Download presentation
Presentation is loading. Please wait.
Published byMario Wollett Modified over 9 years ago
1
MCB Camp Lejeune Transportation Projects Analysis, Charrettes & Design on the Fast Track Sreekanth (Sunny) Nandagiri, PE, PMP Ryan Eckenrode, PE, PTOE NCAMPO Annual Meeting May 3 rd, 2012
2
Base Details Camp Lejeune – Jacksonville, North Carolina Established 1941 244 square miles, 11 miles of beach Greater than 180,000 people-Base and Jacksonville –40,000 Marines –Base and surrounding community –Active duty, retired and civilian $3 Billion in commerce every year Source: http://www.lejeune.usmc.mil/about/
3
Project Overview $30 Million-Indefinite Quantity Contract-NAVFAC (Naval Facilities Engineering Command ) Utilities Design and Engineering Utility-repair, replacement & upgrade Each project had a separate “Mod” Transportation Projects: –Road widening-Several corridors –Traffic capacity analysis-Synchro –Signal Design and ITS
4
Transportation Projects HP (Hadnot Point) Roads-Widening –Louis Road –Dogwood Street –Holcomb & McHugh roundabout / traffic circle Piney Green Road-Widening Gonzalez Boulevard Extension Resurfacing of Streets
5
Map Louis Rd Piney Green Rd Roundabout Resurfacing Gonzalez Blvd Ext
6
HP Roads – Louis Road 2 existing signals Sneads Ferry McHugh Blvd Heavy congestion Dogwood Street Not a through street today
7
HP Roads – Louis Road Recommendations Add two more signals –Birch Street –Dogwood Street Widen to three lanes Complete Dogwood Street Provides new link to commissary FYA at 3 of 4 signalized intersections
8
Roundabout – McHugh at Holcomb McHUGH HOLCOMB North
9
Roundabout – McHugh at Holcomb Recommendation
10
Gonzalez Boulevard Extension New location Barracks under construction Mess hall under construction Would Provides link to French Creek between McHugh Blvd and Sneads Ferry Rd Two lane section recommended FYA at signalized intersection
11
Piney Green Road Alternative entrance into MCB Camp Lejeune –Main commercial truck entrance Improvements at entrance control facility underway
12
Piney Green Road - Recommendations Widen to four lane section Add additional exiting lane at entrance control facility Non typical widening to avoid impacts to adjacent land uses Status: Piney Green was bid as an option which NAVFAC has not awarded yet.
13
Specs Intact Does not include signal specifications –Signal specifications were added as needed to reflect NCDOT standards Other standards also must be included –ASTM –NEC –NCDOT Example: –Instead of referring to the NCDOT standards for foundations, detailed specifications were listed for excavation, concrete pouring, curing etc—Mast arm poles
14
Charettes Intense 2 day Design Charettes (20-25% design stage) between the Client and the Consultant –First day: Initial discussion/Powerpoint presentation regarding the project Consultant presents initial design and recommendations/alignment options Client provides feedback/direction Consultant captures the feedback using “smart boards” Consultant analyzes the changes on that evening –Second day: Consultant updates/modifies the presentation Consultant gets the “buy-in” on the design concept Client approves the concept
15
Challenges Flooding Very flat and adjacent to the ocean Steam vaults Vehicular types Cars Military trucks (MRAPs) - 30+ tons weight Tanks Trains Base access Projects in parallel--Review process High concentration of young drivers
16
Challenges Continued Vehicular patterns Everyone arrives at 6AM and leaves at 3PM No range for the peaks-It happens at once Considered reversible lanes: –Piney Green –80/20 Traffic split –Dropped because of operational challenges
17
Pleasant Surprises of Working at MCB Lejeune No ROW constraints as all Military property Traffic very predictable, congestion early AM, lunch and late afternoon Drivers stopping and allowing us to continue working No speeding drivers Review process was very formal All utilities were owned by the Military-Coordination was easier
18
Questions
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.