1
Part I Project Initiation © 2012 John Wiley & Sons Inc.
2
Project Management
3
Strategic Management and Project Selection
Chapter 2 Strategic Management and Project Selection © 2012 John Wiley & Sons Inc.
4
Problems With Multiple Projects
Delays in one project delays others Inefficient use of resources Bottlenecks in resource availability
5
Project Results 30 Percent canceled midstream
Over half of completed projects came in up to190 percent over budget Over half of completed projects came in up to 220 percent late
6
Challenges Making sure projects are closely tied to goals and strategy
How to handle the growing number of projects? How to make these projects successful?
7
Project Management Maturity
Project management maturity refers to the mastery of skills required to manage projects competently Number of ways to measure Most organizations do not do well
8
Project Selection and Criteria of Choice
Evaluating Choosing Implementing Same process as other business decisions
9
Types of Companies Companies considering projects fall into two broad categories: Companies whose core business is completing projects Companies whose core business is something else They can also be broken down as: Companies looking at projects to do for others Companies looking at projects to do for themselves
10
Model Criteria Realism Capability Flexibility Ease of use Cost
Easy computerization
11
The Nature of Project Selection Models
Models turn inputs into outputs Managers decide on the values for the inputs and evaluate the outputs The inputs never fully describe the situation The outputs never fully describe the expected results Models are tools Managers are the decision makers
12
Types of Project Selection Models
Nonnumeric models Numeric models
13
Nonnumeric Models Models that do not return a numeric value for a project to be compared with other projects These are really not “models” but rather justifications for projects Just because they are not true models does not make them all “bad”
14
Types of Nonnumeric Models
Sacred Cow A project, often suggested by the top management, that has taken on a life of its own Operating Necessity A project that is required in order to protect lives or property or to keep the company in operation Competitive Necessity A project that is required in order to maintain the company’s position in the marketplace
15
Types of Nonnumeric Models Continued
Product Line Extension Often, projects to expand a product line are evaluated on how well the new product meshes with the existing product line rather than on overall benefits Comparative Benefit Projects are subjectively rank ordered based on their perceived benefit to the company
16
Numeric Models Models that return a numeric value for a project that can be easily compared with other projects Two major categories: Profit/profitability Scoring
17
Profit/Profitability Models
Models that look at costs and revenues Payback period Discounted cash flow (NPV) Internal rate of return (IRR) Profitability index NPV and IRR are the more common methods
18
Payback Period The length of time until the original investment has been recouped by the project A shorter payback period is better
19
Payback Period Example
20
Payback Period Drawbacks
Does not consider time value of money More difficult to use when cash flows change over time Less meaningful for longer periods of time (due to time value of money)
21
Discounted Cash Flow The value of a stream of cash inflows and outflows in today’s dollars Also know as discounted cash flow or just discounting Widely used to evaluate projects Includes the time value of money Includes all inflows and outflows, not just the ones through payback point
22
Discounted Cash Flow Continued
Requires a percentage to use to reduce future cash flows This is known as the discount rate The discount rate may also be known as a hurdle rate or cutoff rate There will usually be one overall discount rate for the company
23
NPV Formula
24
NPV Formula Terms A0 Initial cash investment
Ft Cash flow in time period t (negative for outflows) k The discount rate t The number of years of life A higher NPV is better Higher the discount rate lower the NPV
25
NPV Example
26
Internal Rate of Return [IRR]
The discount rate (k) that causes the NPV to be equal to zero The higher the IRR, the better While it is technically possible for a series to have multiple IRR’s, this is not a practical issue Finding the IRR requires a financial calculator or computer In Excel “=IRR(Series,Guess)”
27
Profitability Index a k a Benefit cost ratio
NPV divided by initial cash investment Ratios greater than 1.0 are good
28
Advantages of Profitability Models
Easy to use and understand Based on accounting data and forecasts Familiar and well understood Gives a go/no-go indication Can be modified to include risk
29
Disadvantages of Profitability Models
Ignore nonmonetary factors Some ignore time-value of money Biased toward the short-term Payback ignores cash flow after payback IRR can have multiple solutions All are sensitive to errors Nonlinear Dependent on determination of cash flows
