IMPROVEMENT PLAN UPDATESPO Richard Latham Bridget Eggers Tyler Brent Valeria Gonzalez
2
PRESENTATION OBJECTIVES Summarize what was achieved last semester Present project timeline Updates on activities Mixing Prep Activities Mixing Clean Up Kaizen Scaling Process Improvement Operations Management Standard Work Implementation
3
MSD I SUMMARY
4
PROJECT PLAN – MSD II
5
ENGINEERING REQUIREMENTS
6
MIXER WORKER JUSTIFICATION PROJECT Objective: To make a decision about whether a second operator is justifiable in the frozen cookie mixer process (for cookies with inclusions). Engineering Requirements: Characterization of all process steps Throughput Implemented solutions are consistent across all crews and shifts Tools that make system run smoothly Management approval Test Method: Cycle time improvement
7
MIXER WORKER JUSTIFICATION PROJECT Current Progress: Videos taken for Dads, Ultimate w/ nuts, Sub Shop w/ nuts Process analysis completed for one operator Job elements created for two workers based off reasonable assumptions Job element comparison charts created for one worker vs two workers
8
Dads 1 operator26 min 15 sec 2 operators15 min 9 sec73% increase
9
Sub Shop W/ Nuts 1 operator33 min 34 sec 2 operators17 min 38 sec90% increase
10
Ultimate W/ Nuts 1 operator27 min 50 sec 2 operators16 min 8 sec72% increase
11
MIXER WORKER JUSTIFICATION PROJECT Next Steps: Experiment with two workers Create standard job element sheet for two workers using operator feedback Present findings to management
12
SANITATION KAIZEN Objective: Create a system that allows the sanitation employee to be at the mixer at the right time. Engineering Requirements: No food safety, ergonomics, quality impacts Throughput Characterization of all process steps Implemented solutions are consistent across crews and shifts Tools that make system run smoothly Management approval Test Method: Mixer wait time per week (see Mixer Operator Time Sheet)
13
SANITATION KAIZEN Current Progress: Interviewed Jim Roode about sanitation processes Agreed that sanitation can work on a schedule Suggested ideal state would be a one to two hour notice Sanitation employee will fill out sanitation section of the Mixer Operator Time Sheet Next Steps: Map information flow scenarios for mixer sanitation Collect data on sanitation cycle time Update schedule to include sanitation Present findings to management
14
RECIPE MODIFICATION PROJECT Objective: Increase usability of recipe by removing the need for calculations to find the number of bags/boxes needed. Engineering Requirements: Characterization of all process steps Implemented solutions are consistent across crews and shifts Tools that make system run smoothly Sustainable solution methods Management approval Test Method: Does the sheets make sense to the operator? - Yes/No Are the sheets being utilized regularly? - Weekly Team Leader Audit
15
OPERATIONS MANAGEMENT MIXING Objective: Make mixer its own resource and develop a single daily mixer schedule. Engineering Requirements: Characterization of all process steps Tools that make system run smoothly Implemented solutions are consistent across crews and shifts Management approval Test Method: Planned vs Actual number of batches (see Mixer Operator Time Sheet)
16
OPERATIONS MANAGEMENT MIXER Current Progress: Collecting mixer cycle times for frozen and commercial cookies Created preliminary mixing schedule Down time, reason, sanitation Trained mixer operators on mixer tracking sheet Next Steps: Collaborate with frozen and commercial schedulers on mixer schedule Test and validate schedule
17
OPERATIONS MANAGEMENT DIVIDER Objective: Create changeover matrix for divider for use in scheduling. Engineering Requirements: Characterization of all process steps Tools that make system run smoothly Implemented solutions are consistent across crews and shifts Management approval Test Method: Was changeover time accounted for in the weekly schedule? – Yes/ No Does the matrix clearly provide the changeover time between different cookie types? - Yes/No
18
OPERATIONS MANAGEMENT DIVIDER Current Progress: Collect reasons for changeover Next Steps: Collect times for changeover Create changeover matrix Present matrix to scheduler
19
STANDARD WORK IMPLEMENTATION Objective: Create work instructions for revised process improvements Engineering Requirements: Characterization of all process steps Implemented solutions are consistent across crews and shifts Tools that make system run smoothly Sustainable solution methods Management approval Test Method: Do the updated work instructions make sense to the worker? – Yes/No Are they being utilized regularly? – Weekly Team Leader Audit