1
N.C. Department of Transportation Southeastern Rail Highway Safety Conference Presented by Michael J. Shumsky, P.E. NS/CSXT Mainline Grade Separation November 8, 2012
3
Reduces conflicts/improves efficiency between freight and passenger trains at NC’s busiest at-grade highway/railroad intersection Grade separates Main Line tracks of Norfolk Southern, CSXT and NS O-Line/future Red Line Corridor Replaces multiple at-grade highway/railroad crossings with bridges over the railroad Enhances safety, reduces noise and increases railroad operating efficiency – improves the environment and local quality of life NS/CSXT Mainline Grade Separation Charlotte Railroad Improvement & Safety Program
5
Places CSXT tracks in trench below NS, CATS North Corridor Relocates CSXT Tryon Yard CSXT, NS and ADM Mill (all remain operational during construction) Current Anticipated 2037 NS3456 CSXT1425 Amtrak220 Total50101 Number of Trains Crossing Diamonds NS/CSXT Mainline Grade Separation Charlotte Railroad Improvement & Safety Program
6
NS/CSXT Mainline Grade Separation
7
Norfolk Southern/CSXT Intersection County Fleet Facility NC Music Factory Elmwood Cemetery CSXT Norfolk Southern Proposed area roadway improvements
8
Mecklenburg County VMF (Proposed Maxwell Court Extension)
9
Adjacent to CSXT Corridor, looking west Pinewood/Elmwood Cemetery
13
Looking west CSXT Corridor
14
Looking east along CSXT Seaboard Street Historic District
15
Soil Boring Plan
17
Over 300 million pounds of flour delivered to NC/SC bakeries each year. Capacity of 1.3 million lbs. of flour every 24 hours. Operates 24/7/365 50,000 tons of mill feed delivered to NC feed mills for cattle, pork and poultry. “Just in Time” Delivery $1M annual electric bill ADM Current Operations
18
Flour and byproduct loading Wheat unloading (rail and truck) General circulation Minimizing “downtime” Impacts to Duke Energy substation and adjacent switchgear. Construction impacts to nearby structures (i.e. Elevator “C”) Emergency Access ADM Areas of Concern
19
NS/CSXT Mainline Grade Separation
20
Secant Pile Wall Construction
21
Construction$110,140,985 Right of Way$10,230,000 PD&A$6,377,716 Total$126,748,701 Cost Estimate (March 2012)
22
Milestone Dates April 2017 Completion Date November 2014 Project Let February 2013 R/W Plans November 2012 65% Plans