Presentation is loading. Please wait.

Presentation is loading. Please wait.

Welcome to SNS The Next Large EPICS Project

Similar presentations


Presentation on theme: "Welcome to SNS The Next Large EPICS Project"— Presentation transcript:

1 Welcome to SNS The Next Large EPICS Project
A Partnership between Six National Laboratories: Argonne National Lab Brookhaven National Lab Lawrence Berkeley National Lab Los Alamos National Lab Oak Ridge National Lab Thomas Jefferson National Lab

2 The SNS Controls Team at ORNL
Your local hosts: The SNS Controls Team at ORNL John Cleaves Richard Epps Bill DeVan John Munro Delphy Nypaver Ron Battle Coles Sibley Bill Stone Herb Strong Ernest Williams Paul Wright Pam Gurd

3 Spallation Neutron Source Aerial/Site Plan

4 Spallation Neutron Source Aerial/Site Plan

5 Schedule Overview Integrated Controls Systems Master Schedule Activity
FY99 FY00 FY01 FY02 FY03 FY04 FY05 FY06 1.1.9 R&D BOD MCR MCR Operational Turnover to operations 1.9.2 Global Systems BOD Start Commissioning 1.9. 3 Front End Controls BOD Start Commissioning 1.9.4 Linac Controls BOD Start Commissioning 1.9.5 Ring Controls BOD Start Commissioning 1.9.6 &7 Target & Instrument Controls Complete Target Commissioning BOD Start Cooldown Complete Cooldown 1.9.8 & CF & CHL Controls BOD MCR Turnover to operations 1.9.9 PPS Legend R&D Integrated Controls Systems Master Schedule Design, Procure, Fabricate Installation & Testing Test Support Software development

6 Status of the Project Good News Unresolved Issues
Funding of $1.4B approved (incl $60M for Controls) FY01 Funding of $278M approved (incl $9.5M for Controls) 1.4 million yard of dirt moved, first concrete poured Unresolved Issues Pre-operations funding Some controls staffing problems at BNL and LANL Who is the President (and is he from Tennessee…)???

7 An aside…

8 We plan a system fully integrated under EPICS, including…
Accelerator Systems Front End, Linac, Compressor Ring, Beamlines ~ 50,000 channels, 160 IOCs Front End already running under EPICS (at Berkeley) Target System Large and complex liquid Mercury Target 1000 channels, 6 PLCs Test facility already running prototypical EPICS system Conventional Facilities 2500 channels, 10 PLCs, 150 screens To be done in EPICS by Sverdrup in Tullahoma Training in January

9 Control System Construction is distributed among all Collaborating Laboratories
ICWG include JLAB 1.3 1.4 1.5 1.6 1.7 1.8 Cryo 1.9 Front End Linac Ring Target Instruments Facilities (JLAB, ORNL) Controls (LBNL) (LANL) (BNL) (ORNL) (ORNL, ANL) (ORNL, CM) 1.9.3 1.9.4 1.9.5 1.9.6 1.9.7 1.9.8 1.9.10 1.9.9 Front End Linac Ring Target Instrument Facilities Cryo Personnel Controls Controls Controls Controls Controls Controls Controls Safety 1.9.2 “Global” Controls: (Network, Timing, Protection, Control Room, Labs, Applications, System Software) 1.9.1 Integration & Management

10 Total Controls Manpower Construction and Operations

11 Where we are now Controls Group Staff of 10 here at ORNL
EPICS Systems running Target Test Facility here and Front End Systems at Berkeley Application Development Environment here at ORNL Distributed CVS – accessible by all the partners Prototypical Environment running in lab here MVME 2100 PPC, EPICS , Tornado II, DM2K ControlLogix PLC ControlNet over EtherNet Driver

12 The SNS Control Room

13 Some things we have agreed upon…
Site-wide Device and Signal Naming Convention ControlLogix PLCs (Allen-Bradley) ControlNet over EtherNet Driver Standard Cabinets PowerPC IOCs (MVME 2100) VME64x (Bid on the street) Including Utility Board Linux Environment where appropriate Oracle, but…

14 … and some we have not. Display Manager Database creation
DM2K (The current “official” standard) vs EDM Database creation Will use Oracle, but the process is uncertain Capfast?? Templates? We hope this meeting will help with these decisions

15 Some EPICS Developments are needed
Large Array Support Needed for Diagnostics Long PV Names We could bump up against the current limit Variable String Size Multipriority Channel Access Needed for Diagnostics and Machine Protect SNS will fund some of these Core developments, but we will need help from the community…

16 Summary Jobs available
Many issues the EPICS Community can help us with. We hope to contribute to EPICS We look for help and advice from this meeting

17 Create 65-mA H- ion beam Ion Source/LEBT
Front End – A Highly Complex System with Several Major Subsystems and Critical Functions The Front End has relationships with all systems: rf, high voltage, diagnostics, alignment, controls, magnets, power supplies, pulsed power, physics, vacuum, Cesium, radiation. Create 65-mA H- ion beam Ion Source/LEBT Accelerate beam to 2.5 MeV RFQ Chop beam into mini-pulses LEBT/MEBT Match 52-mA beam into DTL MEBT

