2 2 John Clerici, P.E. Chief Environmental Consultant

3 3  Identification due diligence AAI  Protection for adjacent property releases  Protection for on-site releases Brownfield This action is now referred to as The Brownfield Act

4 4  Georgia Hazardous Site Response Act (HSRA)  Georgia Hazardous Site Reuse and Redevelopment Act (HSRRA)  Amendments HB 531 SB 277

5 5  Identified Contaminated Property in Georgia Hazardous Site Inventory sites (800 ) Non-HSI sites (1600) Mine sites (200) Petroleum sites (8,000)  Senate Bill 277

6 6 FEAR ! Superfund Liability Cost of investigation Cost of clean-up Liability civil and regulatory Regulatory changes Resale

7 7 2002 Federal Brownfields Law 1994 USEPA ID’s 600,000 + 2002 GA Brownfields Law 2003 GA HB531 Tax Relief 2005 SB 277 Petroleum Sites

8 8

9 9

10 10

11 11 Westinghouse A&D Wireburn GA Tech

12 12  Groundwater clean up is exempt  No third party liability  Exempt from regulatory changes  Protections are passed down to future owners

13 13  Purchase price is probably depressed  Property value / taxes are frozen  May be eligible for funding

14 14  Applications go thru either GA Brownfields Program Hazardous Site Response Program (HSRP)  Meet HSRP requirements*  Fees used to fund fast track review * For Petroleum releases, too

15 15 Application Public Notice Agreement Purchase Property Clean-Up File Tax Relief Certification TIMELINE

16 16 $3,000 fee PPCAP or CSR (clean-up plans) Property Qualification Purchaser Qualification Financial Assurance (thru HSRP) Application

17 17  Minimum $3,000  Money well spent Speeds up process Gets special HSRP review

18 18 Compliance Status Report (CSR) List of hazardous substances Extent of soil & groundwater impacts Certify compliance with Risk Reduction Standards (RRS) Proposed Purchaser Corrective Action Plan (PPCAP) Preliminary CSR No compliance with RRS Corrective Action Plan OR

19 19  Site has pre-existing release of hazardous substances or petroleum products  Not a waste facility (landfill)  Not on NPL  Not under federal corrective action program  No unsatisfied liens

20 20  Purchaser did not contribute to release  Not related to owner or other persons who contributed to release  Not shareholder or officer in company associated with owner or property  Not shareholder or officer in company that contributed to release  Not in violation of any environmental rule or regulation

21 21  Financial guarantee bond  Performance bond  Letter of credit  Financial statements  Trust fund  Insurance Not Required for non-HSRP voluntary clean ups

22 22  Public notification is triggered when application is submitted  Posted in local newspaper  Gives public opportunity to respond  Not Required for non-HSRP voluntary clean ups

23 23  Property acquisition must await EPD agreement  May require additional investigation  May require corrective action  Contingent upon compliance with RRS

24 24  Get EPD agreement first  Expect seller to want changes in contract

25 25  Property must be remediated according to plan described in corrective action plan  Be sure to document clean-up and costs carefully

26 26  Go to EPD with clean-up costs  Get EPD agreement  Take EPD agreement forms to County  Property value is frozen for 10 years  Property taxes are effectively frozen

27 27 Time (weeks) Cost (x$1,000) Common Timing/Cost Ranges HSRPBFPItemHSRPBFP 2 – 41 – 3PPCAP preparation4 – 102 – 6 4 – 81 – 4EPD review, with HSRP NOD or BFP comments-- 2 – 51 – 2Respond to NOD letter/comment3 – 151 – 2 2 – 61 – 3EPD letter after NOD/comment response-- 2 – 100 – 6Remediation, if required0 – 250+ 0 – 100+ 2 – 42 – 3CSR Preparation10 - 258 - 15 6 – 101 – 4EPD Review-- 2 – 51 – 3Final CSR3 – 152 – 4

28 28 CASE STUDY Aladdin Cleaners 18 th Site approved in Georgia

29 29

30 30

31 31 Property Line Groundwater contamination Soil contamination Dry Cleaners

32 32 Dry Cleaners

33 33

34 34

35 35 Application Includes:  $3,000 fee  PPCAP List of contaminants Source of release Extent of contamination Corrective Action Plan  Qualifications  Financial assurance Public Notice: Marietta Daily Journal Atlanta Journal Constitution

36 36 Required action: Monitoring Groundwater (to define conditions for indemnification) Additional sampling Soil removal and off-site disposal Bench tests (if decide to use on-site treatment) and disposal Meet RRS CSR

37 37 Septic Tank Lint Dumping Dry Cleaners

38 38 Weeks PPCAP prep3 EPD review & comments3 Response to EPD comments2 EPD letter of agreement3 Property purchase3 Clean-up6 Final CSR4 Total24 (6 mo.)

39 39 This is real ! Benefits are substantial Protection last forever Opportunities abound

40 40 Questions

41 41 HOW CAN WE HELP? JOHN CLERICI, P.E. 770-582-2819 SCOTT SMELTER, P.E. 770-582-2839