1 Inland Waterways Authority of India 13th April, 2012
IWT in NER Inland Waterways Authority of India 13th April, 2012 Doner_

2 IWAI Inland Waterways Authority of India (IWAI) was constituted in October, 1986 by an Act of Parliament for development and regulation of inland waterways. Doner_

3 Charter of IWAI Development and regulation of National Waterways
Advise Central Government on matters relating to IWT Assist State Governments in development of IWT Lay down standards for classification of inland waterways Enter into joint ventures concerning inland shipping Conduct research in matters relating to IWT Doner_

4 National Waterways So far five waterways have been declared as National waterways NW-1, the Ganga (1620 km)- declared in 1986 NW-2, the Brahmaputra (891 km)- 1988 NW-3, the West Coast Canal (205 km)- 1993 NW-4, the Godavari, Krishna and canals between Kakinada & Puducherry (1028 km)- 2008 NW-5, the Brahmani river, Mahanadi delta & East Coast canal (588 km)- 2008 Barak river in Assam is under consideration for declaration as NW-6 (121 km) Indo- B’desh Protocol routes (1700 km) connect NW-1 with NW-2 and proposed NW-6 Doner_

5 North Bank Subanasiri Burali Bargang Dhansiri Puthimari Pagladiya Beki
Manas Aie Champamati Gadadhar South Bank Noa dihang Burhi dihang Disang Dikhu Jhanju Dhansiri Kopili Kulsi Krishnai Jinary SADIYA SAIKHOWA DIBRUGARH BOGIBIL JAMGURI TEJPUR SILGHAT BRAHMAPUTRA R. JOGIGHOPA GUWAHATI PANDU DHUBRI BANGLADESH SHISHUMARA Dir/presentation 1/NER-Thai Oct07

6 mmm Doner_

7 Protocol route distances
TEJPUR NAGALAND P SILGHAT INDO – BANGLADESH PROTOCOL ROUTES 31C I N D I A Brahmaputra R. NW-2 A S S A M 36 JOGIGHOPA DISPUR 37 31 PANDU DHUBRI P 37 KOHIMA SHISHUMARA 40 DAIKHAWA SHILLONG 31 51 M E G H A L A Y A BIHAR CHILMARI 53 Barak MANIPUR Ganga R. Surma R. ZAKIGANJ 34 BAHADURABAD LAKHIPUR SYLHET BHANGA 53 IMPHAL KARIMGANJ P JHARKHAND Jamuna R. MARKULI Kusiyara R. FENCHUGANJ B A N G L A D E S H SHERPUR AJMIRIGANJ DHULIAN GODAGARI SIRAJGANJ RAJSHAHI P 54 Ganga R. Baral R. BHAIRAB BAZAR ASHUGANJ 44 N TRIPURA BAGHABARI ARICHA Meghna R.` AKHAURA AGARTALA DHAKA AGARTALA AIZWAL NW-1 Bhagirathi R. MIZORAM NARAYANGANJ Padma R. P Legend Legend 2 CHANDPUR Declared National waterway Proposed National waterway Protocol route Road Rail NH KHULNA 35 P BARISAL Meghna R. WEST BENGAL CHALNA KAUKHALI KOLKATA P 51 Protocol route distances P MONGLA 6 41 Kolkata - Guwahati/Pandu km Kolkata - Karimganj km Dhulian-Rajshahi km HALDIA P ANGTIHARA Hooghly R. 7 NAMKHANA Raimangal R. Bay of Bengal Myanmar (Burma) ORISSA Sunderbans Doner_

8 Importance of IWT for NER
A cost effective & environment friendly mode Best suited for bulk goods, ODC, Project cargo & hazardous goods IWT offers shorter, alternative route to Lower Assam, Tripura, Mizoram & Manipur Provides port- hinterland connectivity to entire region – Kolkata – Haldia Access to Chittagong port by Bangladesh set to change EXIM cargo transport pattern in NER as well as Bhutan Doner_

9 Importance of IWT for NER
891 km stretch of Brahmaputra developed as NW 2; 121 km stretch of Barak river under consideration as NW 6 So, about 1012 km of National Waterways likely Another 1566 km stretch of tributaries of Brahmaputra & Barak identified in NER for development as State Waterways – Feeder routes Kaladan multi-modal transport project set to provide alternate route through Myanmar to NER Nagaland can get access to Myanmar through development of Tizu river link River Brahmaputra offers immense scope for development of ‘river cruise’ & ‘eco-tourism’ in NER Doner_

