INFO 638Lecture #81 Software Project Management Cycle plan and build INFO 638 Glenn Booker
2
INFO 638Lecture #82 Cycle Planning Cycle planning is performed like in traditional project management (TPM), but there are key differences In APF, the planning is done in detail only for the next cycle – not the entire project at once APF planning may or may not use project software; it could be done with more informal tools
3
INFO 638Lecture #83 Cycle WBS In the APF scope definition, we had to define the WBS down to what is called mid-level Essentially, this means we defined work down to the cycle level, then stopped high level planning Now we pick up from there for the first (or later iterations, next) cycle
4
INFO 638Lecture #84 Top to Mid Level WBS Fig. 15.2 Define this level of WBS in the APF Scope phase; now use one or more subfunctions as the scope of one cycle, and define activities and tasks to implement that cycle in more detail.
5
INFO 638Lecture #85 Beware Micromanaging With such a small scope to be planned, it’s easy to micromanage APF projects Might be good to micromanage if very novice staff, or previous projects had serious trouble with estimation Otherwise, avoid by setting a limit on the smallest task – 4 hours, 8 hours, etc.
6
INFO 638Lecture #86 Estimate Task Duration This follows the same estimation method you’d use for any other project Estimate the reasonable time needed to complete each task, given normal levels of productivity
7
INFO 638Lecture #87 Estimate Other Resources Consider whether other resources are needed for this cycle Facilities Equipment Money Materials Failure to plan for long lead items can cause serious problems in APF
8
INFO 638Lecture #88 Sequence Tasks Keeping the time box in mind (the overall time limit for the cycle), sequence the tasks to be done and assign resources to each of them That’s it for planning a cycle Pretty painless, huh?
9
INFO 638Lecture #89 Cycle Build It is assumed that Cycle Plan is done by one person or part of the team Cycle Build requires the whole team’s presence to refine the schedule if needed Identify specific resources for each task, and ensure conflicts are resolved and workload is balanced
10
INFO 638Lecture #810 Cycle Build Typically the smallest time unit needed is a half day’s work (4 hours) Less than that isn’t worth planning, and leads to micromanagement Arrange tasks in a Pert-like format Check resource availability, both people and facilities
11
INFO 638Lecture #811 Work Packages Identify critical tasks for which a work package might be needed Could use formal critical path, but key tasks should be easy to find Can also use work packages for high risk tasks, or those which require previously unknown skills
12
INFO 638Lecture #812 Build Cycle Functionality Start building the functionality promised for this cycle, following the plan just developed During the cycle, daily stand-up meetings are used for status Stand up so it doesn’t drag on forever Monitor the system scope & their priorities, and issues identified
13
INFO 638Lecture #813 Scope Bank The scope bank is used as a change control tool for the functionality of the system It should be visible to all, including the customer Its contents are reviewed at each Client Checkpoint phase
14
INFO 638Lecture #814 Issues Log An issues log is maintained to flag and track problems It should be visible to the development team, and is continually updated
15
INFO 638Lecture #815 Scope Matrix This isn’t a separate tool It just emphasizes that entries to the Scope Bank or Issues Log need to be prioritized when they are entered Discuss the impact of scope changes, and how resolving issues might be influenced by project priorities
16
INFO 638Lecture #816 Daily Team Meetings As noted earlier, daily team meetings are the norm in each cycle Keep them very brief (15 min) Focus on status with respect to the plan, and if behind schedule, describe what plan there is to get caught up Scope changes and problems are noted, but not discussed in this meeting
17
INFO 638Lecture #817 Status Reporting Daily status is posted in the main project location (“war room”) Brief written status reports for the customer are prepared at the end of each cycle Longer reports to senior management are prepared at the end of each version