Transportation/Logistic Strategy Introduction to Inventory Total Cost Analysis Computation of Safety Stocks Setting Order Points Joint Replenishment Number.

Similar presentations


Presentation on theme: "Transportation/Logistic Strategy Introduction to Inventory Total Cost Analysis Computation of Safety Stocks Setting Order Points Joint Replenishment Number."— Presentation transcript:

1 Transportation/Logistic Strategy Introduction to Inventory Total Cost Analysis Computation of Safety Stocks Setting Order Points Joint Replenishment Number of Facilities and Inventory

2 Transportation/Logistic Strategy Total Cost Analysis Start with EOQ Identify alternatives Vendor discounts Transportation options Other issues Examine only total relevant costs Select least cost alternative

3 Transportation/Logistic Strategy Economic Order Quantity Order Quantity Cost of Ordering Cost of Carrying Inventory Total Cost $ *

4 Transportation/Logistic Strategy Interest and Opportunity Cost 10-20 % Storage and Handling8-14 % Depreciation and Obsolescence6-12 % Insurance and Taxes 2 -3 % Total 25-50 % Elements of Inventory Carrying Costs

5 Transportation/Logistic Strategy Order Quantity Cost of Ordering Cost of Carrying Inventory Total Cost $ (With Constant Ordering Costs) Zero Inventory JIT Economic Order Quantity

6 Transportation/Logistic Strategy Total Cost = OC + CC OC = Order Placement Cost = A(R/Q) CC = Inventory Carrying Cost = 1/2(QVW) Where: Q = Optimal Order Quantity (EOQ) A = Cost of placing an order R = Annual Rate of use V = Value per unit W = Carrying cost as a percentage of average value of inventory Determining EOQ

7 Transportation/Logistic Strategy Average Inventory Quantity Time Average Inventory Inventory Carrying Cost = 1/2 (QVW) Where: Q=Order Quantity V=Value per Unit W= Carrying Cost as a Percentage of the Average Value of Inventory

8 Transportation/Logistic Strategy Total Cost = OC + CC OC = A(R/Q) CC = 1/2(QVW) Total Cost = A(R/Q) + 1/2(QVW) and solve for QTo minimize cost, set 1st derivative = zero TC = ARQ -1 +.5QVW ARQVW Q 2 + TC = or TC ’ = - ARQ -2 +.5VW or -ARVW Q2Q2 2 + TC ’ = = 0 ARVW Q2Q2 2 = or 2AR VW Q2Q2 =  Q =Q = 2AR VW Determining EOQ

9 Transportation/Logistic Strategy Total Cost = OC + CC + Tr + PC + It + SS + Other Where: OC = Order Placement Cost CC = Inventory Carrying Cost Tr = Transportation Cost PC = Product Cost It = Inventory in Transit Cost SS = Safety Stock Cost Total Cost Analysis

10 Transportation/Logistic Strategy Total Cost = OC + CC + Tr + PC + It + SS + Other OC = A(R/Q) CC = 1/2(QVW) Tr = rRwt/100 PC = VR It = iVRt/365 SS = BVW Where: Q, R, A, V, W = As previously defined r = Transportation rate per 100 pounds (CWT) wt = Weight per unit i = Interest rate or cost of capital t = Lead time in days B = Buffer of inventory to prevent stockouts Total Cost Analysis

11 Transportation/Logistic Strategy Total Cost without Coordination of Purchasing and Transportation TC CC PC TR OC Quantity ~ ~ $ r1r1 r2r2 p2p2 p1p1

12 Transportation/Logistic Strategy Total Cost without Coordination of Purchasing and Transportation PC TR OC CC TC $ Quantity ~ ~ r 1/ p 1 r 2/ p 2

13 Transportation/Logistic Strategy If sales or lead times vary, safety stock is necessary to maintain desired service levels. Computing Safety Stock Begin with Order Point (BVW) If sales are constant and there is no variation in delivery times, no buffer is necessary, i.e., safety stock is not a relevant cost.

