FOR REMOVAL OF COLLAPSED PORTION AT SHERSHAH BRIDGE SITE
MAKRAN COASTAL HIGHWAY MAI KOLACHI NDMA RAN PATHANI LYARI EXPRESSWAY WORK METHODOLOGY FOR REMOVAL OF COLLAPSED PORTION AT SHERSHAH BRIDGE SITE RBOD - II 25 Jun 2007 SUKKUR BARRAGE
2
NHA ACHIEVEMENTS PSDP FUNDING FOR THE YEAR 2007 – 2008 RS 29 BILLION
NHA NETWORK – CUSTODIAN OF 30 NATIONAL HIGHWAYS, MOTORWAYS, EXPRESSWAYS AND STRATEGIC ROADS – TOTAL LENGTH KM * PUNJAB KM % * SINDH KM % * NWFP KM % * BALOCHISTAN KM % * NAs / AK KM % BRIDGES CULVERTS CURRENT PORTFOLIO PROJECTS 510 BILLION REPAIR & MAINTENANCE * – M TOLL M MAINTENANCE ALLOCATION * – M
3
MAJOR ACHIEVEMENTS OF FWO
KARAKORAM HIGHWAY (806 KM) KKH – SKURDU ROAD MAKRAN COASTAL HIGHWAY TORKHUM – JALALABAD ROAD RUNN PATHANI RAILWAY BRIDGE RUNWAY SKARDU AIRPORT MANGLA HYDEL POWER STATION LODHRAN – KHANEWAL RAILWAY DOUBLE TRACK REHABILITATION OF SUKKUR BARRIAGE LAHORE – SHEIKHUPURA – FAISALABAD DUAL CARRIAGEWAY SIMLY DAM AKRA KAUR DAM MANSEHRA – NARAN – JHALKAD ROAD GIZIRVALLI ROAD AZAD PATTAN – RAWALA KOT ROAD RATTO DERO – SHAHDAD PUR ROAD GHOTKI – UBARO ROAD LYARI EXPRESSWAY (ONGOING) RBOD – II (ONGOING)
4
AIM TO PRESENT WORK METHODOLOGY FOR REMOVAL OF COLLAPSED PORTION AT SHERSHAH BRIDGE SITE
5
KNB PROJECT DATA SALIENTS TOTAL LENGTH - 56 KM COST 3.2 BILLION NLC
32 KM (2.4 BILLION) ECIL 24 KM (0.8 BILLION) BRIDGE COST (600 m) 320 MILLION BRIDGE PORTION (120 m) WHICH IS FELL 90 MILLION DELAY 2003 – 2005 TWO YEARS WORK STARTED MAY 2005 MAR 2006 FAULT DEVELOPED OCT 2006 WORK STARTED AGAIN (AFTER REDESIGNING OF FOREIGN CONSULTANTS) OPENED FOR TRAFFIC 10 MAY 2007
15
SHERSHAH BRIDGE SALIENTS LENGTH OF CONCRETE STRUCTURE - 496 m
LENGTH OF REINFORCED EARTH RAMP – 1 390 m LENGTH OF REINFORCED EARTH RAMP – 2 314 m NO OF SPANS 16 30 m 11 22.5 m 02 60 m (INNER BOX GIRDER) 120 m (OUTER CONTINUOUS BOX GIRDER) 01 DAMAGED PORTION (INITIAL ASSESMENT) 120 m
16
REMOVAL OF COLLAPSED PORTION OF SHERSHAH BRIDGE
ASSESMENT OF TASK DEMOLITION OF 2x60 m INNER BOX GIRDERS RESTING ON COLUMNS DEMOLITION OF 1x120 m COLLAPSED OUTER BOX GIRDER REMOVAL OF INNER AND OUTER DAMAGED GIRDERS REMOVAL OF COLUMNS AND OTHER COMPONENTS CORDONING OF AFFECTED AREA TRAFFIC DIVERSION DISPOSAL OF DEBRIS
