Dr. Neal CIS 480 MS Project Concepts Dr. Greg Neal CIS 480 Systems Analysis and Design
2
Dr. Neal CIS 480 Pert Network
3
Dr. Neal CIS 480 Gantt Chart 1,2 & 3 all start at beginning
4
Dr. Neal CIS 480 Task List Early Start Late Start Slack Difference Early-Late Critical Path
5
Dr. Neal CIS 480 Calculation of EarlyStart,LateStart,Slack Task Three (3 days) –EarlyStart (Project Start on 6/1/06) –LateStart = Task 7 LateStart – Task 3 duration: 6/2/06 Task Seven (6 days) –Task 7 StartFinish predecessor of Task 3 –EarlyStart =Task 3 Finish 6/5/06 + 1 day: 6/6/06 –LateStart = Task 9 LateStart – Task 7 duration: 6/7/06 Task Nine (3 days) –Task 9 StartFinish predecessor of Task 7 –EarlyStart = Task 7 Finish 6/13/06 + 1 day: 6/14/06 –LateStart = Task 10 Start – 3 days: 6/15/06 Forward Calculation Backward Calculation Slack 1 day
6
Dr. Neal CIS 480 Task Dependencies Finish-to-Start (FS) –Task B cannot start until task A finishes Start-to-Start (SS) –Task B cannot start until task A starts (both start the same time) Finish-to-Finish (FF) –Task B cannot finish until task A finishes (both finish at the same time) Start-to-Finish (SF) –Task B cannot finish until task A starts
7
Dr. Neal CIS 480 Dependency Gantt Examples FinishStart(FS) StartStart(SS) FinishFinish(FF) StartFinish(SF)
8
Dr. Neal CIS 480 Lead and Lag Dependencies 1 day Lag 1 day Lead