BEPCII RF POWER SYSTEM RF group, IHEP
2
2004 Sep ~ 2005. April 1.The 1 st transmitter had finished installing,commissioning and SAT (Site Acceptance Test). 2.The 1 st circulator had finished installing and commissioning. 3.The equipments and components for the 2 nd transmitter had been prepared in IHEP.
3
2005.July ~ 2005. Nov. East Hall reconstruction for 2 nd. Power Sys Setting up Cooling Water, Cooling Air and Electricity
4
2005.7 th. Nov ~ 2006. 23th. Jan Installation and commissioning in East Hall for the 2 nd transmitter.
5
Positioning
6
Installation
7
Commissioning
8
Some problems 1. Some certain signals always tripped because of something wrong in the isolation transformer. We replaced the isolation transformer with a new one. 2. During 50 hours 250kW high power test, after first 24 hours, we had a electricity shut-down. Transmitter was OK and restarted very soon.
9
Satisfied Result Frequency : 499.8MHz @Bandwidth : +/- 1MHz Pout≥ 250kW η≥60% RF Gain : Gain ≥ 40dB @ 250kW Harmonic: ( 499.8MHz×2 ): -39.66dB ( 499.8MHz×3 ): -61.17dB At 250kW, output power is stabling between - 0.001dB and 0.002dB , phase stabling between - 0.2 0 and 0.02 0 。
10
Rf output versus Gain
11
Rf output versus phase
12
Frequency versus Bandwidth
13
50 Hours 250kW on load Test Commission Succeed
14
2006.17 th. April ~2006.20 th. April The 2 nd Circulator installing and commissioning.
15
Commissioning
16
The result diagram: Return Loss vs. Sliding short position
17
2006 1 rd. Mar ~ 2006 25 th Mar West hall wave guide installed and loaded 150kW for 1 month to be prepared for Coupler high power test
18
2006 26 th. Mar ~ 2006 25 th. Apr 1.Transmitter EPICS ICS extension 2.Interlock system for SCC 3.Operation mode for m1: Operation m2: Coupler high power test m3: SCC high power test
19
Test Plan 29 th. April 2006 conditioning in Mode2 10 th. May 2006 conditioning in Mode3 June 2006 moving into tunnel and test again
20
Coupler high power test Signals for mode2 has been connected to IOC computer and interlock system. Signals concerning water, air, temperature, arc, input power, reflected power, person safe. Ready for high power test for coupler.
21
Control station EPICS (VME, LINUX, VXWORK) FPGA interlock sys. And mode switch.
22
Signal Relays Locker All hardware signal relays here.
23
Signal list
24
Int. ARC detector ARC for coupler high power test outside Test Room
25
Int. Air for coupler Air cooling for coupler high power test
26
Int Water for coupler Water cooling for coupler Water in T Water out T Flow Pressure Conductivity
27
Int. Vac Cavity VAC. Nitrogen Shield VAC Coupler VAC
28
Int. Temp. for coupler PT100 –25C ~ 125C Window up interlock Window down interlock Doorknob interlock Doorknob up interlock Doorknob down interlock
29
Scc monitor
30
Cooling monitor
31
Interlock pannel
32