Projects currently Under Construction  Lewisville High School Auditorium  Westside Aquatics Center  Flower Mound High School 9 th Grade Campus  Marcus.

Similar presentations


Presentation on theme: "Projects currently Under Construction  Lewisville High School Auditorium  Westside Aquatics Center  Flower Mound High School 9 th Grade Campus  Marcus."— Presentation transcript:

1

2 Projects currently Under Construction  Lewisville High School Auditorium  Westside Aquatics Center  Flower Mound High School 9 th Grade Campus  Marcus High School 9 th Grade Campus

3 Lewisville H.S. Renovation and Rebuild Project Contractor: Balfour Beatty Construction Architect: SHW Group Project started: September, 2010 Project completion: November, 2013

4 Contractor: Balfour Beatty Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Lewisville High School Auditorium Purdue

5 Lewisville High School Auditorium

6

7

8 Contractor: Adolfson and Peterson Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Westside Aquatics Center

9

10

11

12 Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall 2014 Flower Mound H.S. 9 th Grade Campus

13

14

15 Marcus H.S. 9 th Grade Campus Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall, 2014

16 Marcus H.S. 9 th Grade Campus

17

18 Projects Pending Construction Camey Elementary Open Bids: September 2013 Board Approval; November 2013 Start Construction: November 2013 Substantial Completion: November 2014 Griffin Middle School Open Bids: November, 2013 Board Approval: December, 2013 Start Construction: December, 2013 Substantial Completion: June, 2015

19 Construction Schedule: Project to start: October, 2013 Project Completion: November, 2014 Main Entry Camey Elementary Rebuild

20

21

22 Griffin Middle School Rebuild Construction Schedule: Project to start: Fall, 2013 Project Completion: June, 2015

23 Griffin Middle School Rebuild

24 Projects Currently Under Warranty: Marcus HS Athletic Package Under Warranty until April, 2014 Flower Mound HS Athletic Package Under Warranty Until October, 2014

25 Contractor: Pogue Construction Architect: PBK Project under warranty until April, 2014 Marcus High School Athletic Package

26 Flower Mound H.S. Sports Package Contractor: Satterfield & Pontikes Construction Architect: PBK Project under warranty until October 2014