Download presentation
Presentation is loading. Please wait.
Published byBaldwin Stephens Modified over 9 years ago
1
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 1 I) CNGS status radiation damage on electronics strip line repair II) OPERA issues Based on the work done by the CNGS/SBWG and the report given to RPC08 by I. Efthymopoulos proton intensity for the 2008 run OPERA experiment status
2
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 2 Radiation damage on electronics
3
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 3 CNGS Electronics - underground Designated “radiation safe” areas for electronics
4
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 4 Ventilation Electronics - Layout Temperature Probes Ventilation Units Target Chamber Service Gallery Proton Beam Line …electronics equipment Ventilation Chamber Junction gallery
5
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 5 Electronics Racks inside the Service Gallery Ventilation ducts (to be moved)
6
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 6 Installed ventilation equipments Unit 231 Ventilation duct Service Gallery TSG4 Unit 232 TSG44 Balcony TCV4 Location of broken PLC
7
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 7 Junction Gallery
8
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 8 Radiation field – FLUKA simulation Energetic (>20 MeV) hadron fluence (/cm 2 /yr 1 ) for a nominal CNGS year of 4.5E19 pot ~ 10 7 – 10 9 h/yr A.Ferrari, et. al., 2007 Location of observed failures Can create Single Event Effects on electronics (bit flip, single event upsets...) A fluence of ~10 9 h/yr would correspond to ~19 failures/yr per device
9
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 9 Radiation field – FLUKA simulation Total dose in Gy/y for a nominal CNGS year with 4.5E19 pot ~ 0.1 – 10 Gy/y A.Ferrari, et. al., 2007 Commercial electronics typically do not fail below 1 kRad (10 Gy)
10
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 10 Radiation field – FLUKA simulation ~ 10 9 – 10 11 n/cm² A.Ferrari, et. al., 2007 Commercial electronics typically do not fail below 10 10 n/cm 2 1 MeV eq. neutron fluence (cm -2 yr -1 ) for a nominal CNGS year of 4.5 E19 pot
11
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 11 Radiation effects on electronics The ventilation electronics that failed were installed along the TSG4 gallery next to the ventilation ducts and in the TCV4 balcony In both areas the radiation levels as predicted by the simulations are far too high for COTS components the electronics should have failed and they did ! No failures to electronics in the TSG4 “safe” area were observed Should not have happened according to simulations for the beam intensities we had, however would have happened if we were running longer... During the 2007/2008 shutdown, work is organized to remedy the problem and assure nominal running of the facility for 2008 and beyond.
12
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 12 Actions for 2008 shutdown General guideline: Move whatever is possible of the electronics out of the CNGS tunnels For the equipment, which needs/must stay in the area: Create a “radiation-safe” area by adding adequate shielding and move all the electronics in there Address the sensitivity to radiation of the installed electronics and investigate upgrade possibilities to rad-tol components Assure a MTBF – of at least 1 year redundancy and preventive maintenance actions Install radiation monitoring system for electronics as in LHC
13
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 13 Ventilation duct layout TCV4 TCC4 TSG4 old TCV4 TCC4 TSG4 new Shielding plugs
14
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 14 New shielding plugs – TSG4 & TSG41
15
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 15 Status The layout modifications will have no impact on operation and design principles of CNGS However, access rules, procedures and dose estimates for maintenance operations need to be updated Simulation studies are ongoing to estimate the radiation field for the electronics Preliminary results with “ideal” shielding (minimal penetrations) show a reduction of at least 10 4 in the high energetic hadrons, reality could be x10 lower Work is ongoing to implement the final shielding geometry as to be built. Basically no work will be executed close to the “hot” areas in TCC4. In the rest of the areas the radiation levels are rather low. Nevertheless, for the planning and execution of the works in-situ the same procedures as with the horn repairs will be followed Optimization of design and execution taking into account RP and safety constraints Detailed planning of activities in parallel to dose planning Supervision of the works/workers in-situ ; use of appropriate materials for RP and waste handling
16
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 16
17
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 17 Ventilation: modified layout in TSG41
18
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 18 Shielding layout in TSG41
19
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 19 Tentative Schedule of the work Very tight schedule: no contingency, 1-2 weeks to be added for beam commissioning
20
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 20 Gy/yr for a nominal CNGS year of 4.5 10 19 pot No shielding 0.1 - 10 With shielding (caveat: the option simulated in TSG41 does not include the ventilation ducts)
21
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 21 1 MeV eq. neutron fluence (cm-2 yr-1) for a nominal CNGS year of 4.5 10 19 pot No shielding 10 9 - 10 11 With shielding (caveat: the option simulated in TSG41 does not include the ventilation ducts)
