1
Department of Water Resources Government of Orissa
2
Guidelines
3
Objective O r i s s a In stream storage. Ground Water recharge Incidental irrigation during late Khariff and Rabi by storing water at the end of monsoon mainly through lifting devices. Irrigation use of water flowing down drainage channels. Other uses like Drinking water, bathing, washing, fishing, recreation etc.
4
O r i s s a Selection Criteria Blocks having less than 35% irrigation coverage to be considered on priority. Areas where farmers are using traditional irrigation by constructing temporary cross bunds on streams. Where the farmers are willing to take up operation & maintenance of the structure. The newly constructed structure should not have any adverse impact on the hydrological efficacy of the existing, ongoing and future major, medium, minor (flow) irrigation and minor (lift) irrigation projects. In-stream storage will be developed near urban centers if suitable rivers and locations available for multipurpose domestic and irrigation use.
5
Salient Features & Types of Check Dams O r i s s a Check dams, up to a height of 2.0 mt. can be constructed across small tributaries / nallah / drainage channel within the banks and streams in middle and higher reaches (within approx. 50 mts. wide) : Low cost structures, irrigation by beneficiaries through own arrangements - lift or flow, operated by beneficiaries. Diversion weir type structure. Check dams in deltaic rivers/ drainage channel (lower reaches) (within approx 50 mts. wide) : Mostly for irrigation through lift, operated by beneficiaries. Storage across major rivers and streams having higher width and huge flood water discharge: Irrigation purpose, to be operated by Department.
6
Design Aspect O r i s s a Check dams on small streams /nallahs / drainage channel & Deltaic river: All the structures shall be designed as per standard practices for ensuring the safety & economy. Height of these structures - normally within 2.0 m. Storage arrangement through gates of wooden planks/ shutter / sand bags/ pre-stressed concrete slabs. Structures are to be constructed in series to make them more effective by storing more water for attaining their objectives. Check dams on main streams. The design of these structures shall confirm to prevailing codes & references.
7
Implementation Arrangements O r i s s a Existing field units of major & medium sector and minor irrigation sector will implement the scheme following standard extant codal procedures with following stipulations. For Small Check Dams: Percentage basis tender to be invited as per OPWD Vol-I clause 3.5.5(v). Tendering process in case of small check dams to be completed preferably within one month. In case of seriously unbalanced bids additional performance security to be deposited by agencies with the tender and to be kept from agencies during execution. On completion projects will be handed over to Pani Panchayats / farmer groups for management. Consent of farmers to be obtained before / during and after completion of the work. Separate implementation arrangements will be formulated for barrages anicuts across major streams which will be constructed, operated and maintained by the Department.
8
Operation and Maintenance O r i s s a Pani Panchayats (WUAs) should be formed by the beneficiaries of the scheme during the process of selection of site for check dams. The infrastructure once completed in all respects will immediately be handed over to Pani Panchayats (W.U.As) for its operation and maintenance. Department will provide necessary technical support. The Department responsible for execution of the scheme will supply the wooden / steel planks or sand bags once only and demonstrate the operation of putting shutters / planks / sand bags in position and their removal, transportation and maintenance in real field scenario. Contd……
9
Operation and Maintenance O r i s s a It is mandatory that the waterway of check dams constructed across stream / nallah / drainage channel etc. should be free from any obstructions / interventions made by planks / steel shutters / sand bags etc. before onset of the monsoon or later by 5 th of June every year. The Pani Panchayats (W.U.As) are responsible to install lifting arrangement for lifting water from the pond and its conveyance for equitable irrigation to users’ farms. The Pani Panchayats (W.U.As) may install and maintain pipe conduits, taps etc. and take care to make water hygienic, if the water is to be used for drinking purpose.
10
O r i s s a Monitoring Mechanism State level monitoring committee. District level monitoring committee. Department level monitoring. Contd…… Monitoring of the activities at three levels.
11
O r i s s a Monitoring Mechanism State level monitoring committee:- Chief Secretary Chairman Agricultural Production Commissioner Member Secretary, Finance DepartmentMember Secy, Revenue & Disaster Management Dept. Member Secretary, Agriculture DepartmentMember Secretary, Energy DepartmentMember Secretary, Panchayat Raj DepartmentMember Secretary, Rural Development DepartmentMember Secretary, S.T. & S.C. Dev. DepartmentMember Contd……
12
O r i s s a Monitoring Mechanism State level monitoring committee:- Secretary, Department of Water ResourcesMember Convener Engineer-in-Chief, Water ResourcesMember Engineer-in-Chief, Planning & Designs Member Chief Engineer, Minor Irrigation, BhubaneswarMember Other Govt. Officer with the permission of the Chair-Member Contd…… Meeting will be held twice within a financial year.
