Download presentation
Published byTerry Spruce Modified over 9 years ago
1
July 2007 egeplast Werner Strumann GmbH & Co. KG Robert-Bosch-Straße 7 48268 Greven
2
The new factory Commissioned: January 2001 Size of grounds: 150,000 m²
Production facilities: approx. 18,000 m² Extrusion hall: m wide, 150 m long Extrusion lines: 14 Dimensional range: DA 7 – 1200 mm Pipe raw materials: PE and PP Rated capacity/year: tonnes
3
Pipe Installation back then….
and today! Strong growth in non-conventional installation techniques over the past 20 years Quelle: Fiedler, Göttinger AWT 2006 Open Installation only 10% pipe material Civil works up to 90% Up to 50% cost for surface restoration Trenchless by Relining Quelle: Gelsenwasser Quelle: A. Hügging in 3R international (2000) Non-conventional pipelaying saves money – however, requirements towards pipe material are higher!
4
Development of PE-HD as a Material for Pipes
PE100 RC PE 100 3rd Generation Perfomance PE 80 2nd Generation PE 63 1st Generation 1970 1980 1990 2000 Year
5
Polyethylene : Molecular Structure
HDPE: filamentary macromolecule with a few branches Polyethylene molecule crystalline structure branches
6
Influence on Materials Properties
PE-molecule Property short molecules without branches long molecules with branches Structure high stiffness high strength crystalline high ductility high crack resistance high resistance against scratches and notches amorphous crystalline amorphous
7
Increase of Resistance against Slow Crack Growth SCG by Comonomer Branches
without Comonomer with Comonomer
8
Today: 3rd Generation PE
1. Generation: monomodale - without comonomer 2. Generation: monomodale - with comonomer 3. Generation: bimodale - with comonomer Chain length Content [%] monomodale bimodale Increasing the crack resistance: Comonomer branch in longest macromolecules By bimodal distribution strength and ductility were equally increased
9
The Right Pipe System for every Application
Trench Installation in Sand Bed egelen® Trench Installation without Sand Bed egeplast 90 10® Trenchless Installation/ Renewal egeplast SLM® 2.0
10
The Right Pipe System for every Application
egeplast SLM® 2.0DCT Detection of embedded pipelines and checking the integrity Protecting drinking water in Contaminated Soil egeplast SLA® 2.0 Environmental safety through permanent leakage monitoring egeplast 3L/SLA®
11
Trench Installation without Sand bed
Sand bedding unnecessary thanks to modern materials • Use of excavated soil allows quicker and more cost-effective installation. • In Rural regions modern techniques like ploughing and milling decrease the contracting time • Additional point loads are exert on the pipe during its live time by stones • Pipe system need to be stable against these point loads, so that these do not result in stress-induced cracking Scoring Point load Ploughing Milling Special Quality Control of the slow crack properties guarantees the long lifetime of these pipes !
12
PE 100 RCplus Resistance to Slow Crack Growth Testing
Full Notch Creep-Test FNCT (ISO/DIS 16770) Point Load Test acc. Dr. Hessel Notch-Test (DIN EN ISO 13479) > 5000 h acc. KRV Richtlinie R
13
Resistance to Crack Correlation between FNCT and Pipe Pressure Test
PE 100 RCplus (Resistence to Crack) > 3300 h DVGW GW 323 „Berstlining“ PE 100+ PE 100 PE 80 PE 63 Source: HESSEL Ingenieurtechnik
14
Materials in Comparison
15
PE 100 RC in accordance with KRV Standard R 14.6.36
Testing time Notched Pipe Test according to DIN EN ISO 13479: Material Temperature Pressure Time [°C] [bar] [h] PE 100 RC ,2 > 5000 Additionally egeplast PE 100 RCplus: Point Load Test as a type test: > 8760 h at 80°C, Arkopal N-100, s=4,0 N/mm² Testing time FNCT (ISO/DIS ) each lot: > 3300 h bei 80°C, Arkopal N-100, s=4,0 N/mm² Acc. Dr. Hessel in 3R international 4/2001 und 6/2001
16
Trench Installation without Sand bed Reducing Costs without forfeiting safety
The ideal combination: Modern crack-resistant Materials and intelligent pipe structure egeplast 90 10® A 10% coloured outer layer is isometrically integrated to allow an exact evaluation of the pipe surface pursuant to DVS, DVGW, KRV and EN standards. Max. 10% damaging are permissible. Pressure pipe manufactured from PE 100 RC plus (Resistance to Crack) 90 % of the standard wall thickness PE 100 RC black 10 % of the standard wall thickness PE 100 RC coloured =100 % safety
17
Signing out the Scratch Depth
One Layer Pipe Control of Scratch Depth is impossible! egeplast 90 10® Scratch Depth is Controllable!
18
Geometry of the pipe wall
Trench Installation without Sand Bed 5.740 m DA 315 x 18,7 mm; SDR 17 660 m DA 315 x 28,6 mm; SDR 11 3.060 m DA 250 x 14,8 mm; SDR 17 Geometry of the pipe wall Installation without Sand Bed is possible
19
Welding of two layer pipe: Standard
Butt Welding Electro Fusion Coupler Different layers are welded together, the welding process follows typical standards like DVS 2207, part 1.
20
Preoperational Cleaning of a new Pipeline
Cutting the but weld Cutting Process Preoperational Cleaning of a new Pipeline
21
Trenchless Installation and Renovation Techniques
Pipe is pulled through undefined bore hole (black box) Relining Horizontal Drilling Pipe Bersting
22
egeplast 90 10® SLM® 2.0 Pressure pipe manufactured from PE 100 RC (Resistance to Crack) According DVGW standard GW 335 A2 Pressure pipe manufactured from PE 100 RC (Resistance to Crack) according DVGW standard GW 335 A2 Isometrically integrated, 10% coloured outer layer, to allow an exact scratch evaluation Additional extremely robust protective coating made of reinforced polypropylene
23
Unprotected PE-Pipe vs. Coated Pipe after No-Dig Technology
[mm] 1 2 3 Unprotected PE Pipe [mm] 1 egeplast SLM® 2.0 Coextruded Multilayer Pipe e.g. egeplast 9010® No-Dig Technology Scratches penetrate polyethylene pipes 3 times deeper than coating No Damages under the coating
24
Protective Function Safety Welding Conditions after No-Dig Technologies
25
Projects: Relining Relining of Cast Iron Pipe 200m SLM® x 25,4mm, PN 10
26
Berstlining for renovation of cast iron pipes
Projects: Berstlining Berstlining for renovation of cast iron pipes Bore hole for tapping valve Bersting of the cast iron pipe Pulling rod GG-Pipe (Gas)
27
Projects: Drilling Drilling through Karst rock in Austria SLM® 2.0 OD 180mm SDR 7.4 sewage pipe with an overall length of 516m Drilling length about 400m
28
Projects Berstlining of a cast iron pipe House connections
29
Thank you for your attention!
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.