1
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012
2
Agenda Phase 1 - Project Overview Phase 1 - Project Status Update Phase 2 - Project Overview Phase 2 - Project Schedule Questions Introduction
3
Phase 1 – Project Completed June 2012
4
Phase 1 – Project Status Update Construction Began October 3, 2011 Project Construction Cost North Pine Aggregate - $620,000 Completion Date – June 2012 Phase 1 - “To-Do” List/Warranty Items Minor Grading Around Catch Basins & Area Drains Seeding Removal of Erosion Control Devices
5
Phase 2 – Project Overview Design Considerations Long Term Stability Minimizing Encroachment on to Your Property While Maintaining the Long Term Stability Original Goal was No Encroachment on to Private Property, but it was determined to not be Possible due to Existing Site Limitations Grading Level Rear Yards to the Extent Practical
6
Phase 2 – Project Overview Design Considerations (continued) Bike Trail Replace Bike Trail at Generally the Same Elevation as it is was Prior to Construction Internal Drainage System PVC Storm Sewer with Concrete Catch Basins 5 Year Design (3.05” in 24 Hours) □ 10 Year Event (3.77” in 24 Hours) □ July 2011 Event (1.18” in 1 Hour) Three (3) Surge Basins
7
Phase 2 – Project Overview Flood Protection Levels Earthen Levee Flood Stage 43 (1 Foot Below Temporary Levee) □ This is lower than what has been done in other locations in Town due to the Geotechnical Engineer’s findings that the existing material on site has become consolidated due to the temporary levee being in place for the past couple years. Structural Wall Flood Stage 45 (1 Foot Below Temporary Levee) 5 Feet Exposed
8
Phase 2 – Project Overview
16
Phase 2 Project Overview – Timberline Flood Wall Backfilled Flood Wall with Approximately 7 feet of Exposed Flood Wall Flood Wall Prior to Backfilling
17
Phase 2 Project Overview – Timberline Flood Wall
21
Phase 2 – Project Schedule October 2012/November 2012 Finalize Construction Plans and Specifications Begin Easement Acquisition Stake Permanent Easements Meet with the City of Fargo & Ulteig Right-of-Way Agent(s) December 2012 Prepare Project to Present to the City Commissioners for Approval to go to out for Bids Finalize Easement Acquisition
22
Phase 2 – Project Schedule January 2013 Advertise & Receive Contractor Bids February 2013 Award Construction Contracts May 2013 – November 2013 Construction
23
Easement Acquisition Process Initial Contact (Easement Acquisition Form) □ Donate □ Minimum Payment Policy □ Mutual Agreed Amount □ Appraised Appraisal Review Offer with Copy of Appraisal Mailed Out Closing Set Up Recording of Documents Phase 2 – Project Schedule
24
Easement Acquisition Process (Continued) The City also has an irrigation policy in place that will reimburse the property owner for repairs to their irrigation system that was damaged due to the temporary levee construction. This policy has a maximum staff discrepancy of $1,000.00. Phase 2 – Project Schedule
25
Questions? Presentation can be viewed at www.cityoffargo.com\engineering