10 Status of NW-2 …. essential requirements
1. Fairway with targeted depth & width 2. Aids for 24 hrs navigation 3. Terminals with cargo handling equipment and Road- Rail link 4. Vessels First three by Govt; fourth by Private sector Doner_

11 Status of NW- 2 Projects being implemented for making NW-2 fully functional : Fairway Least available depth (LAD) of 2.5 m between Dhubri- Neamati (630 km); 2.0 m between Neamati-Dibrugarh (138 km) 1.5 m between Dibrugarh-Sadiya (123 km) IWAI has 2 dredgers at present (1 CSD and 1 HSD) 2 more CSD & one HSD being added in Doner_

12 Status of NW- 2 Navigation aids
24 hrs navigation aids in 440km (Dhubri- Silghat), which can be extended to entire waterway depending on necessity DGPS station set up at Jogighopa and works are nearing completion at Silghat and Dibrugarh One more DGPS station will be set up at Dhubri These DGPS will provide safe navigation to Inland vessels using electronic navigational charts Fortnightly talweg survey through 6 survey vessels of IWAI; river notices being issued Besides, pilots are provided to cargo vessels Doner_

13 Status of NW- 2 Terminals IWT Port Pandu
IWT Port at Pandu has been developed by IWAI as a hub for multimodal connectivity in the North-East region by investing Rs. 100 Cr. Low level permanent jetty is operational with mechanical handling equipment Rail connectivity (BG) completed and ready for commissioning Road connectivity already available High level jetty in progress Alternate road connectivity with NH-31 for container/heavy traffic is under construction Doner_

14 Status of NW- 2 Terminals
Floating terminals at Dhubri, Jogighopa, Tejpur, Silghat, Neamati, Bogibil (north & south banks), Dibrugarh, Panbari & Orium ghat are being maintained with pontoon and gangway Floating terminal can be provided at other locations on need basis Two shore cranes and five floating cranes are availble for loading/unloading of cargo at the terminals Doner_

15 Status of NW-2 Vessel Repair Facility A critical deficiency
IWT unit of Army; Para-military forces also face immense problems Assam Govt’s partially completed slipway at Pandu can be completed as joint project of IWAI, GoA & GRSE Doner_

16 Status of NW-2 Cargo Vessels
Failure of CIWTC is perhaps the biggest set back for IWT in NER IWAI has 2/3 cargo vessels for demonstrative voyages only IWT Directorate, Assam also has some cargo vessels but now virtually defunct Private operators consider investment in vessels too risky - lack of assured cargo; uncertainties surrounding Indo- Bangladesh Trade & Transit Protocol Doner_

17 Important IWT Projects
Declaration of Barak river as National Waterway Kaladan multi modal transport project Kaladan RO-RO terminals at Dhubri and Hatsinghimari (Phulbari) for RO-RO vessel movement Slipway facilities at Pandu Construction of terminals at Tejpur, Bishwanath Ghat, Oriyumghat Study by RITES for development of State waterways Doner_

18 Important IWT Projects
Transportation of FCI foodgrains by IWT Mode to North-East Transportation of coal by waterway for NTPC power plant at Bongaigaon Transportation of pipes & other cargo of ONGC & Oil India Ltd. from Kolkata to North-East Transportation of containers by IWT mode between Kolkata and Pandu Doner_

19 Barak river Declaration of Barak river [Lakhipur- Bhanga stretch (121 km)] as National Waterway is in advanced stage Cost of development – Rs 123 Cr (2011prices) Navigational Channel of 40 m width and 1.6 m/2.0 m depth 1 CSD unit, 1 survey launch, & 1 inspection boat are proposed for this NW IWT terminals at Lakhipur, Silchar and Badarpur Protocol routes connect Karimganj and Kolkata Doner_

20 Proposed National Waterway (No 6)
River Barak Bhanga Badarpur Silchar Stretch Km Bhanga - Lakhipur 121 Length –121 km Development cost -Rs 123 Cr (at prices) Status: Declaration in process Doner_