18 Layout of Linac RF with NC and SRF Modules
805 MHz, 0.55 MW klystron 805 MHz, 5 MW klystron 402.5 MHz, 2.5 MW klystron RFQ DTL CCL (4) (1) (6) 2.5 MeV 86.8 MeV 186 MeV SRF, ß=0.61 379 MeV SRF, ß=0.81 972 MeV HEBT (33) (59) (2) from CCL 1 33 1 59 (92 total)

19 Ring Lattice 2000P-03550/jhb

20 SNS Integrated Control System
WBS 1.9 Scope includes control of all major subsystems as well as Personnel Safety and “Global Systems.” SNS Integrated Control System OPIs IOCs ( ) ROUTER FILE SERVERS (EPICS FILE SERVER, ARCHIVERS, ETC.) ( ) ( ) ( ) ( ) ( ) MAIN CTRL. RM. EQUIP. FRONT END CTRL. RM. EQUIP. RING CTRL. RM. EQUIP. OTHER LOCAL CNTL STNS TIMING SYSTEM MASTER ( ) BEAM PERMIT SYSTEM ( ) CABLES ( ) RACEWAYS (1.8.X) CONTROL SYSTEM NETWORK (EQUIPMENT AND NODE CABLING) POWER AND COMMUNICATIONS SYSTEMS (BACKBONE CABLING) CABLES ( ) RACEWAYS (1.8.X) CONVENTIONAL FACILITIES IOC’S (1.9.8). PPS IOC (1.9.9) FAST PROTECT OUTPUT HARDWARE ( ) FRONT END CONTROL SYSTEMS (1.9.3) LINAC CONTROL SYSTEMS (1.9.4,10) RING CONTROL SYSTEMS (1.9.5) TARGET IOC’S (1.9.6) EXPERIMENT CONTROL SYSTEMS (1.7) PPS PLCs (1.9.9) C.F. PLCs (1.8.x) SYS. (1.3.x) CABLE RACEWAY SYSTEM (1.8.x), TYPICAL SYS. (1.5.x) CABLE PLCs CABLE SYS. (1.6.8) SYS. (1.7.x) CABLE SYS. (1.4.x) CABLE CABLE S (1.8.x) CABLE S (1.8.x) (1.9.6) PERSONNEL PROTECTION SYSTEM SENSORS &CONTROL ELEMENTS, ETC. (1.9) FRONT END SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.3) LINAC SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.4) RING SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.5) TARGET SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.6) EXPERIMENT SENSORS, CONTROL ELEMENTS, CONTROLLERS, ETC. (1.7) CONVENTIONAL FACILITIES SENSORS & CONTROL ELEMENTS, CONTROLLERS, ETC.(1.8) EQUIPMENT PROTECTION SYSTEM HARDWARE ( ) TIMING SYSTEM SLAVE HARDWARE ( )

21 Subsystem interfaces are varied and complex
Ethernet – TCP/IP Channel Access Protocol VME IOC VXI IOC PC IOC VME IOC PC IOC Negotiated Exception Examples: Cryoplant Conven. Facilities Default Interface Examples: Injector PLC Negotiated Exception Examples: LLRF Diagnostics Default Interface Examples: Beamlines Vac. Sys. PLC Default Interface Example: HPRF Embedded PLC System “Packaged” PLC System PLC Equipment Equipment Equipment Equipment PLC Equipment IOC = Input.Output Controller PLC = Programmable Logic Controller PC = Personal Computer

22 Proposed Baseline for full operations (26)
Management GL Secretary 2 Safety Eng (2) Techs (2) 4 12 Hardware Design Eng Tech Pool (7) 8 Software EPICS System Programmers (3) Application Engineers (7) Network, Sysadmin, Database (2) Total is 26* *APS is 29 for same scope

23 The exact number of IOCs depends upon Title II design.
Ethernet - TCP/IP RF System Cavity System Control System HPRF IOC ControlNet KA KB PLC KA HPRF System KA KB LLRF IOCs Power Supply KA KB LLRF IOCs KA KB (50 Channels) KA KB PLC PLC X 6 Transmitter Transmitter X 5 (125 Channels) (125 Channels) Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron Klystron 11 Cavities

24 Baseline Staffing Plan for Controls

25 Ring Straight Section Functions
Separate functions in each straight Four straights: m; 2 x 6.85 m Injection modules Two-stage collimation 3 (h=1)+1 (h=2) interchangeable RF cavities Beam-in-gap kicker Empty section for future use

26 Spallation Neutron Source Aerial/Site Plan

27 Control System Systems and Functions
Data Acquisition and Control 160 distributed Input Output Controllers with 50,000 signals Timing and Synchronization Synchronizes choppers, kickers, rf systems and beam diagnostics Time stamps all acquired data to microsecond accuracy Machine Protection Turns off beam in <20usecs for beam loss) or equipment failure Control System Network Isolated Control system network includes >20 switches System and Application Software Communications, databases, EPICS core software, “engineering applications” and the human interface Control Room Operator Consoles, Personnel Access control, network hub, computer servers, timing distribution etc


Download ppt "Welcome to SNS The Next Large EPICS Project"

Similar presentations


Ads by Google