Download presentation
1
9/7/2012 MBS UU
2
Lahore Metro Bus System
Dr Nasir Javed CEO: The Urban Unit Pakistan 9/7/2012 MBS UU
3
MBS Lahore is still in the phase of execution and hence most of the presentation is either Planning or future Please criticize & Advise as well 9/7/2012 MBS UU
4
City Lahore The capital of Punjab, a city of around 9m, with a growth rate of around 3% 9/7/2012 MBS UU
5
Vision The Vision is to provide the city of Lahore with a high quality Public Transport System, with a road based mass transit system, in the medium term. 9/7/2012 MBS UU
6
Basics Estimated Project Cost ~ Rs. 30 Billion
Total Length 32 km (Elevated portion – 8.5 km) Median Side BRT with one each lane each direction Level Boarding for Passenger from Station Commercial Speed of 25 Km/h & reliability of service
7
Length The Route (Green Corridor) is 32km long, running south to north across the city, on one of the four primary arteries of the city 9/7/2012 MBS UU
8
Dedicated Route all along, except 8 traffic intersections
9/7/2012 MBS UU
9
Elevated Portion Around 7 km is elevated, which is because of the constraints on widening the Road 9/7/2012 MBS UU
10
Stations These are on the sides of the Route 3 platforms on each side
Sliding Doors 9/7/2012 MBS UU
11
9/7/2012 MBS UU
12
BRT Station layout AREA FOR TURNSTILES STOP BAR
2.5m WIDE COLOURED PAVEMENT PORTION FOR LATERAL GUIDANCE RUBBER PADDED SURFACE PLATFORM AREA
13
Pedestrian Bridge & Access to Station & ticketing booth
9/7/2012 MBS UU
14
ARTICULATED BUS (Green Line)
15
Capacity It is designed to carry around 18,000 passengers per hour per direction 9/7/2012 MBS UU
16
E Ticketing We are introducing e ticketing , but only limited to the MBS for the time being 9/7/2012 MBS UU
17
ITS There are 11 traffic signals on the route that is at grade
These signals are being upgraded to make these Intelligent, providing Bus priority and managing allied traffic as well. Control Center is being set up 9/7/2012 MBS UU
18
Command & Control Center
9/7/2012 MBS UU
19
Overall Route Network-Network Integration
Three Types of Bus Operation/Routes with fare integration Main Road/Trunk/BRT Present Future Ring Road and Sub Urban Bus Feeder Bus Transfer facilities
20
Communication Strategy
9/7/2012 MBS UU
21
That makes Land acquisition easy
9/7/2012 MBS UU
22
Institutional Development Metro Bus Authority
23
Thank you 9/7/2012 MBS UU
24
9/7/2012 MBS UU
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.