13
O r i s s a Monitoring Mechanism District level monitoring committee:- Collector & District Magistrate-Chairman P.D., DRDA -Member P.A., ITDA -Member Superintending Engineers concerned -Member E.E. Irrigation Divn. concerned - Member District Agricultural Officer -Member Soil Conservation Officer -Member Horticulturist concerned-Member E.E., Minor Irrigation concerned-Member Convener Monitoring committees will be notified by DoWR Meeting will be held once in every quarter of each financial year. Contd……
14
O r i s s a Monitoring Mechanism Department level monitoring:- To be monitored by the Director, M&E, O/o the Engineer-in- Chief, Water Resources. The CE&BMs / CEs / CCEs will furnish Monthly Progress Reports during the 1 st week of each month preferably transmitted electronically. The Director M&E will prepare a consolidated progress report and furnish it to DoWR under intimation to all the Chief Engineers and Basin Managers / Chief Engineers and Engineer- in-Chiefs. Day to day progress will be monitored by the regular monitoring arrangements of the department.
15
IN STREAM STORAGE STRUCTURE WILL HAVE Instream structures (Low height) store water within banks Low height pier to support gates Gates at bed level to release flood water & flush silt in rainy season High floods to spill over piers Gate/closure will be removed up before 1st June to release flood Gate will be kept in place by 15th October to store water
16
DISTRICT-WISE STATUS OF CHECK DAMS Contd… Sl. No District District A/A Accorded Status of Check Dams No of applicati ons received No Cost in lakh rupees Ayacut in ha Taken up CompletedProgress Tender invited 12345678910 1Angul20140.1227514-146120 2Balasore1621401.81273874601417175 3Bargarh1641602.253485621349111233 4Bhadrak1162.93230862524 5Bolangir1031088.84204384265839300 6Boudh1021206.4814642762140151 7Cuttack121876.061905575256490 8Deogarh46376.0671142882020300 9Dhenkanal72566.44130558223614143 10Gajapati2086.64254---17103
17
Contd… Sl. No District District A/A Accorded Status of Check Dams No of applicati ons received No Cost in lakh rupees Ayacut in ha Taken up CompletedProgress Tender invited 12345678 910 11Ganjam1101127.67148828111738126 12Jagatsinghpur-------- 13Jajpur33223.99365281414578 14Jharsuguda24179.43323201645224 15Kalahandi1671296.36233751143753304 16Kandhamal40360.86425---22130 17Kendrapara-------- 18Keonjhar1321574.862577391722102346 19Khurda90822.951052308226156 20Koraput51479.278182642215136 DISTRICT-WISE STATUS OF CHECK DAMS
18
Sl. No District District A/A Accorded Status of Check Dams No of applicat ions received No Cost in lakh rupees Ayacut in ha Taken up Compl eted Progress Tender invited 12345678910 21Malkangiri1087.911165-5-10 22Mayurbhanj1561316.352747121378442404 23Nabarangpur43462.546424113286100 24Nayagarh105798.51167048222637120 25Nuapada1441280.462294302010129132 26Puri---44--- 27Rayagada102685.2212453963361545 28Sambalpur105775.23125180275337500 29Sonepur32457.9061229722954 30Sundargarh1792069.17325354203428244 Grand Total 234421406.433762510854336529285248 DISTRICT-WISE STATUS OF CHECK DAMS
19
Check Dam in different stages Benkera Check Dam, Bolangir Dist.
20
Benkera Check Dam in different stages Benkera Check Dam, Bolangir Dist.
21
Check Dams closed by Sand Bags
22
Check Dam in Khurda District
23
Check Dams in GUJARAT & MAHARASTRA
24
UKARDA CHECK DAM-I ACROSS RIVER AJI IN RAJKOT DISTRICT
25
UKARDA CHECK DAM-II ACROSS RIVER AJI IN RAJKOT DISTRICT
26
CAUSEWAY-CUM-CHECK DAM ACROSS RIVER HIRAN AT VILLAGE TALALA OF JUNAGARH DISTRICT.
