Construction Flowchart
Ground Anchoring Work Preliminary Fabrication in Workshop Setting Out Coring ( Optional ) Drilling Assembly on Site Homing/Installation Grouting Grout Cube Test Stressing De - Tensioning
2
Construction Flowchart
Ground Anchoring Work (2 Layers) Excavation until 1st layer elevation Excavation until 2nd layer elevation Setting Out Setting Out Coring ( Optional ) Coring ( Optional ) Drilling Drilling Homing/Installation Homing/Installation Grouting Grouting Grout Cube Test Grout Cube Test Stressing Stressing
3
GROUND ANCHORING WORK STAGES
4
GROUND ANCHORING WORK STAGES
5
GROUND ANCHORING WORK STAGES
6
GROUND ANCHORING WORK STAGES
7
GROUND ANCHORING WORK STAGES
8
GROUND ANCHORING WORK STAGES
9
STAGE 1 - EXCAVATION WORK
1st stage of site excavation (for 1st layer anchors installation) 2nd stage of site excavation (after completion of 1st layer anchors)
10
STAGE 2 - DRILLING WORK Drilling in progress
11
STAGE 3 - FABRICATION WORK
Tendon being fabricated Fabricated tendon
12
STAGE 3 - FABRICATION WORK
Fabricated Tendon Fabricated tendon
13
STAGE 4 - INSTALLATION WORK
Permanent anchor being installed (Long Stoorage Kali Item Project) Temporary tendon being installed/homed (Plaza Asia & Sudirman Mansion Project)
14
Grout pump used for anchor grouting
STAGE 5 - GROUTING WORK Grout pump used for anchor grouting Grout cube samples
15
Completed anchor after stressing
STAGE 6 - STRESSING WORK Anchor being stressed Completed anchor after stressing