Newmarket Viaduct Replacement STAGED VIADUCT CONSTRUCTION / DECONSTRUCTION PROCESS PROJECT DELIVERY BY NGA NEWMARKET
2
Current situation EXISTING NEWMARKET VIADUCT Existing 3 lanes both directions
3
Stage one EXISTING NEWMARKET VIADUCT Existing 3 southbound lanes – width reduced Existing southbound light poles and guard rail (LHS) removed Temporary lighting added
4
Stage one SOUTHBOUND TRAFFIC ON NEW SOUTHBOUND LANES New 3 lanes southbound (3.1m widths) in use Existing southbound lanes vacated Construction for 4 th lane tie-ins at north and south approaches
5
Stage two DECONSTRUCTION OF EXISTING SOUTHBOUND LANES New 4 lanes southbound (3.1m widths) in use
6
Stage three CONSTRUCTION OF NEW NORTHBOUND LANES
7
Stage four DECONSTRUCTION OF EXISTING NORTHBOUND LANES Northbound traffic relocated to new structure Widen all new lanes to final width New 4 lanes southbound: 3.5m widths New 3 lanes northbound: 3.1m widths
8
Final result COMPLETED NEW NEWMARKET VIADUCT