27
SERIES OF CHECK DAMS ACROSS RIVER HIRAN OF JUNAGARH DISTRICT.
29
BIG CHECK DAM ACROSS RIVER BHADAR NEAR UPLETA IN RAJKOT DIST.
31
CKECK DAMS AT DIST-KOLHAPUR, MAHARASTRA
35
CKECK DAM CONSTRUCTED BY FARMERS
36
CKECK DAMS AT DIST-KOLHAPUR, MAHARASTRA
37
Modified Check Dams ( to Close the Vents Permanently for a height of 0.6 m).
38
Check Dam at Haja, Khurda
39
Check Dam in Keonjhar District
46
Check Dam at Haja, Khurda
47
Check Dams in Hilly terrain/ KBK Areas
49
Dumda-ambaCheck Dam in Rayagada
50
Checkdam at Chitinala Jeeba in Operation (Gumma Block, Gajapati District)
51
SEMELPALLI CHECK DAM IN BOLANGIR DISTRICT
52
BHUTIARBAHAL CHECK DAM IN BOLANGIR BLOCK
53
KAKHAL CHECK DAM IN BOLANGIR BLOCK
54
JHANKARPALI CHECK DAM IN BOLANGIR BLOCK
55
Rinbachan- II CD at Bolangir Block
56
KAPANI CHECK DAM IN BELPADA BLOCK OF BOLANGIR DISTRICT
57
TALBAHALI CHECK DAM IN TITILAGARH BLOCK OF BOLANGIR DISTRICT
58
Benkera CD at Khaprakhol Block of Bolangir District
59
CHAULDIA CHECK DAM IN KHAPRAKHOL BLOCK OF BOLANGIR DISTRICT
60
TELENPALI CHECK DAM IN KHAPRAKHOL BLOCK OF BOLANGIR DISTRICT
61
Khomekotenala Check Dam in Nilagiri Block of Balasore District
62
JHITRITODA NALLA Block- Khariar, Dist- Nuapada
63
ROHINIPADAR NALLA-I Block- Khariar, Dist- Nuapada
64
Tumbarla Check Dam in Nabarangpur
65
) Check dam on Baijhalnala, Debadala ( Gajapati District)
66
KALKALI NALLA-II Block- Boden, Dist- Nuapada
67
KALKALI NALLA-III Block- Boden, Dist- Nuapada
68
ALAT NALLA-I CHECK DAM IN BODEN BLOCK OF NUAPADA DISTRICT
69
CHECK DAM AT DHATIKA ACROS SANAMACHAKANDANA NALLA IN KEONJHAR DISTRICT
70
CHECK DAM AT BAMPARACROSS ARADEI NALLA IN KEONJHAR DISTRICT
71
Photographs of Check Dams in Plain terrain.
72
BARUNEINALA CHECK DAM IN BALASORE DISTRICT
73
GANDIBEDNALA CHECK DAM IN BALASORE DISTRICT
74
HARISILA CHECK DAM-I IN BALASORE DISTRICT
75
DANDAKALI CHECK DAM-2 IN BALASORE DISTRICT
76
Badajorenalla Check Dam in Gondia Block of Dhenkanal District
77
Bhadalia Check Dam-II in Gondia Block of Dhenkanal District
78
Ghodadian Check Dam in Parjang Block of Dhenkanal District
79
Rangathalinala Check Dam in Parjang Block of Dhenkanal District
80
Biripadar Ckeck Dam in Bhanjanagar Block of Ganjam District
81
Gadagadianala Nimina Ckeck Dam in Polasara Block of Ganjam District
82
Gadagadianala Nimina Ckeck Dam-II in Polasara Block of Ganjam District
84
Pua- I CD at Tarva Block in Sonepur District
85
Pua-II CD at Tarva Block in Sonepur District
86
Convergence with PR A joint workshop at District ( EE, MI as N.O) Sharing of Design and Technical details Listing of feasible sites( < 10 M for PR). Applications recd can be distributed. Exposure visit for concern block officials ( visit to check dam sites). Squads at district for quality checking. Monitoring in Dist. Meetings. Converging Agri and Horti activities/ demonstration Model blocks.
87
87 All the water that will ever be is, right now. National Geographic
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.