NCTD/SANDAG Project Update Capital Improvement Program Bill Prey, P.E., LOSSAN Corridor Director San Diego Association of Governments RELATED TO AGENDA.

Similar presentations


Presentation on theme: "NCTD/SANDAG Project Update Capital Improvement Program Bill Prey, P.E., LOSSAN Corridor Director San Diego Association of Governments RELATED TO AGENDA."— Presentation transcript:

1 NCTD/SANDAG Project Update Capital Improvement Program Bill Prey, P.E., LOSSAN Corridor Director San Diego Association of Governments RELATED TO AGENDA ITEM W1

2 Current Rail Projects 19 projects now in development 11 funded through construction $467 million in funding $915 million estimate cost at completion Schedule currently funded through 2016 2

3 3 North Coast Corridor Program

4 In Design: Batiquitos Lagoon Double Track 4 Batiquitos Lagoon Double Track $3 million Funded through preliminary engineering 2.7 miles of second track Anticipated to reach 60% design Feb. 2015

5 In Design: Elvira to Morena & SD River Bridge 5 Elvira to Morena Double Track $78.7 million 2 miles of second track in City of San Diego Construction start 2015 San Diego River Bridge $9.4 million Realignment of bridge 0.9 miles of second track San Diego River Bridge Elvira to Morena

6 Sorrento Valley Double Track North of Sorrento Valley Station $34 million 1 mile of second track Construction start Late 2013/Early 2014 6 Near Construction: Sorrento Valley Double Track Sorrento Valley Double Track

7 San Onofre to Pulgas Double Track Camp Pendleton area Longest stretch of double track 4.2 miles $38 million Construction start Fall 2013 7 Near Construction: San Onofre Double Track

8 Near Construction: Los Peñasquitos Lagoon 8 Los Peñasquitos Lagoon Bridge Project $25 million Recipient of $14 million TIGER grant from US DOT 4 wooden bridges to be replaced with concrete bridges Construction begins mid-2014 for one year

9 Near Construction: Oceanside Transit Center 9 Platform Improvement Project $19.5 million Add third track and new platform Construction start TBD Level boarding considerations Oceanside Transit Center

10 In Construction: Santa Margarita River Bridge 10 Santa Margarita River Bridge North of Oceanside $41 million 0.8 miles Deck now replaced Est. completion April 2014 Sorrento to Miramar 1 Tecolote Crossover

11 In Construction: Sorrento to Miramar Phase 1 11 Sorrento to Miramar Double Track Phase 1 South of Sorrento Valley Station $44 million 1.4 miles Estimated completion January 2014

12 Washington Crossover Near Completion: Tecolote/Washington Crossovers Tecolote/Washington Street Crossovers Facilitates trains passing north of Downtown San Diego $11 million Tecolote: Completed September 2013 Washington: Completion slated in October 2013 Tecolote Crossover

13 Near Completion: San Luis Rey Transit Center 13 San Luis Rey Transit Center New bus transit center $9 million SANDAG construction completion October 2013 NCTD communications work through early 2014 Bus operations to begin in February 2014 Sorrento to Miramar 1 Santa Margarita River Bridge

14 Other SANDAG Initiatives  Station Parking Prioritization Study  Santa Fe Depot Study – in support of Convention Center COASTER station  Level Boarding Analysis 14

15 LOSSAN Coastal Rail Corridor Capital Improvement Projects 15 QUESTIONS & ANSWERS More Information: KeepSanDiegoMoving.com/LOSSAN