Presentation is loading. Please wait.

Presentation is loading. Please wait.

11-1 ELC 347 project management Week 12. 11-2 Agenda Integrative Project –4 th part due –Outline of deliverables (posted in WebCT)Outline of deliverables.

Similar presentations


Presentation on theme: "11-1 ELC 347 project management Week 12. 11-2 Agenda Integrative Project –4 th part due –Outline of deliverables (posted in WebCT)Outline of deliverables."— Presentation transcript:

1 11-1 ELC 347 project management Week 12

2 11-2 Agenda Integrative Project –4 th part due –Outline of deliverables (posted in WebCT)Outline of deliverables (posted in WebCT) Quiz 2 Corrected –More effort wouldn’t hurt Today we will discuss Critical Chain Project Scheduling

3 11-3 Schedule for the final few Days Nov 28 –Assignment 5 due Nov 30 –IP part 5 due –Discussion on resource Leveling (Chap 12) Dec 7 –IP part 6 Due (will be corrected and returned within 24 hours) –Quiz 3 Assigned (Chap 10, 11, 12, & 13) –Discussion on Project Evaluation and Control (chap 13) Dec 8 @ Midnight –Resubmission of IP part 1 – 5 deadline Dec 11 @ 10 AM –IP project (complete) due –Resubmission of Part 6 –IP project Presentation Dec 15 @ noon –Quiz 3 Due One less quiz and 2 less assignments then was identified in syllabus

4 11-4 Course Grading Rubric Exams (3 @ 12% each)36% Assignments (5 @ 7% each)35% IP Project19% Pre-professional Conduct10% Total100%

5 11-5 Critical Chain Project Scheduling Chapter 11 © 2007 Pearson Education

6 11-6

7 11-7 BAE Systems http://www.baesystems.com/

8 11-8 Theory of Constraints & Critical Chain Project Scheduling A constraint limits system output. The Goal – Goldratt TOC Methodology 1.Identify the constraint 2.Exploit the constraint 3.Subordinate the system 4.Elevate the constraint 5.Repeat the process

9 11-9 Dr J Edwards Deming

10 11-10 Variation Common Cause Inherent in the system Special Cause Due to a special circumstance Managers should Understand the difference between the two Not adjust the process if variation is common cause Not include special cause variation in risk simulation Not aggregate discrete project risks

11 11-11 CCPM and the Causes of Project Delay How safety is added to project activities 1.Individual activities overestimated 2.Project manager safety margin 3.Anticipating expected cuts from management time 25% 50% 80% 90% Gaussian Distribution

12 11-12 Wasting Extra Safety Margin 1.The Student Syndrome a.Immediate deadlines b.Padded estimates c.High demand 2.Failure to pass along positive variation a.Other tasks b.Overestimation penalty c.Perfectionism 3.Multitasking 4.Path Merging

13 11-13

14 11-14 Critical Chain Solutions  Central Limit Theorem  Standard deviation of the sum is less than the sum of the standard deviations!  Aggregating risk leads to reduced risk  Activity durations estimated at 50% level  Buffer reapplied at project level –Goldratt rule of thumb (50%) –Newbold formula (2σ)  Feeder buffers for non-critical paths

15 11-15

16 11-16 CCPM Changes  Due dates & milestones eliminated  Realistic estimates – 50% level not 90%  “No blame” culture  Subcontractor deliveries & work scheduled ES  Non critical activities scheduled LS  Factor the effects of resource contention  Critical chain usually not the critical path  Solve resource conflicts with minimal disruption

17 11-17

18 11-18

19 11-19

20 11-20 Critical Chain Solutions Bob Feeder Buffer Project Buffer Bob Buffers protect constraints and prevent delays

21 11-21

22 11-22 Critical Chain Project Portfolios Drum – system-wide constraint that sets the beat for the firm’s throughput Drum – person, department, policy, resource Capacity constraint buffer – safety margin between projects Drum buffer – extra safety before the constraint

23 11-23 Applying CCPM to Project Portfolios 1.Identify the drum 2.Exploit the drum a.Prepare a schedule for each project b.Determine priority for the drum c.Create the drum schedule 3.Subordinate the project schedules (next slide) 4.Elevate the capacity of the drum 5.Go back to step 2

24 11-24 Subordinating Project Schedules Schedule projects based on drum Designate critical chain Insert capacity constraint buffers Resolve any conflicts Insert drum buffers so the constraint is not starved

25 11-25

26 11-26 CCPM Critiques  No milestones used  Not significantly different from PERT  Unproven at the portfolio level  Anecdotal support only  Incomplete solution  Overestimation of activity duration padding  Cultural changes unattainable

27 11-27 Problems on 373 Assignment 5 –Problems 1,2,3 4 & 5 on page 373 & 373 Pert to CCPM –Figure total Duration –Take 50% activity duration Figure new total duration –Project buffer = 50%(old –new) –If you have non critical path critical Change to Late start Feeder buffer is 50% of slack on non –critical path


Download ppt "11-1 ELC 347 project management Week 12. 11-2 Agenda Integrative Project –4 th part due –Outline of deliverables (posted in WebCT)Outline of deliverables."

Similar presentations


Ads by Google