Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: W/S Construction Substantial Completion Date:August, 2010 Contract Sum:$9,920,194 Change Orders: $36,900 (#1--Demo) Current Phase:1 (On Schedule) Estimated Completion:Demo – 100% June 2009
2
Arlington Elementary – Renovation Rendering of Final Façade June 2009
3
Arlington Elementary – Renovation Work Completed in Last 30 Days: WS-Construction has mobilized. Site preparation has begun, including erosion control adding engineered fill, and preliminary grading. Structural shoring of existing walls has also begun. Current Work Effort (June): Selective demolition, additional site work and the laying out of the new building footprint. June 2009
4
Arlington Elementary – Renovation WS Construction Trailer Site Prep / Erosion Control June 2009 Preliminary Grading