From… Maintenance Technical Advisory Guide (MTAG) Chapter 6 Dowel Bar Retrofit
2
Load Transfer Restoration Through Dowel Bar Retrofit Load Transfer Restoration Through Dowel Bar Retrofit
3
Learning Objectives 1.List benefits of load transfer restoration 2.Describe recommended materials and mixtures 3.Describe recommended construction procedures 4.List important quality control activities 5.Describe potential construction and performance problems 6.Identify associated solutions
4
3-5.4 II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting Presentation Outline
5
Mechanism of transferring wheel loads across a joint or crack Accomplished through: Mechanical devices (dowel bars) Aggregate interlock Foundation support Load transfer efficiency (LTE) Load Transfer Definition
6
Load Transfer (continued) Wheel Load Leave SlabApproach Slab 0% Load Transfer Direction of Traffic Wheel Load Leave SlabApproach Slab 100% Load Transfer Direction of Traffic
7
Causes of Poor Load Transfer Absence of load transfer devices Failed load transfer device Excessive crack/joint opening Poor pavement drainage Erodible base
8
Results of Poor Load Transfer Pumping
9
Results of Poor Load Transfer Transverse Joint Faulting
10
Results of Poor Load Transfer Corner Breaks
11
Results of Poor Load Transfer Deteriorated Mid-Panel Cracking
12
Load Transfer Restoration Installation of mechanical devices in an existing pavement to restore load transfer Definition Suitable for transverse joints or cracks
13
Temporary joint insert for sealant reservoir 65 mm (2.5 in) min. 100 mm (6 in) max. End view Mill or Saw cut Dowel bar cap (at least one side) 6 mm (0.25 in) expansion As required Full depth joint forming medium & dowel support Side view 350* mm + 5 mm (14 in + 0.2 in) T T/2 *460 mm (18 in) max. 40 mm (1.5 in) Retrofitted Dowel Bar 3-5.13
14
Load Transfer Restoration Benefits Reduced probability of pumping, faulting, and corner breaks Improved long-term rideability Increased service life
15
Relatively good condition but with: Poor load transfer Faulting between 3 and 13 mm (0.125 and 0.5 in) <10% slabs with multiple cracks Pavements expecting overlays Medium to heavy truck traffic Good Candidate Projects
16
Typical Item Codes Item CodeDescription 074017Prepare water pollution control program 074019Prepare storm water pollution prevention plan 074020Water pollution control 074042Temporary concrete washout (portable) 120090Construction area signs 120100Traffic control system 128650Portable changeable message sign 406100Dowel bar retrofit 413111Repair spalled joints 414101Seal transverse joint 420201Grind existing concrete pavement http://i80.dot.ca.gov/hq/esc/oe/awards/#item_code
17
Design, Materials & Specifications From… Maintenance Technical Advisory Guide (MTAG) Module 6-1
18
3-5.18 II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting Presentation Outline
19
Material Selection Load transfer devices Retrofitted dowel bars Other devices Repair (filler) materials Portland cement concrete (PCC) Rapid-setting proprietary materials Polymer concretes Epoxy-resin adhesives
20
Load-Transfer Devices Dowel Bars
21
3.7 m (12 ft) 610 mm (24 in) 305 mm (12 in) 3 to 5 dowels @305 mm (12 in) Truck Lane AC Shoulder 457 mm (18 in) 457 mm (18 in) PCC Shoulder Truck Lane Dowel Design and Layout 3 to 5 dowels @305 mm (12 in) 38-mm (1.5-in) dia. dowels
22
Repair Material Requirements Little or no shrinkage Good ultimate strength Thermal compatibility Freeze-thaw durability Good bond to existing concrete
23
Partial-depth repair materials work well Required time until opening to traffic Laboratory testing Selecting Repair Materials
24
Construction and Inspection From… Maintenance Technical Advisory Guide (MTAG) Module 6-2
25
3-5.25 II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting Presentation Outline
26
Construction 1.Slot creation 2.Slot preparation 3.Dowel bar placement 4.Repair material placement 5.Material consolidation and finishing
27
Slot Creation Parallel to centerline Diamond saw cutters vs. modified milling machines Slot dimensions Length: 1 m (3 ft) on surface Width: 65 and 100 mm (2.5 and 4 in) Depth: 13 mm (0.5 in) below dowel
