John James Audubon Bridge Main Span
4
Materials and Equipment Cement from Thailand Structural Steel from Japan Oscillator from Germany Wind tunnel analysis from Ontario, Canada
5
Main Span Sequence of Events –Construct drilled shafts –Construct footing –Construct towers –Lay deck –Attach stay cables
6
Drive Permanent Casing Set Permanent Casing In Frame Drive To Grade (Vibratory Hammer)
7
Set Shaft Template The drilled shaft template holds the casing straight as it is vibrated into the ground
8
Drive Permanent Casing A vibratory hammer is used to vibrate the casing into the ground
9
Install Oscillator Layout/Place Oscillator Base And Lock Down Place Oscillator
10
Install Oscillator 1. Set Base
11
2. Set Oscillator Install Oscillator
12
Drive Temporary Casing Speed has been accelerated An oscillator works like someone is opening and closing a jar (back and forth)
13
Footing Cofferdam Structure Piles and trestle are installed
14
Install Soffit Panels
15
Install Bracing Frame Install first tier of brace frame
16
Erect Pre-Cast Wall Install pre-cast walls Connect to soffit panels and first tier brace frame
17
Install Jacking System Install jacking system with permanent hangers Lower structure to facilitate 2 nd & 3 rd tier bracing installation
18
Install 2 nd and 3 rd tier brace frame. Install Additional Brace Frames
19
Install Follower Sheeting Install sheet pile
20
Lower Structure Lower structure to final elevation Lock off hangers
21
Pour Concrete Seal Install 8 foot concrete seal Oink
22
Dewater Structure Install pump. Remove water
23
Remove Hangers and Cut Casing Remove hangers Cut casing
24
Place Reinforced Pile Cap Place reinforced pile cap concrete
25
Place Pedestal Concrete Place pedestal reinforcing and concrete lift 1 Restrut as required
26
Place Pedestal Concrete Lift 2 Place pedestal concrete lift 2
27
Remove Cofferdam Remove sheeting Remove Bracing Patch blockouts
28
Build Main Span Towers Install formwork & rebar Pour concrete Raise formwork Repeat process
29
Install Girders
30
Build Bridge Deck
31
Install Segmental Sections
32
Bridge Segments Segments are installed in sections Cable anchorage is added Cable stays are installed for support
33
Build bridge in segments Install Cable Stays to support bridge Overall Method of Construction
34
The Finished Bridge