22
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 22 Energetic (> 20 MeV) hadron fluence (cm-2 yr-1) for a nominal CNGS year of 4.5 10 19 pot No shielding 10 8 10 6 With shielding (caveat: the option simulated in TSG41 does not include the ventilation ducts)
23
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 23 Fluences in front of the shielding
24
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 24 TSG41 shielding : preliminary results Fluence of high energy hadrons Absorbed dose [Gy per particle] simu
25
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 25 Strip Line Repair
26
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 26 Reflector flexible cable : Strip line Failure observed only in the outer plate of the reflector The break is due to material fatigue from the mechanical & thermal effects during pulsing, most likely enhanced by the treatment during construction (brazing, etc..) Last minute discovery before the 2007 startup Flexibles are needed to compensate for mis-alignment errors in the striplines and absorb the thermal dilation during operation
27
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 27 Reflector flexible cable : strip line Temporary measures taken in 2007 to continue with the run: Insulating sheets installed on the flexible section Protects against short-circuits Installed on horn and reflector Put an electrical by-pass in place Ensure that current still flows in case last cable breaks Installed on most outer reflector plate In shutdown 2008: Design new flexible strip lines Replace existing ones for both horn & reflector
28
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 28 Proton intensity for the 2008 run
29
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 29 2008 run : SPS schedule 147 days max for the CNGS Spread over 23 weeks (Nominal CNGS year : 200days) May 29 th November 10 th
30
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 30 2008 run : Super-Cycle SPS super cycle as in the proposal Proposed super cycle in 2008: Extended to 39.6 sec in 2007: 3 CNGS : 18 sec fix target cycle 16.8 sec (flat top 4.8 9.6 sec) MD cycle added (4.8 sec) Adding LHC pilot cycle: 8.4 sec super cycle = 48 sec ! tuning parameters: o replace the LHC pilot cycle (and MD cycle ?) by CNGS cycles when LHC R&D is off o reduce the flat top for fixed target experiments to 4.8 sec
31
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 31 2008 run : expected statistics Expected 2008 runNominal CNGS Number of days147200 Super Cycle (sec.)4827.6 Circulating proton3.8 10 13 4.5 10 13 4.8 10 13 efficiency70%80%55% Integrated pot2.1 10 19 2.9 10 19 4.5 10 19 Total number of interactions2770 CC events2070 NC events455 Electron events16 Charm decay83 Tau candidate (@2.5 10 -3 eV 2 )1.1 Minimal granted by CERN If no delay in the CNGS repair ~120 evts/week
32
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 32 Possible gain for the number of CNGS cycles (A) Nominal 2008 Super Cycle 3 CNGS / 48 sec 1800 CNGS/shift 1. (B) Reducing flat top to ~4.8 sec 3 CNGS / 43.2 sec 2000 CNGS/shift 1.11 (C) B + adding 1 CNGS cycle 4 CNGS / 49.2 sec 2341 CNGS/shift 1.30 (D) C + replacing LHC & MD by CNGS 6 CNGS / 48 sec 3600 CNGS/shift 2.00 (E) CNGS dedicated mode 1 CNGS / 6 sec 4800 CNGS/shift 2.7 Only way to increase the nb of pot and (or) compensate CNGS delay Example of an optimized week (for OPERA): scenario C during day shifts (working days) scenario D during night shift and WE Gain : ~1.7 This would imply up to ~200 evts /week Can OPERA handle this rate ?
33
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 33 OPERA issues: Status of the preparation of the OPERA experiment : Detector filling Electronic detectors Brick handling, processing, scanning In 2008, our main goal is to get a full year of data taking: First OPERA year First candidates
34
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 34 Detector filling Remember what was the situation one year ago ! Warmest congratulations to the teams involved: Brick components (Lead & CSd), BAM & BMS Coordinated in a Kaisen way by Salvatore 154000 June 10 th July 28 th October 25 th Achieved ! Including 15% contingency (~3 weeks)
35
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 35 Electronic Detectors SM1 Veto BMS Target tracker SM2 Spectrometer: XPC, HPT, RPC, magnet all installed & commissioned DAQ validated, data transfer onto the DB implemented data analysis tools being tuned on real data ! o HPT reconstruction still to be validated o Event reconstruction & Brick Finding: more data needed for a complete tuning
36
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 36 Brick Handling, Processing & Scanning This subject was the purpose of this Workshop it was a very fruitful meeting, organized in a smart way thanks to Nakamura san, Hoshino san, Sato san & Kodama san better to look at the summary reports from the Working groups Recommendation: 1)Do not underestimate the amount of work for a nominal OPERA year with 5200 events this year 320 shifts to be fulfilled for the film development improving the track finding efficiency in the CSd is an issue 2)Quality control is essential during the brick processing
37
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 37 CONCLUSION Looking forward to discuss the first Tau candidates next year in Nagoya Keep your fingers crossed … in your mind, you need your hands for working !
38
January 23 rd, 2008 CNGS & OPERA status Yves Déclais 38 title
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.