2 Civil Works Baltimore District River and Harbor Projects

3 SEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCT FY07 FY06 FY08 Hopper Dredge Maintenance Dredging Baltimore Harbor & Channels, VA - Cape Henry/York Spit 400 KCY Sea Turtles - Screens and Observers Page 1 of 1 Scheduled FY07 Dredging Work in Baltimore District Sea Turtles Atlantic Coast of Maryland, MD & DE Award Apr 13, 06 850 KCY Tourism

4 PROJECT: Atlantic Coast of MD TYPE WORK: Renourishment QUANTITY: 800,000 cy TYPE OF MATERIAL: Sand BORROW AREA: 9 NOURISHMENT AREAS: 33 rd Street and north of 60 th Street DISTANCE FROM BORROW TO BEACH: 3-7 Miles TYPE OF EQUIPMENT: Hopper SMALL BUSINESS SET ASIDE: No LAST NOURISHED: 2002 ENVIRONMENTAL WINDOW: Sep 7 – Jun 30 REASON FOR WINDOW: Tourism ADVERTISING: Feb 28, 2006 BID OPENING: Mar 31, 2006 AWARD: Apr 13, 2006 CONTRACT: $6,674,769.25 CONTRACTOR: Weeks Marine

5

6 Ocean City, Maryland, Looking North from Ocean City Inlet

7 Ocean City, Maryland, Looking North

8 Erosion at 70 th – 79 th Street

9 Atlantic Coast of Maryland Renourishment

10 PROJECT: Baltimore Harbor & Channels, VA - Cape Henry & York Spit Channels TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 1,000 and 800 Feet LENGTH: 3 and 18 Miles QUANTITY: 400,000 cy TYPE OF MATERIAL: Sand PLACEMENT AREAS: Dam Neck Ocean and Wolf Trap Alternate DIST. TO PLACE. AREA: 7 Mi TYPE OF EQUIPMENT: Hopper SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2006/2004 ENVIRONMENTAL WINDOW: Dec 1 – Mar 31 REASON FOR WINDOW: Sea Turtles FY 07 FUNDING: $1,500,000 ADVERTISING DATE: Dec 06 BID OPENING DATE: Jan 07 AWARD DATE: Jan 07

11 SEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCT FY07 FY06 FY08 Hydraulic Pipeline Dredge Maintenance Dredging Wicomico River, MD Awarded July 25, 2006 Anadromous Fish Page 1 of 1 Scheduled FY07 Dredging Work in Baltimore District 43 KCY Oysters Tilghman Island Harbor, MD Awarded Sep 29, 2006 11 KCY 99 KCY Knapps Narrows, MD Awarded Sep 29, 2006 Poplar Island, MD 900 KCY Oysters

12 PROJECT: Wicomico River, MD TYPE WORK: Maintenance DEPTH: 14 Ft. WIDTH: 150 Ft. LENGTH: 10 miles. QUANTITY: 99,000 c.y. TYPE OF MATERIAL: Silt/Clay PLACEMENT AREA: Upland DISTANCE TO PLACEMENT AREA: 1-2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: Yes LAST DREDGED: 2005, 2000, 1998 ENVIRONMENTAL WINDOW: June 16 – February 14 REASON FOR WINDOW: Anadromous fish spawning FY 07 FUNDING: $800,000 ADVERTISING DATE: May 5, 2006 BID OPENING DATE: June 13, 2006 AWARD DATE: July 25, 2006 CONTRACT: $368,750 (Base only) $1,444,271 (Options) CONTRACTOR: Cottrell Contracting Corp.

13 PROJECT: Knapps Narrows, MD TYPE WORK: Maintenance DEPTH: 9 Ft. WIDTH: 75 Ft. LENGTH: 9,000 Ft. QUANTITY: 43,000 c.y. TYPE OF MATERIAL: Sand/Silt/Clay PLACEMENT AREA: Wetland Creation, Shoreline Stabilization DISTANCE TO PLACEMENT AREA: 1-2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: Yes LAST DREDGED: 2000 ENVIRONMENTAL WINDOW: October1- December 15, March 15 - June 1 REASON FOR WINDOW: Oysters REQUEST FOR PROPOSAL: Sep 7, 2006 PROPOSAL DUE: Sep 20, 2006 AWARD: Sep 29, 2006 CONTRACT: $850,000 CONTRACTOR: Coleman Construction

