Yakima Air Terminal
2
Project Overview Project Schedule Impacts Project Status Questions
3
The Yakima Air Terminal has received an $11,000,000 grant. The grant is to: Resurface and widen Alpha Taxiway, Taxiway Connectors A1-A5, and portions of Bravo and Charlie Taxiways; Resurface airfield pavement between the north taxiway edge line to the non-movement line; Replace the existing MITL system with LED MITL, including new conduit, fixtures, and regulator; Replace all existing directional and hold short signs; and Correct several markings not meeting FAA standards.
6
Expected construction START DATE June 22, 2015: Phase 1: June 22, 2015 – July 17, 2015 Phase 2: July 20, 2015 – July 31, 2015 Phase 3: August 1, 2015 – August 14, 2015 Phase 4: August 15, 2015 – September 4, 2015 Phase 5: September 8, 2015 – September 29, 2015 Phase 6/7: September 30, 2015 – October 30, 2015
8
Phase 1: June 22, 2015 – July 17, 2015 Ramp Closures. McCormick West, and Plath Hangar. Partial Ramp Closures. Fuel Tank/House and McCormick Air Center. Temporary Runway 9/27 Closure for work within the Runway Safety Area. On-going construction activities and vehicle traffic on service roads and ramps.
10
Phase 2: July 20, 2015 – July 31, 2015 Ramp Closures. Airlift Northwest, FedEx Air Cargo and Airport Maintenance Building. Partial Ramp Closures. McCormick Air Center and Private Hangars (formerly Noland-Decoto). Temporary Runway 9/27 Closure for work within the Runway Safety Area. On-going construction activities and vehicle traffic on service roads and ramps.
12
Phase 3: August 1, 2015 – August 14, 2015 Ramp Closures. GE Aviation, West Itinerant Ramp, Med Assets, and West Terminal Apron Ramp. Partial Ramp Closures. Private Hangars (formerly Noland-Decoto). Temporary Runway 9/27 Closure for work within the Runway Safety Area. On-going construction activities and vehicle traffic on service roads and ramps.
14
Phase 4: August 15, 2015 – September 4, 2015 Ramp Closures. East Terminal Apron Ramp. Partial Ramp Closures. East Itinerant Ramp. Runway 4/22 and Bravo Taxiway Closed. Temporary Runway 9/27 Closure for work within the Runway Safety Area. On-going construction activities and vehicle traffic on service roads and ramps.
16
Phase 5: September 8, 2015 – September 29, 2015 Ramp Closures. No Ramps Closed. Alternate routes required for: Cub Crafters, McAllister Museum, Advanced Medical Systems, and South Air Park. Temporary Runway 9/27 Closure for work within the Runway Safety Area. On-going construction activities and vehicle traffic on service roads and ramps.
18
Phase 6: September 30, 2015 – October 30, 2015 Partial Ramp closures denoted by barricades. Runway 4/22 closed intermittently. On-going construction activity and vehicle traffic on service roads and taxiways.
20
Phase 7: September 30, 2015 – October 30, 2015 Not expecting any closures, however a schedule will be provided of the impacted areas to minimize air traffic and vehicle operations within the work areas. On-going construction activities and vehicle traffic on service roads and ramps.
21
If at all possible, avoid construction areas. Please plan all operations around construction to the maximum extent possible. If there are known operations that will be impacted by the proposed schedule, please let us know. The Airport Management will provide NOTAMs. Do not travel (plane or car) across barricades delineating closed pavement. Do not provide direction to the contractor unless there is an emergency.
22
Robert Peterson Rob.Peterson@yakimaairterminal.com Office: (509) 575-6149 (#7) Cell: (509) 833-0898 Kris Yalovich Kris.Yalovich@yakimaairterminal.com Office: (509) 575-6149 (#7) Stephanie Ray, PE sray@hlacivil.com (509) 966-7000 Michael Battle, PE mbattle@hlacivil.com (509) 966-7000