Download presentation
Presentation is loading. Please wait.
Published byRosemary Butler Modified over 9 years ago
1
Areva Resources Canada Inc. Midwest Project Presentation to Engineering consulting firms Vincent Lanièce, Director of Project Development September 2006 AREVA Resources Canada Inc.
2
> Titre de la présentation - Date - Références - 2 > Midwest project – presentation to Engineering consulting firms, Sept 2006 2 Areva Resources Canada Inc. Midwest location
3
> Titre de la présentation - Date - Références - 3 > Midwest project – presentation to Engineering consulting firms, Sept 2006 3 Areva Resources Canada Inc. Midwest site picture
4
> Titre de la présentation - Date - Références - 4 > Midwest project – presentation to Engineering consulting firms, Sept 2006 4 Areva Resources Canada Inc. Midwest Project and overall schedule The Midwest project is divided in 4 parts 1. Mining (Open Pit) – done internally 2. Transportation (dedicated haul road) – done with local consultants/contractors 3. Midwest water treatment system – looking for EPCM 4. Milling - Midwest expansion Project (Increase the JEB Mill production from 12 to 16 Mlbs/y U 3 O 8 ) – looking for feasibility study Key dates Mine: dam and dewatering of Mink Arm starts in summer 2007 – mine stripping starting in Apr 2008 Water treatment plant, pipeline, road and power line: operational for Apr 2008 Mill modifications: in production by Nov 2009
5
> Titre de la présentation - Date - Références - 5 > Midwest project – presentation to Engineering consulting firms, Sept 2006 5 Areva Resources Canada Inc. Preliminary Midwest site layout
6
> Titre de la présentation - Date - Références - 6 > Midwest project – presentation to Engineering consulting firms, Sept 2006 6 Areva Resources Canada Inc. Midwest and McClean road connection
7
> Titre de la présentation - Date - Références - 7 > Midwest project – presentation to Engineering consulting firms, Sept 2006 7 Areva Resources Canada Inc. Preliminary 3D picture of mill expansion Tailings Neutralization Solution Shipping Oxygen Plant Ore Receiving CCC Grinding Circuit Neutral Thickener Yellowcake Storage Molybdenum Recovery SX Addition Midwest WTP cancelled – located at Midwest
8
> Titre de la présentation - Date - Références - 8 > Midwest project – presentation to Engineering consulting firms, Sept 2006 8 Areva Resources Canada Inc. 2 services requested from Engineering firm 1. Midwest water treatment plant system: Detailed Engineering, Procurement and Construction Management 2. McClean Lake JEB mill expansion: Feasibility Study, including detailed cost estimate and level 1 schedule
9
> Titre de la présentation - Date - Références - 9 > Midwest project – presentation to Engineering consulting firms, Sept 2006 9 Areva Resources Canada Inc. Midwest water treatment plant “System” - overview Need to treat water, 25,000m3/day expected, released to the McClean Lake effluent system called “Sink reservoir” (20 km distant). Current process contemplates: Combination of membranes and conventional water treatment plants, with the treated water quality greater than the Sask Surface Water Quality Objectives (SSWQO) Single wall pipe (20 km long) that would carry the treated water from Midwest to Sink Reservoir
10
> Titre de la présentation - Date - Références - 10 > Midwest project – presentation to Engineering consulting firms, Sept 2006 10 Areva Resources Canada Inc. Midwest water treatment plant “System” – Engineering status Feasibility study in progress, including flow sheets, P&IDs, detailed cost estimate The feasibility report should be available by end of November 2006 and will be used as the basis to tender the EPCM portion Note that the Procurement of the EPCM will be supervised by the Areva Resources Project Contract Manager Time line short (schedule driven project) as we need to use the 2007 fall season to start construction System in operation (including commissioning) by early April 2008
11
