Download presentation
1
Inspection & Test Overview suite412
2
Why does an electrical installation require Inspection and Testing?
BS 7671:2001 Every installation shall, during erection and on completion before being put into service be inspected and tested to verify, so far as is reasonably practicable, that the requirements of the Regulations have been met suite412
3
Before being put into service
“It’s ok misses we've finished the electric's, we've put the supply on”. “be back next week to test it” Simple: If it has not been inspected and tested, it should not be energised. No discussion - No connection! suite412
4
The inspection shall be made to verify
that the installed electrical equipment is: (i) in compliance with Section 511 compliance with standards - British Standards or, Harmonized Standard (ii) correctly selected and erected in accordance with the Regulations (iii) not visibly damaged or defective so as to impair safety suite412
5
Certification suite412
6
Every Inspection and Test must be recorded on the appropriate
certificate suite412
7
The Installation Certificate
“Where do I use it?” suite412
8
include a new circuit For new installations
For alterations or additions that include a new circuit suite412
9
The Installation Certificate
“what does it consist of?” suite412
10
Installation address - Must include post code
Details of client Installation address - Must include post code Description and extent of the installation Signatories those with a responsibility for (i) The design (ii) The construction (iii) The inspection and testing Recommend date for next inspection suite412
11
THE DESIGNER Who recommends the date for the next
inspection (Periodic) ? THE DESIGNER suite412
12
THE INSPECTOR Who recommends the date for subsequent
inspections and tests (Periodic) ? THE INSPECTOR suite412
13
SUPPLY CHARACTERISTICS AND EARTHING ARRANGEMENTS
TN-C (of specialist nature) TN-S TN-C-S TT IT (of specialist nature) suite412
14
Number and type of live conductors
whether the supply is a.c. or d.c. number of phases number of poles suite412
15
Nature of Supply Parameters
nominal voltage U/Uo (V) Fixed nominal frequency, f (Hz) Fixed prospective fault current, Ipf (kA) external loop impedance Ze () suite412
16
Prospective Fault Current (Ipf) kA
May be obtained by Measurement Calculation Enquiry Public Electricity Supply (PES) suite412
17
External loop impedance Ze
May be obtained by Measurement Calculation Enquiry suite412
18
Supply Protective Device Characteristics (PES)
Type i.e. BS 1361 Type 2, BS 88 Nominal current rating (A) suite412
19
Particulars of installation referred
to in the certificate Means of earthing Maximum demand (Not rating of service head fuse) Details of earth electrode resistance if applicable suite412
20
Review - Characteristics of Supply
The following characteristics of the supply or supplies, from whatever source shall be determined by calculation, measurement, enquiry or inspection suite412
21
The nature of the current and frequency
The nominal voltage/s The nature of the current and frequency The prospective short circuit current Earth fault loop impedance Ze Maximum demand after diversity Type and rating of overcurrent device at the origin of the installation suite412
22
Main Protective Conductors
Earthing Conductor Material Cu - copper etc c.s.a Connection verified (low resistance ohmmeter) suite412
23
Main Equipotential Bonding Conductors
Material Cu - copper etc c.s.a Connection verified (low resistance ohmmeter recommended maximum value 0.05) suite412
24
BS /BS EN Number Number of Poles Current Rating Voltage Rating
suite412
25
Main Switch or Circuit Breaker
BS Type and Number of Poles Current rating (A) Voltage rating Fuse rating or setting Location RCD In (mA) and operating time (mS) at In suite412
26
Comments on Existing Installation
To be used for alterations or additions suite412
27
Schedule of items inspected
Refer to Schedule Common to both Installation & Periodic Inspection Report suite412
28
The Visual Inspection Footnote to Regulation 711-01-01
Chapter 71 Initial Verification Footnote to Regulation Precautions shall be taken to avoid danger to persons and to avoid damage to property and installed equipment during inspection and testing suite412
29
The Visual Inspection 712 Inspection
Inspection shall precede testing and shall normally done with that part of the installation under inspection disconnected from the supply suite412
30
Safe Isolation Test equipment to GS 38 Fused Leads Finger Guards
Probes 4mm max pref 2mm max suite412
31
Schedule of Test Results
Refer to Schedule Common to both Installation & Periodic Inspection Report suite412
32
Periodic Inspection Report (PIR)
Change of use or ownership As a result of damage. Fire - Flood etc Electrical overloading To ensure compliance/continued compliance with the Regulations Mortgage/Insurance request Local bylaws - Places of public entertainment - Theatres/Cinemas etc suite412
33
Periodic Inspection Report (PIR)
Some areas common to Installation Certificate, i.e. Details of client and installation Recommended next inspection date Signature of competent person Supply characteristics Particulars of installation suite412
34
Schedule of inspection
(PIR) continued Schedule of inspection Schedule of test results suite412
35
Major Differences Estimated age of installation?
Evidence of alterations or additions? Are there records available? Extent and limitations Observations and recommendations suite412
36
Extent and Limitations
Extent - Details indicating what part/s of the installation will be inspected and tested Limitations - State exactly what items are excluded, i.e. portable appliances, fire alarm systems, emergency lighting, cctv, door entry systems, smoke detectors etc. suite412
37
Departures from BS 7671 must be allocated a numerical code
1. requires urgent attention 2. Requires improvement 3. Requires further investigation 4. Does not comply with BS imply that installation is unsafe suite412
38
Minor Works An alteration or addition to an existing installation that does not include the addition of a new circuit, i.e. spur to radial or ring circuit etc. suite412