Presentation is loading. Please wait.

Presentation is loading. Please wait.

MICE OsC – 22 nd June 2010 Liquid-hydrogen system and absorber M Hills T Bradshaw M Courthold S Ishimoto W Lau I Mullacrane P Warburton.

Similar presentations


Presentation on theme: "MICE OsC – 22 nd June 2010 Liquid-hydrogen system and absorber M Hills T Bradshaw M Courthold S Ishimoto W Lau I Mullacrane P Warburton."— Presentation transcript:

1 MICE OsC – 22 nd June 2010 Liquid-hydrogen system and absorber M Hills T Bradshaw M Courthold S Ishimoto W Lau I Mullacrane P Warburton

2 MICE OsC – 22 nd June 2010 Contents 1.Introduction 2.Latest progress on R&D system manufacture 3.The system safety case 4.Control system 5.Hall infrastructure 6.Integration with the AFC module 7.Summary & plans for 2010/11

3 MICE OsC – 22 nd June 2010 The Hydrogen Delivery System and Absorber 3 AFC Module (Tesla/Oxford /STFC) Absorber (KEK/Mississippi) Hydrogen Delivery System (STFC)

4 MICE OsC – 22 nd June 2010 System Components

5 MICE OsC – 22 nd June 2010 R&D System Manufacture (1)  Buffer Volume, Transfer Line and Test Cryostat all complete  Gas Panel assembly well advanced  Design of enclosure is being detailed 5

6 MICE OsC – 22 nd June 2010 R&D System Manufacture (2) –Gas Panel manufacturing –Weld inspection and pipe cleaning complete –Final assembly of pipework underway –Flow meters (final item of instrumentation) procured and installed in the gas panel –Relief valves assembled into dedicated mounting frames 6

7 MICE OsC – 22 nd June 2010 Cryostat Cooldown Set-up

8 MICE OsC – 22 nd June 2010 Cryostat Cooldown Pre-cool with LN2

9 MICE OsC – 22 nd June 2010 Safety Approach –The system must tolerate two things going wrong simultaneously without becoming unsafe –Design philosophy Maintain separation of hydrogen and oxygen atmospheres Avoid sources of ignition (a hydrogen-oxygen mixture only needs 19µJ to ignite) –Standards Dangerous Substances and Explosive Atmospheres Regulations (DSEAR). This is the UK implementation of the EU ATEX User Directive. IEC 61508 (Functional safety of electrical/electronic/programmable electronic systems) –Passive safety concept Relief valves will open to return gas to the hydride bed or high level vents in the event of a rapid pressure rise (e.g. due to loss of insulating vacuum). This happens independently of the control system. 9

10 MICE OsC – 22 nd June 2010 MICE Safety Considerations The design of the MICE AFC module creates particular requirements: –Thin windows on absorber have a design pressure of 1.7bara (they will be burst pressure tested to 4x this). –Hydrogen system consequently operates at low pressure (relief valves set at 1.5bara; burst discs at 1.9bara) –Rapid pressure rise could result from large liquid-to-gas expansion ratio of hydrogen (approx. 780/1) –Pipework, Buffer Volume and relief valves are sized for total loss of vacuum in the AFC module 10

11 MICE OsC – 22 nd June 2010 DSEAR Zoning 11  Test Cryostat (or AFC absorber vacuum space)  Gas Panel Enclosure  Pump Enclosure  Connecting ductwork...are Zone 2. (“A place in which an explosive atmosphere....is not likely to occur in normal operation, but, if it does occur, will persist for a short period only.”) The MICE Hall is not

12 MICE OsC – 22 nd June 2010 Control System (1)  Control Panel assembled with (almost) all components needed for He testing  Barriers provide intrinsic safety (<19µJ in the circuit) for all wiring except the heaters.  PLC programmed  Temperature logging  Valve control tested  Example control sequence tested  Heater control implemented 12 PLC Barriers GP & Cryostat Connectors

13 MICE OsC – 22 nd June 2010 Control System (2) –Cryostat monitoring complete (almost) –Sequences for gas panel operation currently being written –Design work underway for ventilation system and vacuum system control.