17
SHERSHAH BRIDGE WORKING METHODOLOGY WORKING ORGANIZATION
DEMOLITION METHODOLOGY PROPOSED LIST OF PLANT / EQUIPMENT
18
SHERSHAH BRIDGE WORKING ORGANIZATION TOTAL 60 – 70 PERSONS
FIELD CONTROL CENTRE (GROUP COMMANDER) COL BASIM (NLC) COORD OFFICER DEMOLITION GROUP – I (LT COL SAEED) DEMOLITION GROUP – II (LT COL TAHIR) SUPPORT GROUP (LT COL MANSOOR) DEMOLITION TEAM – A (IC – JCO) (2 x NCOs, 10 x OR) DEMOLITION TEAM – C (IC – JCO) (2 x NCOs, 10 x OR) COORD TEAM (IC - JCO) DEMOLITION TEAM – B (IC – JCO) (2 x NCOs, 10 x OR) DEMOLITION TEAM – D (IC – JCO) (2 x NCOs, 10 x OR) TPT / PLANT MGMT TEAM (IC – JCO) (3 x NCOs, REQ OP) TOTAL 60 – 70 PERSONS
19
DEMOLITION METHODOLOGY
SHERSHAH BRIDGE DEMOLITION METHODOLOGY DEMOLITION OF 120 m FALLEN BOX GIRDER THROUGH EXPLOSIVE / MECHANICAL MEANS DEMOLITION OF 2x60 m INNER BOX GIRDERS THROUGH DEMOLITION OF COLUMNS WITH EXPLOSIVE / MECHANICAL MEANS CUTTING OF 2x60 m INNER BOX GIRDERS INTO PORTABLE PIECES DISPOSING OFF DEBRIS AND CONCRETE PIECES AT PRESELECTED PLACE USING CRANES, DUMP TRUCKS AND TRANSPORTERS ESTABLISHMENT OF LOGISTIC BASE AT LOCATION OF 756 CONSTRUCTION TEAM ENGINEERS (MAURIPUR INTERCHANGE)
20
DEMOLITION METHODOLOGY
SHERSHAH BRIDGE DEMOLITION METHODOLOGY
21
DEMOLITION METHODOLOGY
SHERSHAH BRIDGE DEMOLITION METHODOLOGY
22
DEMOLITION METHODOLOGY
SHERSHAH BRIDGE DEMOLITION METHODOLOGY
23
DEMOLITION METHODOLOGY
SHERSHAH BRIDGE DEMOLITION METHODOLOGY
24
DEMOLITION METHODOLOGY
SHERSHAH BRIDGE DEMOLITION METHODOLOGY
25
PROPOSED LIST OF PLANT / EQUIPTMENT
SHERSHAH BRIDGE PROPOSED LIST OF PLANT / EQUIPTMENT DEMOLITION TEAM FOR ONE TEAM FOR 4xTEAMS JACK HAMMERS - 3 Nos 12 Nos EXCAVATORS 2 Nos 8 Nos FE LOADER 1 No 4 No DOZER SIZE – II CRANE HEAVY DUTY CONCRETE CUTTER FORK LIFTER COMPRESSOR GAS CUTTER 5 (1 x RESERVE) 20 PNEUMATIC DRILL MACHINE 4 (1 x RESERVE) 16 GENERATORS (300 – 500 KVA) 3 (1 x RESERVE) 12 SWR AS REQUIRED EXPLOSIVE / ACCESSORIES
26
SHERSHAH BRIDGE SUPPORT GROUP
ARRANGEMENT OF PLANT / EQUIPMENT / EXPLOSIVE / POL etc. REPAIR OF PLANT / EQUIPMENT ESTABLISHMENT OF FIELD CONTROL CENTRE REPORTS AND RETURNS SECURITY COMMUNICATION MEDICAL COVER COORDINATE TRAFFIC PLAN MEDIA MANAGEMENT