21 Kaladan multi modal transport project
Project funded by MEA – total project cost could be of over Rs.1000 crore Provides alternative connectivity of North- East with mainland India through Kaladan river & Sittwe port in Myanmar Multi modal project: Road- IWT- Sea IWAI as PDC did the bid process management M/s Essar Projects appointed by MEA as main contractor for port & IWT components Cost of work (IWT & Port): Rs 342 crore Completion period is 3 years Construction commenced; likely completion June 2013 Doner_

22 Myanmar Bay of Bengal I N D I A I N D I A B A N G L A D E S H Sittwe
Aizwal I N D I A I N D I A B A N G L A D E S H NH 54 Lawngtlai Myeikwa (IM Border) Kaletwa Myanmar Paletwa Bay of Bengal Kolkata Sittwe 539 km Sea Paletwa 158 km IWT Kaletwa 67 km Road Myeikwa (IM Border) 62 km Lawngtlai 100 km Aizwal 334 km 1260 km Kyauktaw Sittwe Doner_

23 RO-RO terminals at Dhubri and Hatsinghimari
Perishable cargo from Meghalaya and consumable goods for West Garo Hills are transported by road using Jogighopa bridge RO-RO terminals at Duhubri (North Bank) and Hatsingimari (South Bank) on River Brahmaputra will provide direct connectivity between Dhubri and Meghalaya avoiding circuitous road route through Jogighopa DPR for construction of RO-RO terminal at Dhubri at a cost of Rs 30 Crore (aprox) is in final stage DPR for Hatsingimari will be completed by May 2012 Action has been initiated for acquisition of land at Hatsingimari Doner_

24 Slipway facilities at Pandu
A partially built slipway (ship repair facility) of Assam Govt’s exists at Pandu IWAI proposes to develope this slipway on Joint management basis with IWT- Assam, Garden Reach Shipbuilders & Engineers and IWAI. A concept note for this project has been prepared through IL&FS and forwarded to Govt. of Assam for their views /suggestions. Ministry of DoNER has been requested to keep a budgetary provision of Rs. 20 Cr for this project under NLCPR- Central during Doner_

25 Construction of other terminals
IWAI is working out the modalities for movement of FCI foodgrains for PDS through IWT to cater the needs of upper Assam, Arunachal Pradesh and adjoining areas Terminals needs to be developed at Oryumghat, Bogibeel, Matmara, Biswanathghat and Tejpur for unloading foodgrains State Government has been requested to acquire land at identified locations Ministry of DoNER has been requested to keep a budgetary provision of Rs. 10 Cr for road connectivity of these IWT terminals under NLCPR- Central during Doner_

26 Recent Study by RITES IWAI has recently conducted a study through RITES (July 2011) for ‘identification of potential waterways of NER’ 23 river stretches identified State Governments may develop these waterways using own resources/CSS /NLCPR-Central Assam 7 river stretches 405 km Arunachal Pradesh 4 river stretches 311 km Mizoram 3 river stretches 370 km Meghalaya 90km Tripura 2 river stretches 126 km Nagaland 204 km Manipur 1 stretch 60 km Total 23 stretches 1566 km Map Details Doner_

27 Transportation of FCI foodgrains
FCI initiated the action for transportation of 10,000 MT of foodgrain from Kolkata to Tripura via Ashuganj on a trial basis Tender was floated during Feb 2012 which remained non-responsive due to: Small quantity of cargo Wrong jetty selection at Kolkata Very high security deposit Doner_

28 Transportation of coal
NTPC has plan to transport 0.5 MMTPA of imported coal from Bay of Bengal to Bongaigaon by IWT To materilize this transportation terminal & loading/unloading facility at Jogighopa and last mile connectivity from Jogighopa to Bongaigaon by Government funding need to be explored IL&FS-IDC has been requested to prepare the Feasibility Report after making field visit alongwith NTPC, Railways and IWAI officials Doner_

29 Transportation of pipes
ONGC and Oil India Ltd. is to convey their decision for transporting their pipes and other cargo to North –East through IWT mode ONGC & Oil India will have to give a long term commitment of cargo through IWT mode including the details of O-D points MoU needs to be signed between IWAI and these Companies Thereafter they have to float a tender to select the transport operator in consultation with IWAI Doner_

30 Transportation of containers
About 80 TEUs per week traffic exists between Pandu - Kolkata CONCOR, Kolkata inspected the IWT terminal at Pandu Long term commitment is required from CONCOR for transportation of part of their container cargo by IWT Doner_

