Download presentation
Presentation is loading. Please wait.
Published byMilton Byrd Modified over 10 years ago
1
Brief Synopsis of Project Hickahala Creek Hickahala Creek Pipeline Protection Project at milepost 347.64 Tate County, Senatobia, MS Designed by Submar, Inc and River Research and Design, Inc. Installed, & Monitored by: Submar Incorporated 805 Dunn St., Houma, LA www.R2D-ENG.com | www.Submar.com
2
Hickahala Creek Pipeline Protection Project at milepost 347.64 Tate County, Senatobia, MS (Looking across and downstream in this view)
3
Looking Upstream - September 2001 - Pipeline Exposed 10 Feet
4
Looking Upstream - September 2002 - Pipeline Exposed 25 Feet
5
Looking Upstream - March 2003 - Pipeline Exposed 50 Feet
6
Looking Downstream - March 2003 - Pipeline Exposed 50 Feet Main stream force & thalweg of stream aimed underneath exposed pipe; note other pipeline exposed.
7
Looking Upstream - March 2003 - Long Straight Reach Thornton Creek (tributary stream; bottom left) feeding into Hickahala Creek (top right)
8
Looking Upstream - April 2003 “and the news is not good"
9
Looking Upstream - the entire stream is trying to flow underneath the pipeline
10
Looking Downstream (standing Upstream) - August 2003 Typical Tourist on Safari in Mississippi
11
Note Pipe Tie-Down Structure
12
July 2003 After May Flood (overbank, picture looking away from stream) Floodwaters Carry Sand 1000 Feet into Farmer's Field
13
August 2003 - Aerial Photos - *Note* Upstream Straight Stretch (bottom right) Pipe Exposed on Overbank, Large Sand Splay in Farmers Field (top right)
14
Looking Downstream - April 2003 Pipe is Vulnerable to Impact from the Next Large Floating Tree. Bank is a mess (technical term)
15
September 5th, 2003 Portable Cofferdams used to Dewater the site for Pipeline Recoating; The Green Portion of the Pipeline is New, Pipe was Cut, and New Section Installed at a Lower Elevation
16
Pre-tested Pipe
17
Hickahala Creek Conceptual Drawings - Total Mats (182)
18
Looking Upstream into Tributary Widening Channel to Accommodate LPSTP
19
The Key Trench is a Thing of Beauty!
20
From Key Looking Downstream in Tributary Toward Hickahala Creek - September 17th, 2003 - Fresh LPSTP
21
Looking Upstream into Tributary Longitudinal Peaked Stone Toe Protection (LPSTP)
22
LPSTP Under Construction Looking Downstream - September 17th, 2003
23
September 17th, 2003 Mat Installation
24
September 17th, 2003 Installing Mat
25
Looking Across and Upstream - September 22nd, 2003 High Water Event During Construction
26
High Water Event During Construction September 22nd, 2003
27
September 26th, 2003 *Note* Bank Paving (left), LPSTP (5 tons/ft; middle), Key (right)
28
September 26th, 2003 *Note* Bank Paving (left), & LPSPT (right)
29
September 27th, 2003 - Mat Installation Complete
30
Looking Upstream - September 30th 2003 Installation Complete
31
Project Completed
32
Looking Upstream - November 24th, 2003 Floodwaters Crested 1 Foot Below Top of Levee
33
Before
34
After
35
Looking Upstream - February 5th 2004 - Flood
36
February 5th, 2004 Flood Flow Left to Right
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.