Presentation is loading. Please wait.

Presentation is loading. Please wait.

ABC130 and HCC Submissions F.Anghinolfi 08/02/131ABC Final Design Review.

Similar presentations


Presentation on theme: "ABC130 and HCC Submissions F.Anghinolfi 08/02/131ABC Final Design Review."— Presentation transcript:

1 ABC130 and HCC Submissions F.Anghinolfi 08/02/131ABC Final Design Review

2 ABC130 (& HCC) Submission on MPW On MPWs – Regular MOSIS MPW on 4 th May 2013 (reachable for ABC130, for HCC ?) – Next regular MOSIS MPW on 4 th August 2013 (reachable for HCC) – Additional quantities on request (but costs) 208/02/13ABC Final Design Review

3 ABC130 Submission on … Shared Engineering Run (ABC + TDCpix) – ABC : Shared Engineering run with the NA62/TDCpix submission (forecast 1Q 2013) – Additional Eng. Run wafers at 3.6KUSD each (120chips/w) – Needs Synchro btw TDCpix(NA62) and ABC (for submission in Feb-March. 2013, FDR January-Feb 2013 for both ASICs) 308/02/13ABC Final Design Review

4 ABC130 & HCC Submission Scenario 2 Shared Engineering Run (ABC + TDCpix) Additional Eng. Run wafers at 3.5KUSD each (120chips/w) Production Run wafers at 2.5KUSD each (120chips/w) 408/02/13ABC Final Design Review

5 ABC130 & HCC Submission Scenario 2 Shared Engineering Run (ABC + TDCpix) Eng. Run + 1 Production run = 3720 chips Eng. Run + 2 Production run = 6120 chips Eng. Run + 3 Production run = 8520 chips 508/02/13ABC Final Design Review

6 Separate HCC Production Option for HCC if ABC is submitted separately MPW Mosis : 40 chips @ 37KUSD “Small Quantity Production” with MOSIS (one 24 wafers lot of HCC-mainly reticle) at 100K-150KUSD range (should provide much more ASICS than the 900 requested ….) 608/02/13ABC Final Design Review Addition of (worst case cost) 7000 ABC (on shared Eng. Run with TDCPix) delivery plus HCC small Production Run = (322 + 150) KUSD ~ 472KUSD

7 ABC130 &HCC Engineering Run Engineering Run (ABC + HCC) – Additional Eng. Run wafers at 3.5KUSD each – Production Run wafers at 2.5KUSD each – HCC drives the schedule 708/02/13ABC Final Design Review

8 ABC130 &HCC Submission Scenario 3 Engineering Run (ABC + HCC) – One engineering run comes short (but close..) to 7000 808/02/13ABC Final Design Review Cost 475KUSD

9 ABC130 Submission Scenario ABC independent of HCC – Regular MOSIS MPW on 4 th May 2013 (reachable for ABC130, probably not for HCC) – Shared Engineering run with the NA62/TDCpix submission (forecast 1Q 2013) With HCC : – Engineering Run, attached to HCC schedule Independent HCC : – Small quantity production possible through MOSIS 908/02/13ABC Final Design Review


Download ppt "ABC130 and HCC Submissions F.Anghinolfi 08/02/131ABC Final Design Review."

Similar presentations


Ads by Google