14 Knapps Narrows Placement Site

15 2000 Shoreline Placement Site Knapps Narrows West End

16 PROJECT: Tilghman Island Harbor, MD TYPE WORK: Maintenance DEPTH: 6 Ft. WIDTH: 60 Ft., Basin 500 x 200 Ft. LENGTH: 2,080 Ft. QUANTITY: 11,000 c.y. TYPE OF MATERIAL: Silts/clay/sand PLACEMENT AREA: Wetland Creation, Shoreline Stabilization DISTANCE TO PLACEMENT AREA: 2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: Yes LAST DREDGED: 1996 ENVIRONMENTAL WINDOW: October 1 - June 1 REASON FOR WINDOW: Oysters FY 07 FUNDING: $0 REQUEST FOR PROPOSAL: Sep 7, 2006 PROPOSAL DUE: Sep 20, 2006 AWARD: Sep 29, 2006 CONTRACT: $500,000 CONTRACTOR: Coleman Construction

17 Tilghman Island Harbor Placement Site

18 Poplar Island Environmental Restoration Project

19 PROJECT: Poplar Island Environmental Restoration, Cell 6 Closure, MD TYPE WORK: New Work/Construction DEPTH: 25 Ft. WIDTH: 400 Ft.. LENGTH: 4,300 Ft QUANTITY: 900,000 c.y. TYPE OF MATERIAL: Sand STOCKPILE AREA: Cell 4 DISTANCE TO STOCKPILE AREA: 1-2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2006 to 15-20 Ft ENVIRONMENTAL WINDOW: January 1 – December 31 REASON FOR WINDOW: N/A FY 07 FUNDING: $6,000,000 ADVERTISING DATE: Dec 06 BID OPENING DATE: Jan 07 AWARD DATE: Feb 07

20 SEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCT FY07 FY06 FY08 Mechanical Dredge Maintenance Dredging Baltimore Harbor & Channels (Awarded August 23, 2006) 2.0 MCY Drying at Poplar Island Page 1 of 1 Scheduled FY07 Dredging Work in Baltimore District Baltimore Harbor & Channels 2.5 MCY Drying at Poplar & Hart-Miller Seagirt Marine Terminal Masonville DMCF State of Maryland New Work 3.0 MCY 1.5 MCY

21 PROJECT: Baltimore Harbor & Channels, MD TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 400 - 800 Feet LENGTH: 10 – 15 Miles QUANTITY: 2,000,000 cy TYPE OF MATERIAL: Silt and clay PLACEMENT AREAS: Poplar Island Environmental Restoration Project DIST. TO PLACE. AREA: 20 -30 Miles TYPE OF EQUIPMENT: Clamshell SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2000 - 2005 ENVIRONMENTAL WINDOW: Dec 1 – July 31, Sep 1 – Mar 31 REASON FOR WINDOW: Sturgeon, Dredged Material Drying FY 07 FUNDING: $18,500,000 ADVERTISING DATE: Jun 30, 2006 BID OPENING DATE: Aug 1, 2006 AWARD DATE: Aug 23, 2006 CONTRACT AMOUNT: $18,834,200 CONTRACTOR: Great Lakes Dredge & Dock Co.

22 PROJECT: Baltimore Harbor & Channels, MD TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 400 - 800 Feet LENGTH: 10 – 15 Miles QUANTITY: 2,500,000 cy TYPE OF MATERIAL: Silt and clay PLACEMENT AREAS: Poplar Island and Hart-Miller Island DIST. TO PLACE. AREA: 20 -30 Miles TYPE OF EQUIPMENT: Clamshell SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2000 - 2006 ENVIRONMENTAL WINDOW: Dec 1 – July 31, Sep 1 – Mar 31 REASON FOR WINDOW: Sturgeon, Dredged Material Drying FY 07 FUNDING: $300,000 ADVERTISING DATE: May 2007 BID OPENING DATE: Jun 2007 AWARD DATE: Jun 2007

23 Existing Dredged Material Placement Sites

24 HART-MILLER ISLAND CONTAINMENT FACILITY

25 Poplar Island Environmental Restoration Project

26 Port of Baltimore Seagirt Marine Terminal Proposed Masonville DMCF

27 Seagirt Marine Terminal

28 Masonville Dredged Material Containment Facility

29 SEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCT FY07 FY06 FY08 Corps Dredge Currituck Assateague Island 90 KCY Page 1 of 1 Scheduled FY06 Dredging Work in Baltimore District 90 KCY

30 Assateague Island Restoration

31 Ocean City Inlet Looking West

32 Assateague Island, Looking North

33 USACE Dredge CURRITUCK Depositing Sand in Surf Zone Off Assateague Island

34 Maryland Port Administration’s Seagirt Marine Terminal