IWTP Facility
2
Holes Drilled for Detailed Blast Drilling and Blasting for final grade prior to construction in 2011
3
Building Foundations
4
Floor Slab Preparation
5
Backfill Building Foundations
6
1 st Column Erection
7
Steel Erection & Roof Girders
8
Building Ready for Cladding
9
Inner Skin Complete, Start Exterior Cladding
10
IWTP Cladded & Roofed
11
Piping Installation
12
Mechanical Installation
13
Equipment Placement
14
Electrical Control Room
15
Settling Pond – Wall Liner Application Wall Liner Application
16
Settling Pond – Wall Liner Application Wall Liner 2 nd Coat
17
Settling Pond – Floor Liner Application Floor Liner 1 st Coat
18
Settling Pond - Complete
19
Settling Pond & IWTP IWTP Settling Pond
20
Completed IWTP and associated infrastructure Completed IWTP Settling Pond Sludge Pit Exfiltration Pond Power Generator & Diesel Fuel Tanks Portal Creek Diversion