28
Slot Creation Slot Cutting Machine
29
Slot Creation Close-Up of Sawblades
30
Slot Creation Slot Sawcuts
31
Slot Creation Slot Cutting with Milling Machine
32
Slot Creation Milled Slots
33
Slot Preparation Material Removal
36
Slot Preparation Sandblasting Slots
37
Slot Preparation Cleaning Slots after Sandblasting
38
Slot Preparation Caulking of the Joint or Crack
39
Apply bondbreaker to dowels Attach expansion caps Place dowel on chair at slab mid-depth Filler board placed at mid-point of dowel bar to maintain joint Proper alignment is critical Dowel Bar Placement
42
Mix material in small quantities Generally 10 mm (3/8 in) top size aggregate Totally encase dowel bar Consolidate with small 25 mm (1 in) spud vibrator Apply curing compound Repair Material Placement
43
Repair Material Placement Backfilling
44
Repair Material Placement Consolidation and Finishing
45
Review of Process
46
Diamond Grinding after LTR
47
Retrofitted Dowel Project
48
Retrofitted Dowels at Cracks
49
3-5.49 II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting Presentation Outline
50
Quality Control Preliminary responsibilities Inspection of equipment Weather requirements Traffic control Construction inspection
51
Quality Control Class Exercise Break into three groups Preliminary responsibilities Equipment inspection, weather requirements, and traffic control Construction inspection considerations Identify importance of each item Use Reference Manual and your experience
52
3-5.52 II ntroduction MM aterial selection CC onstruction QQ uality control TT roubleshooting Presentation Outline
53
Project Checklist Preliminary Responsibilities Project Review Document Review Materials Checks Cementing grout Dowel bars Joint/crack materials Other materials General
54
Project Checklist Equipment Inspections Slot Cutting Equipment Slot Cleaning and Preparation Mixing and Testing Equipment Other Equipment Others Weather Requirements Traffic Control
55
Project Checklist Project Inspection Responsibilities Slot Cutting and Removal Slot Cleaning and Preparation Placement of Dowel Bars Mixing, Placing, Finishing, and Curing Backfill Material Cleanup Diamond Grinding Resealing Joints and Cracks
56
Troubleshooting Identify Problem Determine Cause Identify Solution Construction and performance problems Approach:
57
Troubleshooting What is wrong here? Misaligned joint forming material
58
Sawcuts are not cut parallel to the centerline Troubleshooting Construction Problems Solution? Problem
59
Dowel bar slots are cut too shallow Troubleshooting Construction Problems Solution? Problem
60
Dowel bar slots are cut too deep Troubleshooting Construction Problems Solution? Problem
61
Concrete fin is not easily removed Troubleshooting Construction Problems Solution? Problem
62
Jackhammer punching through slot Troubleshooting Construction Problems Solution? Problem
63
Cracking of in place patch material Troubleshooting Performance Problems Causes? Problem
64
Patch material pops out Troubleshooting Performance Problems Causes? Problem
65
Wearing off of patch material Troubleshooting Performance Problems Causes? Problem
66
Troubleshooting Guide – Causes and Solutions Slots are not parallel to pavement edge or longitudinal joint Dowel bar slots are too shallow Dowel bar slots are too deep Concrete fin not easily removed Jackhammer punches through bottom of slot Epoxy coating on dowel bar is chipped or missing
67
Troubleshooting Guide – Causes and Solutions Joint/crack sealant does not fully seal joint/crack along entire length expose in slot Joint/crack sealant extends more than 0.5 in. (13 mm) into slot Backfill material cracks in place Backfill material pops out of slot Backfill material wears faster than adjacent pavement
68
3-5.68 Introduction Material selection Construction Quality control Troubleshooting Presentation Outline
69
Learning Objectives 1.List benefits of load transfer restoration 2.Describe recommended materials and mixtures 3.Describe recommended construction procedures 4.List important quality control activities 5.Describe potential construction and performance problems 6.Identify associated solutions