Design/Build Team for the US 36 Express Lanes Project
3
Selected Ames/Granite Joint Venture on Feb. 29 In addition to the base project elements, the team has committed to: Extending the terminus of the project from Interlocken Loop west to 88 th Street in Louisville/Superior; Reconstructing the Sheridan Boulevard Bridge over US 36, along with roadway approaches and ramp intersections Reconstructing the US 36 bridge over the Burlington Northern Santa Fe Railway Improving RTD stations along the corridor, including new canopies with enhanced weather protection Selection of the Design-Build Team
4
Proposed Phase 1 Construction Schedule (August 2012 – April 2013)
5
Proposed Phase 2 Construction Schedule (April 2013 – December 2013)
6
Proposed Phase 3 Construction Schedule (December 2013-2014)
7
Final Configuration/Completion
8
Maintain all existing general purpose and HOV lanes during all phases of construction No long-term closures Required lane closures will be on off-peak traveling hours Median work will be minimized Shortened the overall duration of the project Minimize traffic switches to improve driver familiarity Maintain a consistent temporary traffic pattern to enhance driver expectancy Key Elements to Proposal MOT Plan
9
Arterial CCTV Cameras to monitor key intersections along the diversion routes. Deployment of two Hotspot Traffic Trailers Additional Web page with travel information Proposed phone application Proposed Value-Added Strategies of MOT Plan