ME 414W/415W Project Management Project Management
2
ME 414W/415W Project Management Project Management DILBERT’S BOSS
3
ME 414W/415W Project Management A Balancing Act u Deliverables u Cost u Quality
4
ME 414W/415W Project Management Learning How u ME 414W/415W - http://www.me.psu.edu/sommer/me415/ http://www.me.psu.edu/sommer/me415/ u MBA u Industrial training programs
5
ME 414W/415W Project Management Planning u Technical u Time u Resources –Personnel –Equipment and Facilities –Budget
6
ME 414W/415W Project Management Benefits of Planning u Framework for communication –Clients and coworkers u Allocate resources –Personnel, equipment and facilities, budget u Benchmark to measure progress
7
ME 414W/415W Project Management Planning - Fundamentals u Establish Performance Standards at the BEGINNING u Use Decision Trees/Matrices, QFD, Taguchi Methods u Assure Performance Standards as Project Progresses u Verify Final Performance Against Standards u NO SUPRISES!
8
ME 414W/415W Project Management Time Planning u Identify TASKS u Estimate DURATION of Tasks u Establish PRECEDENCE of Tasks u Record MILESTONES (Performance and Dated) u Plan Start and Finish DATES for Tasks
9
ME 414W/415W Project Management Models u Gantt Charts - Bar Charts u CPM/PERT - Network u Control Charts - Planned versus Actual u http://www.mne.psu.edu/me415/resources/doc s/gantt chart.pdf http://www.mne.psu.edu/me415/resources/doc s/gantt chart.pdf
10
ME 414W/415W Project Management Example Gantt Chart
11
ME 414W/415W Project Management Gantt Chart u Tabulate Project Tasks –Title and ID Number for Each Task –Estimate Duration of Each Task –Estimate Resource Requirements for Each Task (May Need Dummy Tasks for Critical Resources) u Identify Prerequisite Tasks for Each Task u Layout Bar Chart with One Bar per Task based on Time u Add Dated Milestones
12
ME 414W/415W Project Management Example Gantt Chart
13
ME 414W/415W Project Management Gantt Chart - Pros and Cons u Strengths –See Status of Each Task at Any Point in Time –See Overlapping and Parallel Tasks u Weaknesses –Unable to Tell if the Entire Project is on Time for Highly Dependent Projects –Difficult to Show Critical Path
14
ME 414W/415W Project Management CPM/PERT u Critical Path Method u Program Evaluation and Review Technique
15
ME 414W/415W Project Management Example PERT Chart
16
ME 414W/415W Project Management CPM/PERT u Tabulate Project Tasks –Title and ID Number for Each Task –Estimate Duration for Each Task D=(O+4M+P)/6 v O = Optimistic, M = Most Likely, P = Pessimistic –Estimate Resource Requirements for Each Task (May Need Dummy Tasks for Critical Resources) u Identify Prerequisite Tasks for Each Task u Layout Flowchart of Tasks Based on Dependencies NOT Time u Indicate Performance Milestones on Flowchart
17
ME 414W/415W Project Management CPM/PERT - continued u Calculate Earliest Completion Time and Latest Completion Time –Beginning at start of project, ECT for task = ECT for preceding node + duration –Beginning at end of project, LCT for task = LCT for following node - duration u Calculate Slack Time for Each Task –Slack for Task= ECT - LCT u Determine Critical Path –Longest Time Path –Zero Slack
18
ME 414W/415W Project Management Example PERT Chart
19
ME 414W/415W Project Management CPM/PERT – Pros and Cons u Strengths –Shows Task Dependencies –Predicts Critical Path –Identifies Slack Time for Resources u Weaknesses –Assumes Subsequent Task Starts Immediately After Prerequisite Concludes –Difficult to Visualize Timing
20
ME 414W/415W Project Management Control Charts u Quality –Statistical Process Control u Schedule –Gantt, Milestone, PERT u Budget –Commitment –Performance –Cash Flow
21
ME 414W/415W Project Management Budget Control Chart
22
ME 414W/415W Project Management Resource Planning u LINK TO TIME PLANNING u Personnel –In-House –Vendors and Subcontractors –Circle-dot chart
23
ME 414W/415W Project Management Circle-dot Chart
24
ME 414W/415W Project Management Resource Planning - continued u Equipment and Facilities –May Need to Add Dummy Tasks for Critical Resources –Downtime for Expected Maintenance or Failure u Budget –Often Not Under Direct Control of Project Team –Contingency Funds –Variable Value of Money v Inflation v International Currency
25
ME 414W/415W Project Management Project Management is …
26
ME 414W/415W Project Management … a Balancing Act