Download presentation
Presentation is loading. Please wait.
Published bySara Statton Modified over 9 years ago
1
WAO 20141 Travis Shrey RHIC Machine Specialist Collider-Accelerator Dept Brookhaven National Laboratory 10/30/2014
2
Facility/Personnel highlights Traditional StartUp Period New StartUp Period ‘Case Study’ provides a test for the new method 10/30/2014WAO 20142
3
‘Summer’ shutdown – June through December ~22 weeks of cryogenic operation ($$$) 3-4 days of cooldown to 4K StartUp Power supply checkout during day & evening shift, beam work during midnight shift only for the first 4-5 days 24 hour beam work from that point forward until Physics is declared Experimental physics operations 10/30/2014WAO 20143
4
10/30/2014WAO 20144 Injectors are set up for beam ~4 weeks prior to RHIC cryogenic operation
5
The StartUp period for RHIC has become a well-defined list of tasks, even with constant recommissioning Some tasks require expert-level knowledge The Operations group now has sufficient experience to be able to perform the balance WAO 2014510/30/2014
6
WAO 20146
7
Operations Group 6 teams of rotating shifts 1 Operations Coordinator (5-15 years experience) 2 Operators (0-10 years experience) 2* RHIC Machine Specialists (17,19 years experience) Responsible for hourly management of the accelerator complex (Booster, AGS, RHIC) WAO 2014710/30/2014
8
Accelerator Physics group Physicists with expert level knowledge of one or more accelerator systems (RHIC & Injectors) Some the original designers of RHIC systems Responsible for developing and commissioning machine upgrades WAO 2014810/30/2014
9
RHIC Run Coordinator Chosen from Accelerator Physics* group Experience with Operations ranging from none to extensive Experience with RHIC ranging from none to extensive Responsible for day to day management of the run and the meeting of Physics goals Often separate Run Coordinators for Protons and Ions if run during the same Fiscal Year WAO 2014910/30/2014
10
Run Coordinator develops StartUp plan Run Coordinator holds daily meeting to report progress Run Coordinator maintains ‘Plan of the Day’ to deliver shift-by-shift instructions Operations staff operates Injector accelerators RHIC Accelerator Physics shift leader operates RHIC to meet shift’s Plan of the Day goals WAO 20141010/30/2014
11
Given the amount of variation in the experience level of the Run Coordinator with regards to Operations or RHIC itself, there can be an extremely steep learning curve The Run Coordinator runs out of hours in the day (especially when needed to complete AP work for the Run) When conflicts arise shift leader requires guidance from Run Coordinator, either in person or via phone 24 hours a day Experienced RHIC AP personnel don’t want to be on shift Less experienced RHIC AP personnel know less about operating RHIC than many of the Operations crews WAO 20141110/30/2014
12
RHIC Machine Specialists develop StartUp Plan Run Coordinator holds daily meeting to report progress RHIC Machine Specialist maintain ‘Plan of the Day’ to deliver shift-by-shift instructions to Operations crews Operations staff operates Injectors and RHIC Newer RHIC AP people on shift to provide expertise and learn about Operations RHIC AP staff available for assistance by phone WAO 20141210/30/2014
13
Planning by RHIC Machine Specialists provides for the most realistic estimates for timing of StartUp tasks – ‘personality management’ based on experience Allows Run Coordinator a much less intensive role during the first ~10 days of running, ease into their role while still being involved running the daily meeting RHIC Machine Specialists share role of leadership and are able to provide 24 hour coverage during the StartUp period without undue hardship Experienced AP personnel are off shift Newer AP personnel gain experience Operations shift crews empowered to make planning decisions when conflicts arise Operators can make great strides in knowledge during StartUp. Watching ≠ Doing!! WAO 20141310/30/2014
14
WAO 201414 Boxed area indicates the new StartUp model in use (effectively for runs 11.5 and 12, officially for runs 13 & 14) 10/30/2014 W. Fischer, BNL
15
Run Coordinator notified of run 6/12 (always had been a very small possibility) Setup Plan created 6/13. Plan details 3 day’s worth of work starting 6/16 and ending midnight 6/18 6/16 mode switch begins (12 hour maintenance period for some physical modifications to power supplies) Store for experimenter setup in place at 2200 6/18 WAO 20141510/30/2014
16
WAO 201416
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.