PAVEMENT MAINTENANCE II Part 1b: Chip Seal Construction Idaho Roads Scholar Program
2
Objectives n Review how to set up a good chip seal, n Investigate equipment operation, and field checks, n Identify common problems and possible solutions.
3
Field Checks n Weather/Surface Condition n Traffic Control n Aggregate n Asphalt n Asphalt and Chip Distributor n Rollers n Sweeping
4
Weather/Surface Condition n Dry or Damp Surface n Temperature n Rain/Humidity n Wind
5
Surface Temperature
6
Proper Traffic Control is Essential!
7
Aggregate Requirements for Successful Seal Coat n Must be clean. u Less then 1% passing #200 sieve. n Cubical chips are better then flat chips. n Must be crushed. u At least 2 crushed faces. n More single sized the better.
8
Dirty Chips n > 1% passing the #200 sieve u Impedes the ability of binder to bond chip to roadway. u Limits amount of binder that can be applied. u Creates dust after sweeping.
9
Aggregate Condition n Emulsions => Damp Surface n Asphalt Cement => Dry Surface
10
n Can only glue down a single layer of chips. n Must have chips at least 60 to 70% embedded to withstand traffic and snow plow damage. n Should see emulsion at top of chips before emulsion breaks. Chip Considerations
11
Which are the better chips?
12
Distributors
13
Asphalt Distributor Components n Nozzles n Spray Bar Height n Application Rate n Product Temperature
14
Nozzle Angle
16
Spray Bar Height
18
Triple Coverage
19
Test Shot n Apply Asphalt Product for Known Distance & Width n Calculate Amount of Applied Asphalt Product n Calculate Spread Rate
20
Product Temperature n Typically 140 to 185 o F n Check At Distributor
21
Common Emulsion: CRS-2P n Develops strength in hours that normally take days. n Sweep same day. n Requires clean chips. n Must place chips within one minute of placement of binder. n Eliminates bleeding u Higher softening point
22
Sample Asphalt Product n Sample Location u Truck or Trailer u Nozzle n Sample Container u 1 Gallon Plastic w/Lined Screw Cap,Wide Mouth
23
Chip Spreaders
24
Chip Spreader Issues n Correct Application Rate n Uniform Application Rate
25
Test Shot to Insure Correct Application Rate n Apply aggregate for known distance and width n Calculate Amount of Aggregate n Calculate Spread Rate
30
Check Rollers n Type n Weight n Speed
31
Rolling
33
Best Pneumatic-Tire Roller
34
Buns Up: Check Embedment
35
Factors Affecting Breaking and Curing n Weather Conditions: temperature, humidity, wind n Water Absorption n Aggregate moisture content: although wet aggregate may facilitate coating, it tends to slow the curing process n Mechanical forces: roller pressure forces water from mix n Surface area: excessive fines or dirty aggregate accelerate breaking n Surface chemistry
36
Broom
38
Safety n Approved Vests n Communication n Eye Contact
39
Typical Problems n Streaked Appearance n Bleeding/Flushing n Loss of Cover Aggregate n Bad Centerline Joint n Utilities/New Patches n Tight Alignment or Steep Grades n Heavy Tree Canopy n Fall Weather
40
Common Chip Seal Problems
41
Rules of Thumb for Seal Coat s Make sure pavement is clean Use high quality materials Proper application rate for binder Proper application rate for aggregates. Extra aggregates only cause failure. Keep distance between the distributor and the chipper to minimum. Aggregate must be placed before emulsion starts to break.
42
Rules of Thumb for Seal Coat s, cont. n Minimum of three rollers. Keep speed under 5 mph. Compaction must be completed before emulsion is broken. n Final sweeping of roadway as soon as possible. No later then the next morning. n Remember that Details count.
43
Questions? Chip Seals