> Titre de la présentation - Date - Références - 11 > Midwest project – presentation to Engineering consulting firms, Sept 2006 11 Areva Resources Canada Inc. Midwest Mill expansion - description McClean Lake uranium mill (called “JEB”) currently expanded from 8 to 12 Mlbs/year – should be in operation by 1 st quarter 2007 JEB expansion to mill Midwest ore: increase of annual production from 12 to 16 Mlbs contemplated, in operation by Nov 2009 Expansion scope described in the next slides
12
> Titre de la présentation - Date - Références - 12 > Midwest project – presentation to Engineering consulting firms, Sept 2006 12 Areva Resources Canada Inc. Mill expansion Project scope 16 Mlbs (1/4) Ore receiving: Existing ore pad large enough to receive additional MW ore. Grinding: Capacity OK. Pulp Density: An additional neutral thickener will increase the density up to 50% solid. Pulp Storage: One additional pulp pachuca required Leaching: 3 rd leach circuit located in current tailings neutralization vault O 2 used as the oxydant with mild pressure leaching (2 bars in average)
13
> Titre de la présentation - Date - Références - 13 > Midwest project – presentation to Engineering consulting firms, Sept 2006 13 Areva Resources Canada Inc. Mill expansion Project scope 16 Mlbs (2/4) CCC-CCD: No modifications anticipated Clarification: 1 additional sand filter required Pregnant aqueous storage capacity fine Solvent extraction: New extraction circuit (cells available recovered from other uranium mill) Current extraction cells used as Arsenic scrub and water wash cells Stripping and regeneration are OK. Mo, Ni and Co recovery circuits: Assessing potential process and cost/benefit analysis in progress
14
> Titre de la présentation - Date - Références - 14 > Midwest project – presentation to Engineering consulting firms, Sept 2006 14 Areva Resources Canada Inc. Mill expansion Project scope 16 Mlbs (3/4) YC precipitation: Addition of a second centrifuge and barren strip solution sand filter Calcining/Packaging: Addition of a yellow cake drum storage area (report currently exists) Tailings Neutralization: New circuit – 2 mix tanks followed by 3 tailings neutralization tanks Mill Water Treatment Plant: No change Ferric Sulphate Plant: Addition of a 3 rd reactor, ferric sulphate storage tank and iron ore pad to expand
15
> Titre de la présentation - Date - Références - 15 > Midwest project – presentation to Engineering consulting firms, Sept 2006 15 Areva Resources Canada Inc. Mill expansion Project scope 16 Mlbs (4/4) Acid Plant: Upgrade of the plant from 150 to 285 t/d H 2 SO 4 (acid strength of 100%) Reagents: Additional lime slurry storage Additional ammonia storage tank Ammonium Sulphate Crystallisation: No change Utilities: No change Electrical Substation: No change
16
> Titre de la présentation - Date - Références - 16 > Midwest project – presentation to Engineering consulting firms, Sept 2006 16 Areva Resources Canada Inc. Midwest Mill expansion – Engineering status Pre-feasibility in progress, done internally Pre-feasibility report available by end of November 2006 – it will be the basis for tendering the feasibility study
17
> Titre de la présentation - Date - Références - 17 > Midwest project – presentation to Engineering consulting firms, Sept 2006 17 Areva Resources Canada Inc. Project organization Engineering consulting firm in charge of design, cost estimate, schedule Areva resources Canada Inc. bringing input and in charge of review Procurement/Contracting: strong interface with Areva Resources Contract Manager Very close and efficient relation expected
18
> Titre de la présentation - Date - Références - 18 > Midwest project – presentation to Engineering consulting firms, Sept 2006 18 Areva Resources Canada Inc. Key assets expected from Consulting firm Engineering team based in Saskatoon, Saskatchewan so that the design control can be done efficiently Experienced Engineers and project Manager during the entire life of the project with very limited turn-over Quality system in place Good understanding of the Uranium/Nuclear industry Documents and Project cost tracking system available Tenders submitted in December 2006 with decision made in January and start of work early February 2006
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.