1 RESTRUCTURED APDRP-II IN XI PLAN Scope of Part - B : Strengthening of Distribution System. Fund Allocation of Part - B: Proposed fund allocation Rs 40,000 Cr.
2
2 Steps for Preparation of DPR Collection of data Physical, Loading, Losses, Voltages Computerise Data Validate Data Benchmark Performance Parameters Prioritise feeders/DTs Group feeders for Optimisation Contd…
3
3 Evaluate options R&M, Augmentation, New Work Cost benefit analysis Prioritise & Shortlist Finalisation of DPR & submission to nodal agencies Steps for Preparation of DPR
4
4 Contents of DPR 1.Executive Summary Introduction Objective Scope & Cost Estimate Benefits Implementation Schedule Payback Period
5
5 Contents of DPR 2.Town/circle profile & organization setup Consumers profile Existing distribution system with sources of supply Details of sub stations, feeders, DTs with electrical and physical boundaries etc. History of Load growth & Consumer growth Power and energy flow details Metering details at all voltage levels HT/LT Ratio Organisation Setup
6
6 Contents of DPR 3.Commercial performance Billing details Input Energy Billed Energy Revenue Billed Revenue Realised T&D and AT&C losses Feeder outage and reliability index Power & Distribution transformer failure rate
7
7 Contents of DPR 4.Constraints & Difficulties in the existing system Adequacy of EHV transformation capacity for supply of power Adequacy of Sub Transmission capacity at 66kV or 33 kV level sub stations Overloading of 66kV or 33 kV, 11 kV and 440 volts feeder Overloading of distribution transformers
8
8 Contents of DPR 5. Scope of R&M works for Existing Sub station Feeders (including reconductoring, Bifurcation, Segregation, Conversion to under ground cable, Conversion to Arial Bunch Cable (ABC) etc. Distribution Transformers Service connection
9
9 Contents of DPR 6.Scope of New Works for New Sub station New Feeders High Voltage Distribution System (HVDS) New DTs Capacitor bank - HT & LT New Service connection
10
10 7.Project Implementation schedule Schedule for NIT,OBD & LOA. Schedule for Project Execution Contents of DPR
11
11 COST BENEFIT ANALYSIS Estimated cost of the scheme Increase in annual revenue due to oIncreased energy consumption (Load growth) oReduction in technical losses oReduction of commercial losses Total annual benefit Payback period Contents of DPR
12
12 Bench marks of performance (Yearly) SlBenchmark ParameterPresent Level Level to be achieved Date by which parameter would be achieved a)Metering efficiency (Input Vs. metered energy) b)Collection efficiency (amount collected to amount billed) c)Transmission & Distribution losses d)DT Failure rate e)Number of feeder outages f)Period of feeder outages g)Reliability Index h)Number of consumer complaints i)Consumer complaint disposal time k)AT&C Loss Contents of DPR