30
Scoring Models Unweighted 0–1 factor model Unweighted factor model
31
Unweighted 0-1 Factor Model
Factors selected Listed on a preprinted form Raters score the project on each factor Each project gets a total score Main advantage is that the model uses multiple criteria Major disadvantages are that it assumes all criteria are of equal importance
32
Unweighted 0-1 Factor Model Example
Figure 2-2
33
Unweighted Factor Scoring Model
Replaces X’s with factor score Typically a 1-5 scale Column of scores is summed Projects with high scores are selected
34
Unweighted Weighted Factor Model
Each factor is weighted the same Less important factors are weighted the same as important ones Easy to compute Just total or average the scores
35
Weighted Factor Model Each factor is weighted relative to its importance Weighting allows important factors to stand out A good way to include nonnumeric data in the analysis Factors need to sum to one All weights must be set up, so higher values mean more desirable Small differences in totals are not meaningful
36
Weighted Factor Model Example
Figure B Page 60
37
Advantages of Scoring Models
Allow multiple criteria Structurally simple Direct reflection of managerial policy Easily altered Allow for more important factors Allow easy sensitivity analysis
38
Disadvantages of Scoring Models
Relative measure Linear in form Can have large number of criteria Unweighted models assume equal importance
39
Risk Considerations in Project Selection
Both costs and benefits are uncertain Benefits are more uncertain There are many ways of dealing with risk Can make estimates about the probability of outcomes Subjective probabilities Uncertainty about: Timing What will be accomplished? Side effects Pro forma documents
40
The Project Portfolio Process (PPP)
Links projects directly to the goals and strategy of the organization Means for monitoring and controlling projects
41
Symptoms of a Misaligned Portfolio
More projects Inconsistent determination of benefits Projects that don’t contribute to the strategy Competing projects Costs exceed benefits No risk analysis of projects Lack of tracking against the plan No client for project
42
Purpose of Project Portfolio Process
Identify nonprojects Prioritize list of projects Limit number of projects Identify the real options for each project Identify projects with good fit Identify co-dependent projects
43
Purpose of Project Portfolio Process Continued
Eliminate risky projects Eliminate projects that skip the formal selection process Keep from overloading the organization To balance the resources with needs To balance returns To balance short-, medium-, and long-term returns
44
Project Portfolio Process Steps
Establish a project council Identify project categories and criteria Collect project data Assess resource availability Reduce the project and criteria set Prioritize the projects within categories Select the projects to be funded and held in reserve Implement the process
45
Step 1: Establish a Project Council
Senior management The project managers of major projects The head of the Project Management Office Particularly relevant general managers Those who can identify key opportunities and risks facing the organization Anyone who can derail the PPP later on
46
Step 2: Identify Project Categories and Criteria
Derivate projects Platform projects Breakthrough projects R&D projects
47
Step 3: Collect Project Data
Assemble the data Document assumptions Screen out weaker projects The fewer projects that need to be compared and analyzed, the easier the work of the council
48
Step 4: Assess Resource Availability
Assess both internal and external resources Assess labor conservatively Timing is particularly important
49
Step 5: Reduce the Project and Criteria Set
Use strengths Synergistic Dominated by another Has slipped in desirability Organization’s goals Have competence Market for offering How risky the project is Potential partner Right resources Good fit
50
Step 6: Prioritize the Projects Within Categories
Apply the scores and criterion weights Consider in terms of benefits first and resource costs second Summarize the returns from the projects
51
Step 7: Select the Projects to be Funded and Held in Reserve
Determine the mix of projects across the categories Leave some resources free for new opportunities Allocate the categorized projects in rank order
52
Step 8: Implement the Process
Communicate results Repeat regularly Improve process
53
Project Proposals The project proposal is essentially a project bid
Putting together a project proposal requires a detailed analysis of the project Project proposals can take weeks or months to complete A more detailed analysis may result in not bidding on the project
54
Project Proposal Contents
Cover letter Executive summary The technical approach The implementation plan The plan for logistic support and administration Past experience