Presentation is loading. Please wait.

Presentation is loading. Please wait.

DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.

Similar presentations


Presentation on theme: "DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate."— Presentation transcript:

1 DPW General Conditions Articles 32 through 37

2 Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate Contract Terminate Contract  34 Subletting or Assigning of Contract  35 Contractor’s Insurance  36 Foreign Materials  37 Hours of Work

3 Article 32 Owner’s Right to Withhold Payment   32.1 The Commissioner may withhold a portion of any Payment due the Contractor that may, in the judgment of the Commissioner, be necessary:   32.1.1 To assure the payment of just claims then due and unpaid to any persons supplying labor or materials for the Work.   32.1.2 To protect Owner from loss due to defective, unacceptable or non-conforming Work not remedied by the Contractor.   32.1To protect the Owner from loss due to injury to persons or damage to the Work or property of other Contractors, Subcontractors, or others caused by the act or neglect of the Contractor or any of its Subcontractors.

4 Article 32 Continued   32.2 The Owner shall have the right to apply any amount withheld under this Article as the Owner may deem proper to satisfy protection from claims. The amount withheld shall be considered a payment to the Contractor.   32.3 The Owner has the right to withhold payment if the Contractor fails to provide accurate submissions of Submittals, up date the status including but not limited to the following: As-Built Drawings, request for information (RFI) log, Schedule, submittal log, Change Order log, certified payrolls and daily reports and all other requirement of the Contract Documents.

5 Article 33 Owner’s Right to Stop Work or Terminate Contract Section 33.1 Right to Stop Work   33.1 The Commissioner shall have the authority to suspend the Work wholly or in part, for such period or periods as the Commissioner considers being in the best interests of the State, or in the interests of public necessity, convenience or safety. During such periods the Contractor shall store all materials and equipment, in such a manner to prevent the materials and equipment from being damaged in any way, and the Contractor shall take precautions to protect the Work from damage.

6 33.1 Right to Stop Work Summarized   33.1.1 (If the delay is deemed excessive) …the Contractor shall submit to the Commissioner in writing a request for a Contract adjustment within 7 Days of receipt of the notice to resume Work...   33.1.2 The Commissioner shall evaluate any such requests received… Commissioner will make a reasonable adjustment, excluding profit, of the Contract terms…   33.1.3 No Contract adjustment will be made unless the Contractor has submitted the request for adjustment within the time prescribed.   33.1.4 No Contract adjustment will be made under this Article to the extent that performance would have been suspended or delayed by any other cause within the Contractor’s control or by any factor for which the Contractor is responsible under the Contract; or that such an adjustment is provided for or excluded under other term or condition of this Contract.

7 Article 33.2 Termination   33.2 …the State may terminate the Contract whenever the Commissioner determines … that such termination is in the best interests of the State. Any such termination shall be effected by delivery to the Contractor of a written Notice of Termination specifying the extent to which performance of Work under the Contract is terminated, and the date upon which such termination shall be effective.   33.2.1 …the Contractor shall be entitled to reasonable compensation as determined by the Commissioner, however, no claim for lost Overhead or profits shall be allowed.   33.2.2 All Work and materials obtained by the Contractor for the Work, that have been incorporated into the Work, inspected, tested as required, accepted by the Commissioner, and paid for by the State, shall become the property of the State.   33.2.3 Materials obtained by the Contractor for the Work… that are not incorporated into the Work, shall, at the option of the Commissioner, be purchased from the Contractor at actual cost as shown by receipted bills. To this cost shall be added all actual costs for delivery at such points of delivery as may be designated by the Commissioner, as shown by actual cost records.   33.2.4 Termination of the Contract shall not relieve the Contractor or its Surety of their responsibilities for the completed Work, nor shall it relieve the Contractor’s Surety of its obligations to ensure completion of the Work and to pay legitimate claims arising out of Work.

8 Article 34 SUBLETTING OR ASSIGNING OF CONTRACT   34.1 The Contract or any portion thereof, or the Work provided for therein, or the right, title, or interest of the Contractor therein may not be sublet, sold, transferred, assigned, or otherwise disposed of to any person, firm, or corporation without the written consent of the Commissioner.   34.2 No person, firm, or corporation other than the Contractor to whom the Contract was awarded shall be permitted to commence Work at the site of the Contract until such consent has been granted.

9 Article 35 Contractor’s Insurance General Information  When in doubt ask…  Procurement handles the initial certificate collection  Need to get certificates from subs, unless contractor is covering subs under his policy  State is to be named as an also insured or loss payee on all policies  Contractor(s) must keep all insurances in force for the duration  Contractor(s) responsible for all costs and all deductibles.

10 Types of Insurance Required  Commercial General Liability  Explosion, collapse, and underground (XCU) or hazardous material riders added as appropriate for the project  Owners & Contractor’s Protective Liability  Automobile Liability  Excess Liability  Workers’ Compensation & Employer’s Liability  Builder’s Risk  Inland Marine/ Transit Insurance

11 Article 36 Foreign Materials   36.1 Preference shall be given to articles or materials manufactured or produced in the United States, Canada, and Mexico, (the members of the North American Free Trade Agreement (NAFTA)); and the products shall meet all of the referenced standards and Specifications for conditions of performance, quality, and price with duty being equal.   36.2 Only articles or materials manufactured or produced in the United States, Canada, and Mexico, (the members of the North American Free Trade Agreement (NAFTA)), will be allowed. The foregoing provisions shall not apply to foreign articles or materials required by the Contract Documents.

12 Article 37 Hours of Work   37.1 No person shall be employed to work or be permitted to work more than eight (8) hours in any Day or more than forty (40) hours in any week for any Work provided in the Contract, in accordance with Connecticut General Statute Section 31-57. .  37.2 The operation of such limitation of hours of work may be suspended during an emergency, upon the approval of the Commissioner, in accordance with Connecticut General Statute Section 31-57.


Download ppt "DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate."

Similar presentations


Ads by Google