COMBINED HEAT AND POWER STEERING COMMITTEE February 26, 2014
2
COMBINED HEAT AND POWER PROJECT Grant Status Workplan, Project Schedule, and Milestone Summary Work Group status Work Group Meeting #1 Agenda KAM Conference Breakfast Meeting Agenda Break-out Session Day 1 Break-out Session Day 2 Steering Committee Next Meeting Date and Agenda
3
SEP AND TAP GRANT STATUS MOA for KPPC CHP SEP is moving forward at DEDI SE CHP TAP funding process is ongoing
4
WORKPLAN Draft Workplan documents have been submitted to DOE outlining phases and goals of the project. KPPC was instrumental with these efforts! Phases include: Program Development and Planning Implementation of Outreach & CHP Screening and Feasibility Program Review Deliverables
5
PROJECT SCHEDULE AND PARTNER ROLES The Project Schedule outlines roles and responsibilities for the primary grant project partners. DEDI will conduct grant management and general oversight for SEP and is a sub- awardee for TAP KAM will be responsible for meeting logistics and channel information to keep industry engaged. KPPC will become the in-state technical assistance expert SE CHP TAP will train KPPC for screening and feasibility and ensure a consistency of efforts and technical transfer between states and administer the TAP grant
6
MILESTONES Some milestones for the project include: At least 4 CHP Workgroup meetings – (likely to be several more) KY CHP Action Plan (2) End User Workshops (1) CHP Webinar (4) Industry Screenings (2) Feasibility Analyses (1) Lessons Learned Webinar
7
CONFIRMED WORKGROUP MEMBERS Confirmation letters were sent to these workgroup members February 18 th.
8
WORKGROUP MEMBERS CONTINUED
9
First Work Group Meeting Agenda
10
CHP AT THE KAM CONFERENCE KY Association of Manufacturers’ 2014 Energy Conference ….. Impacting Your Bottom Line May 14 th and 15 th at the Lexington Convention Center KAM Conference Planning meeting took place 2-19-2014 (Next Meeting is scheduled for 3-18-2014) Revised Schedule will be released soon. Break-out sessions have been shuffled to avoid conflicts. Speaker Names, narratives, bios, photos, topic titles due 3-18- 2014. Presentation are due 4-18-2014
11
CHP AT THE KAM CONFERENCE May 14, 2014 at 7:30am - Workgroup Breakfast (CHP Workgroup Mtg #2) Suggested Agenda Topics: CHP Barriers Sub-commitee Goals KY Action Plan
12
CHP AT THE KAM CONFERENCE Breakout Session Day 1: May 14 at 3:15pm, 1.25 Hours Title: CHP 101 Agenda: See 3-11 Work Group Meeting #1 Thorough explanation of combined heat and power Policy Options Barriers
13
CHP AT THE KAM CONFERENCE Breakout Session Day 2: May 15 th at 1:45, 45 minutes (TBD may shuffle times on day 2 and add an extra case study) What is CHP? Case studies Fort Knox Domtar
14
NEXT STEERING COMMITTEE CALL Proposed Date: April 16, 2014 Suggested Agenda Topics: KY CHP Action Plan Workgroup status Barriers Identified (Steering Committee is welcome and encouraged to participate in the CHP Workgroup)