14 Transportation/Logistic Strategy Setting Order Points Order Point = Daily Use X Lead Time in Days Place orders when stock level falls to the level of the order point. Lead Time Quantity Order Point Time No Uncertainty

15 Transportation/Logistic Strategy Order Point = Mean Daily Use X Lead Time in Days To Protect Against Stockouts, Place Orders Sooner But How Much Sooner? Lead Time Quantity Order Point Time Stockout Setting Order Points With Uncertainty

16 Transportation/Logistic Strategy Place orders when stock levels fall to the mean, and half the time you have enough to cover sales and half the time you don’t; i.e., you have a 50% Fill Rate. Raise the order point, and you raise the service level. One Standard Deviation of Buffer Stock Provides an 84% Fill Rate Two Standard deviations of Buffer Stock Provides a 97.5% Fill Rate How Do We Know? Example Setting Order Points With Uncertainty

17 Transportation/Logistic Strategy Average Daily Sales Sales Day (X i ) (X i ‑ X) (X i – X) 2 1 100 0 0 2 90 ‑ 10 100 3 110 10 100 4 85 15 225 5 105 5 25 6 110 10 100 7 95 ‑ 5 25 8 115 15 225 9 100 0 0 10 90 ‑ 10 100 11 110 10 100 12 90 ‑ 10 100 SUM 1200 0 1100 Mean = 100; Std Dev = 10

18 Transportation/Logistic Strategy Mean and Standard Deviation of Average Daily Sales Mean = 1200/12 = 100 ___________ ________ Std Dev = √  (X i – X) 2 = √ 1100/11 = 10 n-1

19 Transportation/Logistic Strategy Assume constant delivery time of one day, i.e., no variation Order Point = Mean Daily Use X Lead Time in Days + Buffer Stock Mean Sales = 100 units Standard Deviation of Sales = 10 units Order Point = 100 + 10 = 110 Setting Order Points With Uncertainty

20 Transportation/Logistic Strategy Order Point = Daily Use X Lead Time in Days + Buffer Stock By Ordering Sooner, Stockouts are Avoided Lead Time Quantity 110 Time 100 What is the service level (fill rate) associated with this order point? Setting Order Points With Uncertainty

21 Transportation/Logistic Strategy One Standard Deviation = 68% of the area. Half of the time sales are below 100; 84% of the time sales are below 110. 68% 34% 10090Sales110 Computing Safety Stock

22 Transportation/Logistic Strategy Two Standard Deviations = 95% of the area. Half the time sales are below 100; 97.5% of the time sales are below 120. 95% 47.5% 10080Sales 120 Computing Safety Stock

23 Transportation/Logistic Strategy z0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 0.00.00000.00400.00800.01200.01600.01990.02390.02790.03190.0359 0.10.39800.04380.04780.05170.05570.05960.06360.06750.07140.0753 0.20.07930.08320.08710.09100.09480.09870.10260.10640.11030.1141 0.30.11790.12170.12550.12930.13310.13680.14060.14430.14800.1517 0.40.15540.15910.16280.16640.17000.17360.17720.18080.18440.1879 0.50.19150.19500.19850.20190.20540.20880.21230.21570.21900.2224 0.60.22570.22910.23240.23570.23890.24220.24540.24860.25180.2549 0.70.25800.26120.26420.26730.27040.27340.27640.27940.28230.2852 0.80.28810.29100.29390.29670.29950.30230.30510.30780.31060.3133 0.90.31590.31860.32120.32380.32640.32890.33150.33400.33650.3389 1.00.34130.34380.34610.34850.35080.35310.35540.35770.35990.3621 1.10.36430.36650.36860.37080.37290.37490.37700.37900.38100.3830 1.20.38490.38690.38880.39070.39250.39440.39620.39800.39970.4015 1.30.40320.40490.40660.40820.40990.41150.41310.41470.41620.4177 1.40.41920.42070.42220.42360.42510.42650.42790.42920.43060.4319 1.50.43320.43450.43570.43700.43820.43940.44060.44180.44290.4441 1.60.44520.44630.44740.44840.44950.45050.45150.45250.45350.4545 1.70.45540.45640.45730.45820.45910.45990.46080.46160.46250.4633 1.80.46410.46490.46560.46640.46100.46780.46860.46930.46990.4706 1.90.47130.47190.47260.47320.47380.47440.47500.47560.47610.4767 2.00.47720.47780.47830.47880.47930.47980.48030.48080.48120.4817 2.10.48220.48260.48300.48340.48380.48420.48460.48500.48540.4857 2.20.48610.48640.48680.48710.48750.48780.48810.48840.48870.4890 2.30.48930.48960.48980.49010.49040.49060.49090.49110.49110.4916 2.40.49180.49200.49220.49250.49270.49290.49310.49320.49340.4936 2.50.49380.49400.49410.49430.49450.49460.49480.49490.49510.4952 2.60.49530.49550.49560.49570.49590.49600.49610.49620.49630.4964 2.70.49650.49660.49670.49680.49690.49000.49710.49720.49730.4974 2.80.49740.49750.49760.49770.49770.49780.49790.49790.49800.4981 2.90.49810.49820.49820.49830.49840.49840.49850.49850.49860.4986 3.00.49860.49870.49870.49880.49880.49890.49890.49890.49900.4990 4.00.49997 \\\ \\\\ Areas under the standard normal probability distribution between the mean and successive values of z

