3 About the plant 4-unit station with a total output of 3,524 megawatts (MW) 20 per cent of Ontario’s electricity  Tritium Removal Facility  extracts tritium from heavy water

4 COMPONENTS AND EQUIPMENT Electrical and I&C Major Components Mech & Rotating Equipment Valves

5 Major Components Fans Compressors Pumps Steam Generators (Boilers) Feeders Reactor Maintenance

6 Inside the plant… Main Boiler Feed Pump Turbine Hall

7 Projects Critical equipment and Critical spares List Root cause analysis of the seal failure Transient monitoring for Feeders Plant walk-down

8 Transient monitoring for Feeders CNSC  Keep track of transient events that have occurred in each unit. – For all nuclear class system piping Plant Information System (PI) – Temperature, pressure, %Power, etc. for all planned and forced outages

9 Feeder thinning reduction in pipe wall thickness of the outlet feeders High pH  dissolves pipes; reduces thickness The cause of feeder thinning is flow accelerated corrosion (FAC). – poor design defects, poor chemistry controls and high temperature and pressure.

10 Face of the CANDU reactor The face of a CANDU reactor (under construction). Some feeder pipes can be seen to the right of the reactor face.

11 Flow Accelerated Corrosion (FAC) motion of a corrosive fluid and a metal surface. Outlet feeders – Dissolution of magnetite (Fe3O4) Affects carbon steel components – High flow and specific water chemistry conditions. – Resulted in excessive thinning and failure of feedwater lines

12 Reduce thinning Outlet feeders – Injected by Titanium Dioxide  Uniform coating inside pipe to reduce thickness  Fe3O4  Dissolves with high temperature and pressure (pH >10.6) Chemistry: pH 10.1- 10.4  rate of solubility is low

13 Feeder Integrity Project The Project is actively pursuing means to: – Extend the life of the feeders – Developing tooling for eventual feeder replacement – Further developing pipe inspection techniques

14 Root Cause Evaluation Second Stage Reheat Pumps – Seal temperature was high above the alarm set point Perform a failure modes analysis of the historical seal failures Review modification packages and make changes to design – Identify technical and human performance related root cause