) –21 for the November-December installation (67%) –9 for further installations.
6
19 Sept 2005Flavio Dal Corso INFN-Pd6 forecast for the future Note: n. of TRB expressed as n. of equivalent MC. TRB production (and manpower) are the limiting factors.
7
19 Sept 2005Flavio Dal Corso INFN-Pd7 Production Schedule MC to be moved to Bologna MC to be received from CIEMAT