JONES RIVER BASIN
4
PROJECT GOALS Document existing flow conditions and water supply management Conduct new analyses to forecast the feasibility of providing fish passage at Forge Pond Dam under different scenarios of flow management and structural modifications
5
FORGE POND
6
SILVER LAKE NATURAL OUTLET
7
FORGE POND DAM Spillway Walkway atop 3 stoplog bays Access road atop 3 culvert openings Forge Pond
8
FORGE POND DAM
9
LAKE STREET CULVERT & ACCESS ROAD
10
FISHERY RESOURCES
11
TARGET SPECIES – River Herring Blueback herring Alosa aestivalis Alewife Alosa pseudoharengus
12
OTHER SPECIES American eel Anguilla rostrata Under review as a threatened species under ESA Tidewater mucket Leptodea ochracea Eastern pondmussel Lagumia nasuta FRESHWATER MUSSELS Species of Special Concern in MA
13
HABITAT REQUIREMENTS Preliminary Summary of River Herring Habitat Assessment at Silver Lake (2008-09)
14
PASSAGE REQUIREMENTS –Depth Targets for herring: ADULTS 8-12 inches MIN 6 inches JUVENILES 4-8 inches MIN 2 inches
15
PASSAGE REQUIREMENTS –Velocity Passage Success Rates for Alewife under Varying Velocities and Distances
16
PASSAGE REQUIREMENTS –Flow Timing Timing of Important Life Cycle Events for Target Species
17
WATER SUPPLY OPERATIONS
18
SILVER LAKE WATER SUPPLY SYSTEM Summary of Brockton Water Supply Sources *Increases annually up to 4.07 mgd. Not included in totals. **110 of systemwide safe yield via a 1995 DEP ACO.
19
SILVER LAKE LEVEL – Average 43.0 43.5 44.0 44.5 45.0 45.5 46.0 46.5 47.0 47.5 48.0 1-Jan1-Feb1-Mar1-Apr1-May1-Jun1-Jul1-Aug1-Sep1-Oct1-Nov1-Dec Silver Lake Elev. (ft, NGVD 29) Forge Pond Dam Spillway Elev. (47.6 ft, NGVD 29) Silver Lake Berm Elev. (45.9 ft, NGVD 29) When SilverLake elevation drops below the natural outlet, it has been observed that water flows from Forge Pond into Silver Lake resulting from groundwater flow into Forge Pond. When theForge Pond water level exceeds the spillway crest, water is passed to Jones River. Spawning adults immigrating Juveniles rearing Juveniles emigrating Period of Record: 1996-2012
20
SILVER LAKE LEVEL – 2011 with Diversions
21
SILVER LAKE LEVEL – Duration Curves Spring Immigration Fall Emigration
22
AQUARIA PLANT – Cost Analysis Overall Cost of Aquaria Water per Amount Purchased by Brockton (2012 example) Fixed Rate = $167,480 per 0.1 mgd (total annual cost of $5,861,800 for 2012 for 3.5 MGD) Variable Rate = $1.23 per 1,000 gallons used Excess Rate = $0.60 per 1,000 gallons used
23
FISH PASSAGE ALATERNATIVES
24
FISH LADDER – Alaska Steeppass
25
FISH LADDER – Plan View
26
FISH LADDER – Detail View
27
NATURE-LIKE BYPASS CHANNEL
28
Elevation Profile of Potential Bypass Channel
29
DAM REMOVAL CONSIDERATIONS Water Supply Sediment Infrastructure Wetlands Historical Resources etc. Former Wapping Road Dam
30
DAM REMOVAL – Modeling Approach
31
NEXT STEPS Required flows for each alternative Feasibility of flow availability Budgetary cost estimates Selection of preferred alternative Conceptual designs LATER PHASES Detailed designs Permitting Implementation Monitoring