2011 Educational Facilities Master Plan Presentation to the Board of Education June 13, 2011 Harford County Public Schools Serving Youth
2
Educational Facilities Master Plan Section I: Mission, Standards, and Guidelines Educational Programs and Policies Section II: Community Analysis Growth and Demographics Information Section III: Facilities Inventory Building Assessment and Inventory of Facilities Section IV: Enrollment Projections 2010 Enrollment Projections Section V: Facility Utilization and Needs Long-Range Planning and Timeline of Capital Projects Section VI: Letters of Approval State /County Enrollment and Master Plan Approval Letters
3
Project Categories C = Capacity Projects M = Modernization Projects B = Building/Program Improvement Projects S = Site/Program Improvement Projects Evaluation of existing buildings and sites to both modernize and expand Master planning to maximize the land we own
4
Parameters For Decision Making State and Local Funding Approvals Educational Facilities Master Plan Cross-functional Steering Committee Balancing Enrollment Capacity, Infrastructure, & Program Projects
5
Status of Projects Red Pump ES - Occupancy August 2011 Homestead/Wakefield ES - Scope Study Approved by BOE John Archer School Addition - Scope Study Approved by BOE Youth’s Benefit ES - Construction Documents Complete William Paca/Old Post ES - Scope Study Approved by BOE Campus Hills ES - Construction Documents Complete Joppatowne HS - Scope Study Approved by BOE
6
Occupancy Time Changes from 2010 Plan Homestead/Wakefield ES - No Change (SY15-16) John Archer School - No Change (SY15-16) Youth’s Benefit ES - No Change (SY16-17) William Paca/Old Post ES - Change (SY16-17 to SY17-18) Campus Hills ES - Change (SY16-17 to SY18-19) Joppatowne HS - Change (SY18-19 to SY20-21)
7
FACILITIES PLANNING & MASTER PLAN 2011 Construction Timeline - Capacity, Modernization and Addition Projects FY12FY13FY14FY15FY16FY17FY18FY19FY20FY21FY22 PROJECTS - STATE/LOCAL11-1212-1313-1414-1515-1616-1717-1818-1919-2020-2121-22 Red Pump Elementary School (SRC = 696) C/O Homestead/Wakefield ES Modernization/Addition (SRC= 1029) PCCC/O John Archer School Addition at Bel Air School (SRC = 200) PCCC/O Youth's Benefit Replacement School (SRC = 1130) PCCC/O
8
FACILITIES PLANNING & MASTER PLAN 2011 Construction Timeline - Capacity, Modernization and Addition Projects FY12FY13FY14FY15FY16FY17FY18FY19FY20FY21FY22 PROJECTS - STATE/LOCAL 11-1212-1313-1414-1515-1616-1717-1818-1919-2020-2121-22 WP/OPR Elementary Replacement School (SRC = 1154) PCCC/O Campus Hills Elementary School (SRC = 696) PCC/O Joppatowne High School Comprehensive Addition & Modernization (SRC = 1475) PCCC/O
9
FACILITIES PLANNING & MASTER PLAN 2011 Construction Timeline - Capacity, Modernization and Addition Projects FY12FY13FY14FY15FY16FY17FY18FY19FY20FY21FY22 PROJECTS - STATE/LOCAL 11-1212-1313-1414-1515-1616-1717-1818-1919-2020-2121-22 Existing John Archer School Modernization/Renovation SSPCC/O New Middle School Cap = TBD SSPCC/O Riverside ES Modernization SSPCC/O Bel Air MS Modernization SSP CC/O Magnolia ES Modernization SSP C C/O GD Lisby ES Modernization SSPC WS James ES Modernization SSC Prospect Mill ES Modernization SS Aberdeen MS Modernization Abbreviation Key - SS = Scope Study, FS = State Required Feasibility Study, P = Planning and Design, C = Construction, O = Occupancy SFR = State Funding Reimbursement
10
Harford County Public Schools Serving Youth Questions & Discussion