REPLACING EAST SIDE OF BRIDGE in 2009
2
WEST Section Sank in 1979 Storm REBUILT and Opened in 1982 EAST Section REBUILDING Shown here 2004-2009 HOOD CANAL BRIDGE Ferry Dock
3
1. Build New Section with new columns under existing section 2. Move old section over 3. Move new section over new colums 4. Remove old section and old colums New - Wider Approach COMPLETED
4
Starting NEW APPROACH Section
5
SETTING BRIDGE ANCHORS
7
TRANSITION Section - READY Photos by Jack and Gwen Duzenski
8
READY to lift
9
LIFTING
11
Transition section in on barge No Traffic here!
12
Breaking pontoons into two sections
13
Meanwhile persons who need to traverse the canal, turn the road into a parking lot.
14
Ferry Dock You can spot this area on slide #2
15
MOVING DAY
16
LOWER SECTION MOVING OUT
17
MOVING NORTH
18
OLD SECTIONS - OUT OF THE WAY
19
Good view of WEST DRAW SPAN CANAL IS BEING CLEARED
20
A NEW – WIDER PONTOON IS MOVED IN
21
And here comes the new TRANSITION Section
22
WAIT! Here comes a Sub.
26
Look, the Sub’s Conning Tower is as wide as the road way.
27
5-17-2009
30
New TRANSITION Section is squeezed into place
31
DRAW SPAN IS IN PLACE
32
ALL IS IN PLACE
33
BREAKING OLD COLUMN INTO SECTIONS > > >
34
REMOVE OLD SUPPORTS > > >
37
HERE COMES TRANSITION SECTION
39
PLACING EXPANSION JOINT
40
POURING CONCRETE IN HOLE USED TO REMOVE OLD BRIDGE SUPPORT
41
NEW SIGNS
43
CHECKING GATE
44
DRIVING ACROSS - TOWARDS PORT ANGELES
46
TURNED AROUND - HEADING BACK EAST
48
THE EAST END
49
THE LAST FOOT FERRY