14 MICE OsC – 22 nd June 2010 Control System Safety Functions Only three functions of the control system identified as ‘safety critical’: I.Operation of the ventilation system on detection of a hydrogen leak II.Shut-off PV20* if there is pressure rise in the cryostat during operation. III.Interlock the Gas Panel Enclosure with system returning to ‘safe state’ on breaking of interlock These will all be hard-wired and separate from the PLC. [*This isolates the vacuum system.] 14

15 MICE OsC – 22 nd June 2010 UPS Requirements  Recent discussions held amongst the Hydrogen System team on the UPS requirements for the system  Document currently being drafted for submission to MICE Technical Board  Key conclusions –In the event of a mains failure: System will fail to its pre-defined ‘safe-state’ Instrumentation and valve position information should continue to be available from the control system The hydrogen detection system should continue to function 15

16 MICE OsC – 22 nd June 2010 Hall Infrastructure To install the R&D system in the MICE Hall requires: –Bottle store –Vacuum system with roughing pumps sited externally –Ventilation system to exhaust any leak in Gas Panel, Buffer Volume or Hydride Bed. 16

17 MICE OsC – 22 nd June 2010 Hall Infrastructure 17 Relief lines Ventilation ducts Fans Test Cryostat Gas Panel Enclosures

18 MICE OsC – 22 nd June 2010 Ventilation System H2 vented during operation of relief valves is separate form ventilation system

19 MICE OsC – 22 nd June 2010 Ventilation System Basis of safety –Eliminate sources of ignition ATEX rated fans –Fans are specified such that one fan only is capable of providing sufficient flow to exhaust all three systems –An explosive atmosphere from a small leak in the gas panel would only persist for a matter of minutes –Fans have been purchased and are ready to install. 19

20 MICE OsC – 22 nd June 2010 Vacuum System –Dedicated pump enclosure to be sited on MICE Hall roof –Will house backing pumps required for all 3 hydrogen systems –Will also have capacity to house backing pumps required for other cooling channel modules –Designated Hydrogen Zone 2 (same as Gas Panel Enclosures) for DSEAR purposes –Turbo pumps for AFC modules’ safety vacuum shown on South Wall (must be behind magnetic shield wall) Turbo pumps Backing pump

21 MICE OsC – 22 nd June 2010 – Located opposite the MLCR – Virtually all preparation for rack installation complete: – room cleaned out – new door fitted – redundant pipes removed – Cabinet support frames installed – cable routes established Hydrogen Control Room

22 MICE OsC – 22 nd June 2010 Integration with the AFC –Working with Oxford, KEK and Tesla to ensure that the R&D system is compatible with the AFC module –Instrumentation –Process line connections –Aim to test absorber in R&D test cryostat to check interfaces and instrumentation 22

23 MICE OsC – 22 nd June 2010 Absorber Instrumentation 23

24 MICE OsC – 22 nd June 2010 Schedule 24

25 MICE OsC – 22 nd June 2010 Summary and Future Plans –R&D System components complete with exception of Gas Panel and Enclosure; these are due for installation at start of long ISIS shutdown. –Control system well advanced –Safety principles of system well established, but implementation and documentation of these are still ongoing. Results from helium testing will be an important input to a pre-operation safety review. –Design work underway for hall infrastructure requirements, but lots to do. –Need to continue to work closely with KEK, Oxford and Tesla to ensure compatibility with AFC. –Aim to take advantage of the long ISIS shutdown and delays to the Spectrometer Solenoids to install as much infrastructure as possible in the rest of this financial year. –Several tasks: Install R&D system components on south mezzanine Build pumping enclosure and install vacuum system Position fans, install ductwork and construct access platforms Route vent lines outside hall Install hydrogen detection system Route cabling and install control racks in H2 Control Room 25


Download ppt "MICE OsC – 22 nd June 2010 Liquid-hydrogen system and absorber M Hills T Bradshaw M Courthold S Ishimoto W Lau I Mullacrane P Warburton."

Similar presentations


Ads by Google