31 Potential Cargo For 34 Hydel projects (30,000 MW) in AP, MoUs signed
- Reliance, NHPC, Jindal, Athena, NEEPCO etc Construction to continue upto 2030 24 million tonnes of cement and 2 million tonne of steel required upto 2027 ODC and other cargo shall also be transported IWT can be used for at least 40-50% of this IWAI has signed MoU with Jindal & Reliance Doner_

32 Project cargo for Hydel Plants in Arunachal Pradesh
For 34 Hydel projects (30,000 MW) in AP, MoUs signed - Reliance, NHPC, Jindal, Athena, NEEPCO etc Construction to continue upto 2030 24 million tonnes of cement and 2 million tonne of steel required upto 2027 ODC and other cargo shall also be transported IWT can be used for at least 40-50% of this IWAI has signed MoU with Jindal & Reliance

33 Thank you Doner_

34 Recent Study by RITES River State Back 1.Dhaleswari Assam (125 km)
12.Karnafuli Mizoram/ B’desh (180 km) 2.Jia Bharali Assam (60 km) 13.Tuichawng Mizoram (135 km) 3.Buridihing Assam (80 km) 14.Tut Mizoram/ Assam (55 km) 4.Dikhow Assam/ Nagaland (40 km) 15.Kyanshi Meghalaya (30 km) 5.Dhansiri Assam/ Nagaland (25 km) 16.Simsang Meghalaya (35 km) 6.Kopili/Kolong Assam (50 km) 17.Jingiram Meghalaya/ Assam (20 km) 7.Disang Assam (25 km) 18.Gumti Tripura (80 km) 8.Dibang Arunachal / Assam (90 km) 19.Hoara Tripura (46 km) 9.Lohit Arunachal/ Assam (100 km) 20.Tizu Nagaland (42 km) 10.Siang Arunachal/ Assam (50 km) 21.Barak (extn) Manipur (60 km) 11. Subansiri Arunachal/ Assam (111 km) 22.Loktak lake Manipur (lake) Back Doner_

35 Back

36 Optimising utilisation of NW2
Indo- Bangladesh Trade & Transit Protocol which expired on 31st March 2012 renewed for one year only Need to have IWT transit valid for duration of the entire Protocol (10 years) instead of shorter period of 1-2 years Need to link major river ports like Jogighopa, Tejpur, Silghat, Oriyam ghat, Dibrugarh, Karimganj, Badarpur, Ashuganj with multi-modal rail & road links Institutional strengthening of IWT setup in all NE States to utilize Central Sector Scheme for IWT Doner_

37 Project Cargo for Palatana project in Tripura
New Port of Call at Ashuganj made movement of this project cargo feasible 90 consignments transported from Kolkata/Haldia since March 2011

38 IWT Protocol Route-Connectivity of Tripura Through Ashuganj
46 Km Akhaura Agartala

39 Low level jetty at Pandu
Next 39

40 Low level jetty at Pandu
Back 40

41 Cargo vessel in Brahmaputra
Next 41

42 Cargo vessel MV Rajagopalachari
Back 42

43 Dredging in river Ganga
Next 43

44 Hydraulic surface dredger in Brahmaputra
back 44

45 Back 45

46 Next

47 ODC movement in Brahmaputra
Back

48 24 hrs navigation aids in Brahmaputra
back 48

49

50 Champakkara & Udyogamandal canals
KOTTAPURAM N National Waterway-3 17 ALUVA (Kottapuram – Kollam) West Coast Canal Champakkara & Udyogamandal canals River distance Kottapuram - Kollam km Udyogamandal canal 23 km Champakkara canal km Total length km UDYOGAMANDAL CANAL KAKKANAD(CSEZ) 49 KOCHI CHAMPAKKARA CANAL MARADU VAIKOM 47 K E R A L CHERTHALA THANNERMUKKOM LOCK CUM BARRAGE ALAPPUZHA 220 THRIKKUNNAPUZHA THRIKKUNNAPUZHA LOCK GATE Legend Waterway alignment Road Rail Important places Arabian Sea KAYAMKULAM CHAVARA 208 Back KOLLAM 50

51 National Waterway- 4 Kakinada - Puducherry Canals integrated with rivers Godavari and Krishna Length km Notified on DPR completed PIB note submitted to Ministry Cost – 1515 Cr 51

52 Back Development cost- Rs 4209 cr (at 2009 prices)
Status: Notified on , DPR completed, PIB note sent to MoS Back 52