1 New Generation Commissioning Emal Latifzai Operations Support Engineer New Generation Information Forum ERCOT Public November 4, 2014
2
2 Commissioning plan A communication tool which helps ERCOT understand some high level plant commissioning information : Maximum generation and load capacities at plant Schedule in tabular format detailing estimated dates for : Energization of POI station (if new) Initiation of parts 1, 2, and 3 for each generator at station Post-synchronization, estimated day by day online generation capability until fully online Availability of reactive devices Availability of AVR, PFR, PSS, etc. Availability of plant control system (i.e. Wind Control System) Testing of leading/lagging reactive capability, PFR, etc. required for part 3 approval Response times for plant shutdown or isolation from grid (in controlled as well as emergency situations) Other information MP believes might be useful This is not a public document
3
3 Part 1 - Energization Procedure to backfeed from grid and soak the transformer All telemetry associated with transmission level equipment at xfmr and above must be mapped and coming in with “Good” quality status and reasonable values ERCOT business process assumes Part 1 checklist is submitted at least business 7 days before intended date of energization More time allows ERCOT to help all parties involved in a timely manner
4
4 Part 1 - Energization Outages affecting backfeed should be coordinated among QSE, TO, and ERCOT ERCOT will provide feedback after checklist is submitted ERCOT will approve backfeed 1 business day before its planned date if all requirements met RE/QSE will receive approval from their ERCOT account manager
5
5 Part 2 - Synchronization Procedure to synchronize to grid and begin bringing the unit(s) online All generation telemetry must be mapped and coming in with “Good” quality status and reasonable values and all transmission level telemetry must still be in good condition ERCOT business process assumes Part 2 checklist is submitted at least 7 business days before intended date of power injection into grid ERCOT will perform studies to determine if the grid can support the new generation
6
6 Part 2 - Synchronization Outages affecting synchronization should be coordinated among QSE, TO, and ERCOT ERCOT will provide feedback after checklist is submitted ERCOT will approve synchronization 1 business day before its planned date if all requirements met RE/QSE will receive approval from their ERCOT account manager
7
7 Part 3 – Prepare for Commercial Operation Procedure to verify all resource testing completed Leading/lagging reactive capability, PFR, etc. Tests are coordinated with ERCOT Operations Analysis group ERCOT business process assumes Part 3 checklist is submitted at least 7 business days before intended date of receiving approval RE/QSE must have received ERCOT notice that all tests have been successfully passed before submitting checklist RE/QSE will receive approval from their ERCOT account manager