Mine Construction
2
Start of Barge Landing area. A trailer, excavator and generator. Early Barge Landing June 2007 with one trailer to start construction.
3
2012 Developed Area Fuel Tank Early Barge Landing July 2007 with projected development outline
4
Early Barge Landing August 2007 with a construction camp Fuel Tank 2012 Developed Area
5
Barge Landing under Construction in 2007 note the significant fill material placed in the area of tree clearing and topsoil removal Fuel Tank Construction Offices Construction Camp
6
Barge Landing – Container storage area raised 3m above river level with compacted fill Fuel Tank Construction Offices Construction Camp Container storage area
7
Barge Landing (winter 2009) – Construction Camp & Supplies Ready. Large equipment fleet used in the construction.
8
Helicopter dropping in first construction camp units at airstrip