24 Transportation/Logistic Strategy Effects of Delivery Time Variation Where: S Dt = Standard Deviation of Demand over time(Units of Safety Stock required to satisfy 68 percent of sales levels during lead time) t = Average delivery time S t = Standard Deviation of delivery time D =Average Demand S D =Standard Deviation of Demand S Dt = (t)(S D ) 2 + (D) 2 (S t ) 2 

25 Transportation/Logistic Strategy Example ASSUMPTIONS Average Sales (D) = 100 units Standard Deviation of Sales (S D ) = 10 units CARRIER A CARRIER B Average Transit Time (t) 5 Days 5 Days Standard Deviation of Time (S t ) 1 Day 2 Days

26 Transportation/Logistic Strategy Combined standard deviations CARRIER A S Dt =  (5) (10) 2 + (100) 2 (1) 2 = 102 units S Dt = √ (5) (10) 2 + (100) 2 (2) 2 = 201 units CARRIER B (Continued) Example

27 Transportation/Logistic Strategy Assumptions: Cost of Carrying Safety Stock = BVW (Buffer Stock) X (Value) X (Carrying Cost) Value per Unit = $100.00 Carrying Cost = 20 percent Service Level = 97.5 percent a ________________________________________________ a To attain a 97.5% service level, the shipper will have to add 2 standard deviations of safety stock to the order point. (Continued) Example

28 Transportation/Logistic Strategy CARRIER A: S Dt = 102 units Cost = 2 X 102 X 100 X.2 = $4,080 CARRIER B: S Dt = 201 units Cost = 2 X 201 X 100 X.2 = $8,040 Additional cost of using a less reliable carrier: ($8,040 ‑ $4,080) = $3,960 (Continued) Example

29 Transportation/Logistic Strategy Basic Trade-off More facilities = more inventory More facilities = shorter shipments Tie in with ABC Analysis Consolidate slow moving items in central locations Trade increased transportation for reduced inventory or vice versa Inventory and the Number of Facilities

30 Transportation/Logistic Strategy Inventory and the Number of Facilities Number of Facilities (X) $ (Y) Y= b X 

31 Transportation/Logistic Strategy Joint Replenishment Order multiple items at the same time. When any item hits an order point, place orders for all items. Constraint: Order only full truckloads (e.g., 40,000 lbs).

32 Transportation/Logistic Strategy Q i = R i Q + I - P R - I i + P i ( ) Where: Qi = Order Quantity of the ith item (to be determined) Ri = Annual Rate of Use of the ith item Ii = Inventory on hand for the ith item Pi = Reorder point for the ith item Q = Total Shipment Size R = Total of Individual Usage Rate I = Total of Individual Inventory Items on Hand P = Total of Individual Reorder Points Joint Replenishment

33 Transportation/Logistic Strategy Example: Corn, Beans, Peas Units R i P i I i Corn 6,400 163 154 Beans 9,800 218 250 Peas 5,100 150 180 Totals 21,300 531 584 Cases =25 pounds R i P i I i Corn160,000 4,075 3,850 Beans245,000 5,450 6,250 Peas127,000 3,750 4,500 Totals 532,50013,27514,600 R P I Joint Replenishment

34 Transportation/Logistic Strategy Q i = R i Q + I - P R - I i + P i ( ) Corn: Qi = 160,000 (40,000+14,600-13,275) - 3,850 + 4,075 = 12,641 532,500 Beans: Qi = 245,000(40,000+14,600-13,275) - 6,250 + 5,450 = 18,213 532,500 Peas: Qi = 127,500(40,000+14,600-13,275) - 4,500 + 3,750 = 9,145 532,500 40,000 Example: Corn, Beans, Peas Joint Replenishment