Download presentation
Presentation is loading. Please wait.
Published byEmily Armstrong Modified over 9 years ago
1
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review 23-24 October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC ACCELERATOR PROJECT
2
2 Outline Vendor Scope of Work List of Government Furnished Materials Vendor Pre-qualification Process Project Schedule RFP Strategy and Schedule RFP Package Information Requested in Bidder’s Response Proposal Evaluation Criteria Summary
3
3 Vendor Scope of Work Fabricate, assemble and test 8 feedboxes per LBNL Specification M-993 (Statement of Work) Integrate LBNL provided parts/assemblies into the feedboxes Complete all electrical and tests per provided specs Provide all necessary tooling, fixtures, instruments and cryogens needed for assembly, handling, test and acceptance activities Pack and ship to CERN in accordance with Shipping Spec LBNL will perform the acceptance tests at CERN Final acceptance requires passing the acceptance tests at CERN
4
4 List of Government Furnished Materials Complete list is generated from BOM Major Components: 1.HTS leads (Pirelli) 2.Vapor cooled leads (subcontractor) 3.Bus duct and lambda plug assemblies (LBNL) 4.Beam tube assemblies (LBNL) 5.Magnet instrumentation conduits (LBNL) 6.Specialized bellows and flanges (FNAL) 7.Specialized cryogenics sensors (CERN) 8.Support jacks, tooling balls, name plates, etc. (LBNL)
5
5 Vendor Pre-qualification Process FNAL commissioned experienced vendors to conduct fabrication study Vendors were visited several times to discuss specifications and design intent Submitted an LOI for price and schedule estimates to five vendors in Dec 2001 Cost and schedule for the full scope of work for 8 DFBXs based on DFBXG design and 5 variants Received positive expression of interest from three companies, two were not interested
6
6 Vendor Pre-qualification Process (cont.) Progress since May 2002 Review: One vendor dropped out leaving two interested in DFBX fab Vendors reviewed Acceptance Specification They accept responsibility for mechanical integrity of the box after shipping to CERN, but Will not accept responsibility for electrical components Vendors were qualified to perform lead splice operation. Vendors and their subcontractors reviewed the Crating and Shipping Specification
7
7 Project Schedule Additional schedule constraint US-LHC Accelerator Project ends Sept. 2005
8
8 Project Schedule (cont.) Schedule forecast Based on the LOI schedule provided by the manufacturers: First DFBX Delivered 13 month ARO oMeets CERN requirement Last (8th) DFBX Delivered 27-29 months ARO oMeets DOE-LHC requirement However, production schedule is aggressive To meet schedule extensive oversight is required Highlights the urgency to get process started
9
9 RFP Strategy Based on discussion with the Project Management Office and vendors: Decision was made to release the RFP based on the fabrication drawings for DFBX-C/G and top level assembly drawings for other 5 variants Get vendors started on preparing their proposals To get the vendor subcontractors started To develop the bid framework and fabrication plan Release all other drawings 4-6 weeks before proposal response due date RFP schedule allows time for BAFO cycle (if needed) Working closely with LBNL Procurement Department and the LHC-PMO to get the RFP out
10
10 Conditions for BAFO After receiving the responses to the RFP we may request a BAFO BAFO address include: Exceptions requested by vendors Design changes requested by LBNL Changes in integration tasks and schedule
11
11 RFP Schedule Production Readiness Review23 Oct 2002 Issue RFP5 Nov 2002 Complete Remaining Drawings28 Nov 2002 Vendor's Response14 Jan 2003 Issue Request for BAFO28 Jan 2003 Vendor's Final Response11 Feb 2003 Place Order4 Mar 2003
12
12 Post Award Conference Meeting to be held at vendor’s facility 4 weeks after award Complete list discussion topic is in the SOW documents Major points are: 1.Review fabrication and assembly plan and schedule 2.Coordinate the delivery schedule of GFM 3.Coordinate in-process inspection 4.Resolve any inconsistencies in the LBNL provided drawings or documents
13
13 Initial RFP Package Technical Specification (SOW) Engineering drawings Detailed fabrication drawings for DFBX-C/G Top level assembly drawings for other 5 variants Acceptance Specification MLI Specification Power Lead Splice Specification Bill of Materials List List of GFM and their replacement cost Installation specification of LBNL supplied materials Crating and Shipping Specification Flow Schematics Wiring Diagrams LBNL QA plan
14
14 Information Provided During Proposal Activities Detailed fabrication drawings for other 5 variants Changes resulting from pipe interconnect specifications
15
15 Information Requested in Bidder’s Response RFP Appendix A contains proposal response information requested to evaluate and rank proposals Two separate proposals are required: Price and Technical Technical Proposal includes: Delivery Schedule Fabrication Milestone Schedule Qualifications: Experience and Past Performance Production Facilities and Planning Understanding the Requirements and Technical Approach Project Management, Quality Assurance and Quality Control Implementation
16
16 Proposal Evaluation Criteria RFP Appendix A contains proposal evaluation criteria: Price Delivery schedule Technical Evaluation Factors: Production Facilities and Planning Conformance with Specification and Understanding the Requirement Qualifications: Management Experience and Past Performance Quality Assurance and Quality Control Implementation Site Access
17
17 Bid Evaluation Evaluation criteria and weighting factors are set before releasing the RFP Price has the highest weighting factor Evaluation committee members from LBNL and FNAL Committee will review and evaluate the technical and schedule responses to the RFP Knowledge of price information will be limited to LBNL Procurement Officer
18
18 Basis of Award Award contract to the bid that contains the combination of those factors offering the best overall value to the Laboratory Lowest overall price will be the primary concern in making the award Credibility of vendor’s delivery schedule and technical performance are important, but ranked slightly below price
19
19 Summary Vendors are familiar with the scope of work and are pre-qualified Fabrication plan is developed RFP documents are nearly complete 4 months are allowed from issuing RFP to placing award Meeting production schedule remains a major challenge
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.