Town of Westerly Pavement Improvement Plan 2009.  Determine current pavement condition.  Identify and prioritize needed repairs.  Coordinate with RIDOT.

Similar presentations


Presentation on theme: "Town of Westerly Pavement Improvement Plan 2009.  Determine current pavement condition.  Identify and prioritize needed repairs.  Coordinate with RIDOT."— Presentation transcript:

1 Town of Westerly Pavement Improvement Plan 2009

2  Determine current pavement condition.  Identify and prioritize needed repairs.  Coordinate with RIDOT projects.  Assess available funding.  Select repairs to fit budget framework.  Prepare bid documents and advertise.

3 Current Pavement Condition

4 Pavement Management Program  Initial inventory and condition survey prepared by Beta Group in 2007.  All roads are rated 0-100 with 100 best.  Database maintained and kept up to date by Engineering Department.  Software automatically predicts pavement condition based on model of deterioration over time.

5 RSR (Road Surface Rating) Network RSR = 69

6 Network Backlog (2009) Repair Method Length (mi) Estimated Cost % Reclamation3.92$1,372,8302.77 Mill & Overlay 9.52$2,415,7816.72 Level & Overlay 55.24$6,321,26139.00 Crack Seal 41.29$227,19129.15 Defer31.67$022.36 Total141.65$10,337,062100.00

7 Network Backlog By Repair

8 RIDOT Planned Projects

9 RIDOT Projects

10  Route 91 1R, Contract 1 - High Street (Route 3) to Larry Hirsch Lane  Route 91 1R, Contract 2 – Larry Hirsch Lane to Church St. (Route 216)  Shore Rd. Resurfacing – Ocean View Hwy. to Post Rd.  Weekapaug Bridge  Elm St. & Beach St. (Main St. to Clark St.)  Railroad Ave., Dixon St., & West St.

11 Available Town Funds  General Fund FY2009 - $450,000  Water Fund FY2009 - $750,000 (Transmission Main Project)  General Fund FY2010- $200,000 Total $1,400,000

12 Proposed Town Projects

13 Town Projects Total = 7.75 Miles

14 Westerly 2009 Projects General Fund ($650,000 budget)  Crack Sealing – $50,000 (Various Roads)  Level & Overlay - $110,000 (Pound Rd., Hiscox Rd. & Wampanoag Ave.)  Mill & Overlay - $370,000 (Bellevue Ave., John St., Narragansett Ave., Raymond St., & Ward Ave.) Total - $530,000 est.

15 Westerly 2009 Projects Water Fund ($750,000 budget)  Mill & Overlay - $460,000 est. ( Terrapat Dr., Perkins Ave., Pond St., Pierce St., Industrial Dr., Narragansett Ave., & Summer St.)

16 2009 Road Improvements Predicted RSR = 71

17 RI – LEAP Funds (Local Equity Aid Program)  $358,000 (Federal) + $150,000 (State) = $508,000 Total  Cross St. Pavement & Sidewalks = $525,000 est. $525,000 est.

18 Additional Planned Projects  Old Hopkinton Road  Canal St./White Rock Road Rehabilitation  Bay Street Drainage/Pavement Restoration  Bradford Streetscape Project  Misquamicut Drainage Extension  Chip Sealing Program


Download ppt "Town of Westerly Pavement Improvement Plan 2009.  Determine current pavement condition.  Identify and prioritize needed repairs.  Coordinate with RIDOT."