1
SHRP 2 - R04 ABC Demonstration Bridge Design and Construction AASHTO Committee on Construction San Francisco, CA August 16, 2012
2
Iowa ABC Demonstration Project Two Week Closure US Highway 6 Bridge over Keg Creek 6 miles east of Council Bluffs, IA Normal construction duration 14-16 weeks ABC construction duration 14 days
3
Project Innovations Precast modular bridge system (including precast approach pavement) Superstructure units create a semi- integral abutment for rapid construction Durable, moment-resisting UHPC joint between deck panels First bridge in US with full, moment- resisting UHPC joint at the piers
4
UHPC UHPC Particle Packing UHPC Constituents: Portland cement silica fume fine, uniformly graded sand crushed quartz steel fibers water superplasticizers
5
14-Day ABC Timeline 123 4 56789 10 111213 14
6
Bridge Farm Concept
7
Precast Abutments and Piers
8
Superstructure Modules
9
Deck Joint Forming
10
Deck Concrete Placement
11
Drilled Shaft Construction
12
Abutment Details Precast Abutment Construction Single piece barrel section SCC to fill pile pockets Temporary support of backwall until SCC reaches 3500 psi
13
Semi- Integral Abutment
14
Abutment Construction
15
SCC Concrete for Abutments
16
Precast Piers
17
Precast Pier Connections
18
Column Assembly and Bracing
19
Capbeam Assembly
20
Modular Superstructure
21
Pier Joint Detail C Pier 1 L C Pier 2 L
22
PT Retrofit for Modules
23
Module Transport
24
Module Assembly
26
Deck Joint Reinforcing
27
UHPC Mixing
28
UHPC Placement
29
FHWA/HFL Workshop
31
SHRP 2 - R04 ABC Demonstration Bridge Design and Construction Questions?